Title: Success Driven Project Management
1Success DrivenProject Management
- Vladimir Liberzon
- www.spiderproject.ru
2Introduction
- Modern project management methods and tools
developed and used in Russia have many advantages
that are yet unknown to the international project
management community. - Some of them will be described in this
presentation.
3Introduction
- We will discuss the proven methodology of project
planning, performance analysis and project
control that we call Success Driven Project
Management (SDPM). - This methodology integrates scope, time, cost,
and risk management and may be of particular
interest for the Critical Chain theory supporters
because both approaches have some common
features.
4Introduction
- We will also discuss some notions and methods of
project planning and performance analysis that
are common in Russia and necessary for SDPM
understanding. - We will illustrate the approaches described in
this presentation using project management
software package Spider Project that is most
popular professional PM tool in Russia.
5Introduction
- We shall start with the definitions and the first
of them is the definition of the Critical Path. - We use the term Resource Critical Path (RCP) to
specify our interpretation of the classical PMBOK
Guide definition. - We believe that project Critical Path, Resource
Critical Path and Critical Chain - a) imply the same set of activities and
- b) the traditional interpretation of the critical
path is not correct.
6Critical Path
- A Guide to the Project Management Body of
Knowledge? defines the Critical Path as those
activities with float less than or equal to a
specified value, usually zero. - Float is the amount of time that an activity may
be delayed from its early start without delaying
the project finish date. - Early start is the earliest possible point in
time at which the uncompleted portions of an
activity (or the project) can start, based on the
network logic and any schedule constraints.
7Critical Path
- Project schedule constraints include resource
constraints, finance and supply constraints,
calendar constraints and imposed dates. - The float should be calculated with all schedule
constraints as well as the network logic taken
into account. - The total float determined by most PM packages
shows the time reserve for the execution of
activity, however the availability of resources
is completely ignored. - It is not the actual activity float as defined by
A PMBOK Guide?.
8Resource Critical Path
- True critical path should account for all
schedule constraints including resource and
financial limitations. - We call it Resource Critical Path (RCP) to
distinguish it from the traditional
interpretation of the critical path definition. - The calculation of RCP is similar to the
calculation of the traditional critical path with
the exception that both the early and the late
dates are calculated during forward and backward
resource (and material, and cost) levelling.
9Resource Critical Path
- It appears that by adding financial and supply
constraints to the Critical Chain definition as
well as the way of the Critical Chain
calculation, we will obtain something very
similar to RCP. - RCP can consist of activities that are not linked
to each other. Traditional critical path approach
assumes that this may be due to the different
activity calendars and imposed dates. In case of
RCP calculation, it can also be due to resource
constraints and financial and supply limitations.
10Activity Volume
- Projects are often planned (especially in the
construction and manufacturing) basing on the
federal, local, industrial or corporate norms and
standards. - These standards usually refer to resource
productivity on the certain activity types, costs
and materials per unit of activity volume (volume
of work to be done on activity). - Usage of these norms affects the planning of
project activities.
11Activity Volume
- Activity volume can be measured in meters, tons,
etc., planned work hours, percents or any other
units. - Activity volume is often used as an initial
activity information instead of duration. If
assigned resource productivity is defined in
volume units per hour then activity duration may
be calculated during project scheduling. - Activity volume does not depend on assigned
resources.
12Resource Productivity
- Calculation of activity duration basing on
assigned resource productivity has many
advantages. We have already mentioned the
possibility of applying corporate norms. Changing
the norm we change the planned duration of all
activities of certain type. - It is especially useful for the forecasting of
project duration and estimating uncertainties.
13Resource Analysis
- Resource analysis is an essential part of project
execution analysis. It is vital for project time
analysis to be able to forecast resource
productivity. - Monitoring of the actual resource performance
allows to determine trends and to make necessary
adjustments of resource productivity databases.
14Resource Analysis
- The usage of project resources varies at the
different project phases. The forecasting that
accounts for these differences is considerably
more accurate than the methods of Earned Value
Analysis. - Methods of risk analysis and simulation should
include estimations and simulations of activity
volumes, resource productivity, resource
availability, etc.
15Resource Analysis
- The main problem with the traditional methods of
risk simulation is their initial assumption that
cost and duration deviations of different
activities are independent of each other. - Activities performed by a set of resources will
have correlated duration. Not taking this into
consideration leads to producing wrong risk
simulation results.
16Sample Project
- Lets illustrate the basic concepts described
earlier using sample project consisting of only
three independent activities and two resources. - Project data are shown at the next slide.
17Sample Project - Data
18Sample Project - Critical Path
- At this slide you see project schedule before
resource leveling. Activity 1 is critical. Other
activities have 5 day float.
19Sample Project - RCP
- After resource leveling activities 2 and 3 became
critical while activity 1 has 20 day float
(resource float). - So RCP consists of activities 2 and 3.
20Activity Resource Float
- Activity resource floats have one large advantage
over the total floats calculated by most PM
software. This advantage is feasibility. - Traditional total float shows the period for
which activity execution may be postponed if
project resources are unlimited. - Activity resource float shows the period for
which activity execution may be postponed within
the current schedule with the set of resources
available in this project.
21Risk simulation
- Our experience of project planning shows that the
probability of successful implementation of
deterministic project schedules and budgets is
very low. - Therefore project planning technology should
always include risk simulation to produce
reliable results. - We will describe the approach to project planning
that is supported by Spider Project.
22Project Planning
- The project planner obtains three estimates
(optimistic, most probable and pessimistic) for
all initial project data. - These data are used to calculate optimistic, most
probable and pessimistic project schedules and
budgets. - The most probable and pessimistic project
versions will usually contain additional
activities and costs and employ other resources
and different calendars than the optimistic
schedule.
23Desired Data
- The planner should define desirable probabilities
of meeting target dates, costs, and material
consumption rates at major project milestones. - Basing on these probabilities, the package
calculates corresponding desired project target
dates, costs, and material requirements. - These desired data form the basis for contract
negotiations and decision making.
24Target Data
- Negotiations may result in establishing new
target data. - Spider Project helps to negotiate by answering
the questions on probability to meet any
restrictions on time and on budget. - Probability of meeting target data (cost, time,
quantity) is called Success Probability. - Success Probability is the BEST indicator of the
current project status.
25Target Schedule
- In addition, the package calculates the target
schedule. - Target Schedule is the backward project resource
constrained schedule with the most probable
activity duration, material requirements and
costs and target milestone dates. - Lets apply the described approach to our sample
project.
26Risk simulation for Sample project
- We will make very simple assumption
- Optimistic productivity of assigned resources is
20 higher and pessimistic is 20 lower than the
planned ones. - Lets assume that we have no other risks )).
27Desired Data
- We want to be on time with 70 probability and
under budget with 75 probability. - The package will identify the desired finish date
and the required project budget
28Desired Data
29Target Data
- Lets assume that after negotiating the contract
we established project target finish date and
target budget. - The package will calculate the probability of
meeting target parameters and we will see that we
were lucky with time and should be very cautious
with the project budget
30Most Probable Data
- Lets assume that the most probable version of
our project was defined as the project baseline. - The initial probabilities to meet most probable
project parameters
31Most Probable Data
- These probabilities are high because we did not
simulate risk events. - We will track the probabilities of meeting
baseline data (24000) and contract budget
(25000).
32Project Execution
- Now lets simulate Sample project execution.
- Lets assume that the actual resource 1
productivity was 10 higher than expected (0.55),
while the actual resource 2 productivity was 10
lower (0.27). - Lets assume that the productivity of these
resources did not change during project
execution. - Our task - to estimate project performance, to
forecast future project results, and to decide if
corrective action is necessary.
33Sample Project Execution - 1st week
- We will use Resource analysis, Success
Probability analysis, and Earned Value analysis. - We assume that estimates were done each week and
will analize trends. - Initial baseline data (estimate at completion)
- Project Finish - 10.05.2002 1600
- Project Cost - 24000.00
34Sample Project Execution - 1st week
35Resource Analysis - 1st week
- Providing Resource Analysis we shall decide if
the actual deviations in resource productivity
are accidental or the planned productivity should
be adjusted. - Lets adjust them raising productivity of
resource 1 by 5 (0.525) and lowering the
productivity of resource 2 by the same 5
(0.285). - Our new forecast (estimate at completion)
- Project Finish - 15.05.2002 1509
- Project Cost - 24028.09
36Resource Analysis - 1st week
Advice your project may be late and over budget
37Success Probability Analysis 1st week
38Success Probability Analysis 1st week
- The cost probability trends are positive, timely
performance probability trend is negative. - Advice pay attention to resource productivity.
39Earned Value Analysis 1st week
Advice everything is fine. Your project will finish early and under budget Advice everything is fine. Your project will finish early and under budget
ACWP 3200
BCWP 3280
BCWS 3200
CV 80
SV 80
CPI 1.025
SPI 1.025
40Resource Analysis - 2nd week
- New performance data show that the planned
resource productivity should be adjusted again. - Lets adjust them raising productivity of
resource 1 to 0.5375 and lowering the
productivity of resource 2 to 0.2775). - Our 2nd forecast (estimate at completion)
- Project Finish - 17.05.2002 1035
- Project Cost - 24107.63
41Resource Analysis - 3rd week
- New performance data show that the planned
resource productivity should be made equal to the
actual because they did not change from the
project start. - Our 3rd forecast (estimate at completion)
- Project Finish - 20.05.2002 1226
- Project Cost - 24242.44
42Resource Analysis - 3rd week
43Resource Analysis
- These forecasts will not change later. The
forecasts based on resource analysis might be
very accurate but are not easy to make and
require detailed performance reports. - Besides they do not consider project risks that
depend on factors other than resource
performance.
44Success Probability Analysis
- Success Probability shows current project status,
Success Probability trends show project manager
if corrective action is needed. - Success Probability trends for our Sample project
is shown in the next slide. - In the same slide you will see Earned Value data
for the Sample Project.
45Success Probability Analysis
46Success Probability Analysis
- Success probability trends show us that the
project will be - certainly late and
- probably over budget of 24000
- though certainly under budget of 25000.
47Earned Value Analysis
- Earned Value Analysis data do not show problems
with our project too long. Quite contrary it
shows that everything is fine till the end of the
execution of activity 1. - Trends of Earned Value data are shown in the next
slide.
48Earned Value Analysis
Parameter 04.03.2002 11.03.2002 18.03.2002 25.03.2002 01.04.2002 08.04.2002 15.04.2002 22.04.2002 29.04.2002
ACWP 3200 6400 9600 12800 16000 18109.1 19309.1 20509.1 21709.1
BCWP 3280 6560 9840 13120 16400 18480 19560 20640 21720
BCWS 3200 6400 9600 12800 16000 19200 20400 21600 22800
CV 80 160 240 320 400 370.89 250.89 130.89 10.89
CV 2.5 2.5 2.5 2.5 2.5 2.05 1.3 0.64 0.05
SV 80 160 240 320 400 -720 -840 -960 -1080
SV 2.5 2.5 2.5 2.5 2.5 -3.75 -4.12 -4.44 -4.74
CPI 1.02 1.02 1.02 1.02 1.02 1.02 1.01 1.01 1
CPI 102.5 102.5 102.5 102.5 102.5 102.05 101.3 100.64 100.05
SPI 1.02 1.02 1.02 1.02 1.02 0.96 0.96 0.96 0.95
SPI 102.5 102.5 102.5 102.5 102.5 96.25 95.88 95.56 95.26
49SDPM Project Management Technology
- We recommend using the optimistic project version
for setting tasks for project implementers while
the calculated contingency reserves should be
used by the PM team for the management purposes. - Start (finish) contingency reserves (buffers) are
calculated as the difference between activity
start (finish) time in the optimistic and target
schedules. - Contingency reserves are also calculated for the
activity cost and material requirements.
50Success Probability
- But the most valuable indicators of project
performance are Success Probabilities -
probabilities of meeting target project
parameters. - Trends of Success Probabilities show project
manager if the corrective action is needed. - The value of Success Probability shows current
project status better than any other project
parameter.
51Project Control Parameters
- Project manager obtains the following estimates
necessary for effective project control - Probabilities of meeting target project
parameters (success probabilities), - Target activity start and finish dates, resource
and material requirements and cost, - Planned activity start and finish dates, resource
and material requirements and cost in the current
schedule,
52Project Control Parameters
- Activity resource floats that show the time for
which activity execution may be postponed without
delaying project finish date in the current
schedule, - Activity contingency reserves (buffers) for time,
cost and materials calculated as the difference
between the corresponding optimistic and target
parameters. - The following slide shows the optimistic and
target schedules, and other scheduling and risk
analysis information for our Sample project.
53Project Control Parameters
54SDPM tips for the project control
- Plan day-to-day activities using the optimistic
estimates but pay special attention to resource
floats and to contingency reserves. - Include the causes of delays in activity
completion and cost overruns in performance
reports. - Regularly update the estimates in the optimistic,
most probable and pessimistic project schedules. - Regularly recalculate the success probabilities
and analyse trends.
55SDPM and Critical Chain - common
- You may notice that SDPM and Critical Chain
approaches have a lot in common. - Resource Critical Path is the same as Critical
Chain. - Therefore Critical Chain project buffer may be
regarded as an analogue of SDPM contingency time
reserve, - feeding buffers are similar to resource floats.
- Both the SDPM and Critical Chain approaches
recommend to use the optimistic estimates for
setting the tasks for project implementers. - But there are differences too.
56SDPM and Critical Chain - different
- We cannot agree with the Critical Chain theorys
assumption that one should always avoid
multitasking. - Usually there are many subcritical activities
belonging to the different network paths and even
the minor delays in the execution of subcritical
activities can lead to the changes in the RCP.
This comes into conflict with the Critical Chain
theorys assumption that the Critical Chain never
changes during the project execution. - The assumption that only one project drum (in our
terminology - critical) resource exists is also
dubious. Our experience shows that critical
resources are different at the different phases
of project lifecycle.
57SDPM technology steps 1
- Assess risks and create optimistic, pessimistic
and expected estimations of activity duration and
volumes, resource productivity and quantity,
activity and resource cost, calendars, etc.
- Estimates are usually based not only on expert
judgement but also on regulatory or corporate
norms.
58 SDPM technology steps 2
- Calculate optimistic, most probable, and
pessimistic resource and cost constrained project
schedules.
59 SDPM technology steps 3
- Calculate project and each phase desired finish
dates and costs (with the desired probability of
successful execution).
60 SDPM technology steps 4
- Negotiate and define target finish dates and
costs.
61 SDPM technology steps 5
- Calculate target schedule with the most probable
activity duration but target finish dates
(backward resource constrained schedule).
62 SDPM technology steps 6
- Determine time and cost buffers, and
probabilities of meeting target parameters.
63 SDPM technology steps 7
- Use the optimistic schedule as a plan for the
employees.
- Using optimistic estimates, we increase our
chances to obtain the reports on any deviations
from the proper activity execution. This
information is necessary for quality and risk
analysis.
64SDPM technology steps 8
- Control risks and regularly recalculate necessary
time buffers and success probabilities.
65THANK YOU
- We would appreciate your comments on this
presentation. - We invite everybody interested in developing
common approaches to contact Moscow PMI Chapter
(E-mail spider_at_mail.cnt.ru).