Extension of Field Life on UKCS - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Extension of Field Life on UKCS

Description:

C. Cranfield, A. Carr & J. Webber Field Development & Approvals Background The prize Key messages Strategies Success factors View of the future UKCS is maturing ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 22
Provided by: CCran1
Category:
Tags: ukcs | extension | field | life

less

Transcript and Presenter's Notes

Title: Extension of Field Life on UKCS


1
Extension of Field Life on UKCS
  • C. Cranfield, A. Carr J. Webber
  • Field Development Approvals

2
Outline
  • Background
  • The prize
  • Key messages
  • Strategies
  • Success factors
  • View of the future

3
Background
  • UKCS is maturing
  • Diminishing reserves in producing fields
  • Reducing size of discoveries
  • Strategies are evolving
  • DTI role is to ensure all options are examined
  • Study scope for extending field life
  • Promote success factors

4
Size of UKCS discoveries
5
UK total remaining resource
6
Developed Discovered undeveloped Reserves
BBOE
7
(No Transcript)
8
(No Transcript)
9
Do nothing - Proven Probable alone
DTI targets
Target set by Task Force
10
Upside - Proven Probable Possible
6
5
4
Target set by Task Force
MMBOE/D
3
2
1
0
2000
2002
2004
2006
2008
2010
2012
2014
11
Key messages
  • Reserves growth in existing fields extremely
    important
  • Action over next few years is critical
  • Action needed to gain further upside from
  • Discovered undeveloped reserves
  • Potential additional reserves
  • Still need exploration success to meet Task Force
    target
  • Proportion of gas reserves will increase

12
Task Force action programme
  • Increased collaboration
  • Technologies for existing fields
  • Through-tubing drilling - coiled tubing rotary
  • Multi-laterals
  • Under-balanced drilling
  • SMART wells
  • Technologies for new fields
  • High resolution seismic dynamic reservoir
    modelling
  • Long tie-back technologies

.
13
Potential additional reserves
  • Over 300 undeveloped discoveries
  • Main barriers
  • Low reserves
  • Sub-surface technical issues
  • Well deliverability
  • Fluid/surface technical issues
  • Distance from infrastructure
  • PILOT / DTI action
  • Structured interviews
  • Workshops in 2001
  • Satellite Accelerator initiative

14
Adding value to mature fields
  • Infill drilling
  • Forties
  • Clyde area
  • Murchison
  • Extension of wells to deeper targets
  • Triassic reserves
  • EOR
  • Commercial successes
  • Magnus pipeline

15
  • Images of channel systems by-passed and unswept
    oil
  • Infill targets remain economic with new imaging
    technology

16
Clyde area oil production
17
Murchison life of field profile
Secondary Infills
Dev Drill
Plateau
Primary Infills
Harvesting
New Operator
B/D
18
(No Transcript)
19
New breed of mature field operator
  • Previous companies focus on new fields
  • Smaller companies take control
  • Reveal potential in satellites catchment area
  • Add value by using existing technology
    innovatively
  • Reduce platform running costs
  • Extend field life

20
UKCS success factors
  • Focused technology application
  • Drilling
  • Wells
  • Sub-surface
  • Tie-back
  • Collaboration on non-competitive issues
  • Share risks and benefits
  • Specialist vessels
  • Supply chain efficiencies
  • Reduced decommissioning costs

21
Future for UKCS
  • Entry of new dynamic, smaller players
  • DNO, Venture, Highlander, Veba
  • New working methods
  • Collaboration
  • Joint drilling campaigns
  • Overcoming technical and logistical problems
  • Sharing of resources
  • Alignment of partner interests
  • Continuing technical innovation