WELCOME TO APGENCO - PowerPoint PPT Presentation

About This Presentation
Title:

WELCOME TO APGENCO

Description:

Reactive power by condenser mode ... Merit Order Dispatch Dispatch through Merit Order shall be on the basis ... progress the new capacities at most optimal ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 23
Provided by: Comme5
Category:

less

Transcript and Presenter's Notes

Title: WELCOME TO APGENCO


1
  • WELCOME TO APGENCOS PRESENTATION
  • ON
  • CERCS DISCUSSION PAPER JUNE-03
  • ON
  • TERMS CONDITIONS OF TARIFF
  • (Commencing 01.04.04)
  • by
  • V.V.RAO, IDAS
  • DIRECTOR/ COMMERCIAL
  • APGENCO.

2
GENERAL
  • The consumer interests are better protected if
    his growing needs for power in future are well
    recognized right now and simultaneously progress
    the new capacities at most optimal cost. The
    tariff structure therefore must aim at not least
    cost alone but equally important, provide timely
    capacity additions too.
  • The CERC tariff shall firmly enable not only
    retention of RoE / Incentive by the State Gencos
    but also consistent capacity additions in a
    planned/ phased manner.
  • CERC Tariff guidelines in respect of CGS shall
    automatically extend and uniformly apply to all
    the State Gencos also and pertinently to all IPPs
    without discrimination.
  • In view of several structural changes either
    already in place or in the offing the PPAs
    concluded with IPPs in the pre-regulatory regime
    shall have to be revisited by the Commissions
    concerned so that a level playing field with the
    State Central Generators is ensured.

3
GENERAL Contd..
  • All State Gencos must be allowed to operate under
    a single PPA without insisting on Station-wise
    PPAs. Variable Charges can be station-wise even
    under this dispensation.
  • Station vintage, obsolescence of technology and
    the past 3-year performance shall be the main
    criteria for prescribing operating parameters in
    respect of small capacity generating units (say
    30-110 MW).
  • Non-tariff components which are peculiar to
    the State Gencos such as unfunded liabilities
    on account of Pension / PF etc. shall be
    entirely borne by the respective State Govts.
    only.
  • State Transcos shall contract the State Gencos
    capacity as well as energy in full whereby no
    such occasion presents for certain (already)
    built-up projects to get deleted/ rejected at a
    later date.

4
FIXED CHARGES RoE Depreciation
  • The existing return at 16 on equity shall
    continue.
  • ROCE proposed by CERC needs a still clearer
    definition. As we understand, computation by
    liability side approach and asset side approach
    is not one and the same and none of these yields
    16 return in later years of the project life at
    a dwindling rate.
  • If ROCE method only is to be adopted, Generator
    must therefore be assured of firmly getting at
    least an equivalent of 16 return on the equity
    portion throughout the project life on
    year-to-year basis.
  • RoE shall take into consideration the equity
    component of subsequent capitalisations on
    account of major R M / life extensions, if any,
    on par with the original equity.
  • The capitalized expenses on major RM/ life
    extension shall also be eligible for depreciation
    at the same rates.
  • The existing rates of accelerated depreciation
    _at_7.84 for thermal and 3.4 for hydel along with
    the provision for advance against depreciation
    may be retained.

5
Fixed charges Interest on loans
  • Interest on the outstanding loans shall be
    allowed at actuals, subject to
  • The interest rate shall not exceed PLR plus a
    stipulated margin which is uniform.
  • Generating companies to renegotiate interest
    rates within these limits from time to time in
    case of falling interest rates.
  • In case of increase in interest rates during the
    course of repayment period, no additional
    liability shall be reckoned, since earlier
    negotiated rates of interest are normally
    operative for the entire term of the loan.
  • Interest will be reckoned on an year-to-year
    basis on outstanding loan.
  • Where a large number of projects are covered or
    different loans involved for the same project,
    the weighted average rate of interest shall apply.

6
Fixed Charges OM.
  • Based on the current capital cost/MW, to be
    declared each year by an Authority like CEA, OM
    expenses shall be allowed _at_ 2.5 for new thermal
    projects and 1.5 for new hydel projects.
  • However, for old stations, this can be the
    average of past 3 years as per Audited Annual
    Accounts. There on, escalating once _at_ 10 yields
    base OM and further escalating it annually _at_ 6
    yields normative OM for each year of the next
    tariff period.

7
FIXED CHARGES Interest on Working Capital
  • The present composition of working capital
    elements does not call for a change.
  • Owing to the irregular and inadequate payments
    being received by the State Gencos, it is
    imperative that the 2-months receivables, as
    billed, shall continue to be the most essential
    working capital element.
  • Similarly, 1 month OM also shall constitute the
    working capital.

8
FIXED CHARGES Incentive Contd..
  • Incentive shall be availability-linked in
    preference to the PLF and the target availability
    for reckoning incentive shall be 80 for thermal
    and 85 capacity index for hydel.
  • The current merit order scenario is not
    PLF-oriented and hence incentive must be
    distanced from PLF.
  • The level of thermal incentive shall be uniformly
    21.5 Ps/Kwh (subject to 50 of fixed expenses)
    for availability in excess of 80 without any cap
    at 90.
  • Hydel incentive as per Cl. 3.8.2.6 of the CERCs
    Discussion Paper (p-46) of June-03 seems to be in
    order. Incentive rate may be specified by the
    Commission. There shall be no disincentive if
    Capacity Index falls short of the targeted 85
    for reasons beyond the control of Generator.
  • Incentives shall be payable monthly based on
    availability/ capacity index for the month.

9
Recovery of Fixed Expenses (Thermal only)
Availability or gt 80 Full fixed cost, including ROE.
Availability between 80 and 70 Progressive pro-rata reduction of fixed cost only in ROE, up to nil ROE at 70.
Availability between 70 and 50 Progressive proportionate reduction in other fixed expenses except depreciation/ debt repayment requirement, reaching 62.5 of other fixed expenses at 50 availability
Availability less than 50 Further proportionate reduction in fixed expenses including depreciation/ debt repayment in case of outages attributable to generating company. If outage is for reasons of force majeure, acts of God or reasons attributable to external factors, no reduction shall be made in (i) above.
The above is necessary in order that the cash-starved state generating companies do not face a more severe financial crunch in case the units remain under forced outage for prolonged periods, particularly for reasons not attributable to them. The above is necessary in order that the cash-starved state generating companies do not face a more severe financial crunch in case the units remain under forced outage for prolonged periods, particularly for reasons not attributable to them.
Even if fixed expenses are to be restricted as above, the requirements of debt servicing shall have to be allowed as advance, and the difference between this advance and what is due will be recovered from future revenues. Interest at rates applicable for working capital may also be recoverable on such advances. Even if fixed expenses are to be restricted as above, the requirements of debt servicing shall have to be allowed as advance, and the difference between this advance and what is due will be recovered from future revenues. Interest at rates applicable for working capital may also be recoverable on such advances.
10
Payment Penal Interest Charges
  • Track record of payments being made to State
    Gencos is far from satisfactory. Unless payment
    covered under LC with penal provisions for
    delayed payment is ordered by the Commissions
    concerned, State Gencos continue to be in dire
    stress at the cost of their credibility as
    commercial entities.
  • Irrevocable revolving LCs covering one month dues
    shall therefore be opened by Transcos forthwith.
  • For delayed payments, penal surcharge shall be
    levied _at_ 2 p.m. on total outstandings from the
    start of the financial year.

11
Development Surcharge and other issues
  • Shall be on par with thermal and hydel CGS.
  • States have no less responsibility for ensuring
    adequate capacity additions. Together with RoE,
    Development Surcharge will also bring about
    necessary investments by the State Gencos for
    this purpose.
  • Development Surcharge shall be kept aside
    annually and ultimately utilized for no purposes
    other than capacity addition.
  • Hydel peaking power shall be accorded special
    tariff in addition to normal fixed charges.
  • Reactive power by condenser mode operation shall
    be on chargeable basis.
  • Sale of energy from the Non-conventional sources
    like mini-hydels and wind projects shall be
    allowable at special tariff for State Gencos on
    par with IPPs.

12
Merit Order Dispatch
  • Dispatch through Merit Order shall be on the
    basis of not only the station-wise variable
    charges but other system conditions also such as
    system stability, improvement of voltage
    profiles, reduction in transmission losses,
    congestion of transmission lines, avoided
    transmission cost etc.
  • Incentive shall not have any role in merit order
    dispatch for the simple reason that the incentive
    cannot be PLF-linked (connected to fuel charges)
    any longer but shall be Availability-linked
    (connected to fixed charges).
  • The existing practice of adding incentive, for
    merit order purpose, at a flat rate of 21.5
    Ps/Kwh to each unit of station-wise variable
    charge for PLF (as long as cumulative PLF is over
    and above 77 is highly unjustified).

13
Merit Order Dispatch Contd
  • Conceding, for argument sake, that the incentive
    is figuring in the merit order, the incentive
    that will be payable/ actually paid alone shall
    reflect even for merit order purposes and they
    cannot be independent of each other.
  • DI shall be such that no coal based unit is ever
    required to be operated at less than 80 of its
    installed capacity, subject to technical limits.
  • Backing down limits for each generating unit
    shall be clearly agreed upon depending on prudent
    technical practice subject to a maximum of 20 of
    respective installed capacity.

14
STATION OPERATING PARAMETERS
Station heat rate (Kcal/ Kwh) Sec. fuel cons. (ml/Kwh) Aux. Cons. ()
New 200 MW units Negotiable, based on design values etc. 2.0 As per GoI norms i.e. 9 for coal based stations without cooling towers and 9.5 for stations with cooling towers.
200 MW sets already in service for 5 years and above Shall be 2500 uniformly 2.0 Subject to GoI norms as minimum limits, station-specific conditions shall have to be considered for extra provision, if required.
Less capacity sets in service for 5 years and above Roll on avg. of past 3 years on year to year basis 3.5 Roll-on avg. of past 3-year period on year-to-year basis.
All the above norms proposed shall be applicable only for despatchability of 85 and above of Installed Capacity. Should the Stations run on partial loading due to Merit Order/ Backing down, the Stations must be suitably compensated for increase in parameters. All the above norms proposed shall be applicable only for despatchability of 85 and above of Installed Capacity. Should the Stations run on partial loading due to Merit Order/ Backing down, the Stations must be suitably compensated for increase in parameters. All the above norms proposed shall be applicable only for despatchability of 85 and above of Installed Capacity. Should the Stations run on partial loading due to Merit Order/ Backing down, the Stations must be suitably compensated for increase in parameters. All the above norms proposed shall be applicable only for despatchability of 85 and above of Installed Capacity. Should the Stations run on partial loading due to Merit Order/ Backing down, the Stations must be suitably compensated for increase in parameters.
15
STATION OPERATING PARAMETERS Contd
  • The element of compensation for oil support
    during partial load operations (or unit startups
    due to DI) in the present ABT/ Merit Order regime
    shall be clearly defined by the Commission in
    terms of X ml/Kwh (in excess of 2.0 or 3.5) for
    every Y of backing down beyond the agreed of
    installed capacity for Z hours of backing down.
  • For hydel stations, which draw station supply
    from the grid through GTs in the absence of
    generation, limit for auxiliary consumption shall
    be enhanced from 1 to 1.5.

16
Coal issues
  • Steep variations in price structure of coal
    within SCCL MCL must be curbed and evolve a
    uniform coal pricing policy. Also, pricing of
    coal shall relate to million Kcal.
  • Serious grade slippage is taking place by 2-3
    grades between the billed actually tested at
    the station end. Consequently, Gencos are paying
    heavily to the coal supplier while collecting far
    less through variable charges.
  • Coal suppliers shall not escape their
    responsibility from joint collection/ testing of
    coal samples at station end also on continuous
    basis. UHV vs GCV relation cannot be established
    otherwise.
  • There by, the grading practice shall be rejected/
    abolished eventually.
  • Coal suppliers only shall wash the coal and
    supply washed coal with 34 ash or less to the
    Generators.
  • Present coal linkage system shall ensure distant
    generating stations be linked with better quality
    coal mines such that quantum of coal purchased
    transported are minimised, resulting in reduced
    specific coal consumption.
  • A coal/ transport Regulator is highly essential
    to bring about such vital changes discussed above.

17
Issues specific to APGENCO
  • Unfunded liabilities
  • GoAP has decided to allocate to APGENCO only (not
    touching Transco Discoms) an unfunded liability
    on account of pension provident funds of all
    the erstwhile APSEB employees to an extent of Rs.
    4617 Cr by way of enhancing the value of fixed
    assets by 4270.90 Cr.
  • The entire burden on APGENCO alone boosts its
    fixed cost.
  • The State Regulator expects APGENCO to meet the
    entire liability (repayment interest) on
    year-to-year basis from the extra depreciation
    owing to enhanced asset value.
  • From the beginning, the understanding with the
    Govt. reforming quarters is that this liability
    is going to be a solid tariff-pass through.

18
Issues specific to APGENCO
  • Unfunded liabilities Contd
  • On the contrary, together with another major
    liability in the shape of Vidyut bonds, the
    depreciation so allowed even with RoE included is
    not adequate to service these 3 liabilities on
    year-to-year basis.
  • APGENCO pleads the interest component only of
    these liabilities to be pass through in tariff,
    but this is not acceptable to Regulator.
  • APGENCO also pleads relegation of pension/ PF
    liability to the respective entities but this
    also is not acceptable to APTRANSCO.
  • In view of this, APGENCO pleads for total
    takeover of this unfunded liability by the Owner
    i.e. GoAP.

19
Issues specific to APGENCO
  • Srisailam Left Bank Power House (SLBPH) 6150 MW
  • Under the GoAPs Transfer Scheme dt. Jan 99, the
    SLBPH, the unique under ground hydel station in
    AP, was inherited by APGENCO while in
    construction stage since late 80s.
  • APGENCO has since then progressively commissioned
    each of the six 150 MW units. The station is now
    fully operational in conventional mode, subject
    to hydrology.
  • Cost of the project is tentatively Rs.3340 Cr.
  • The widespread impression is that the GoAP had
    assumed major liability of the project for
    servicing from its funds and therefore the
    capital cost should be less.
  • This is to clarify that, in real terms, no
    liability was taken over by GoAP as such. All
    loans availed and interests accrued upto 31.01.99
    were paid up i.e. adjusted against the subsidy
    payable by GoAP to APSEB as on that date. Hence
    there has been no remission of any of the loans
    and interests by GoAP.

20
Issues specific to APGENCO
  • (SLBPH) Contd
  • Project objectives are
  • To tap surplus water to generate seasonal energy
    of 1000 to 1200 MU.
  • Operating together both the Left Right Bank PHs
    in conventional mode with reduced load factor to
    meet higher system peak demand (1300 MU or more
    of peaking energy with 1500 MW capacity for
    varying in a year of normal hydrology) and
  • At a later stage, to resort to pump mode
    operation when the water availability gets
    reduced for conventional mode operation.
  • Efforts are already on for enabling pump mode
    operation with necessary river course correction
    at the best optimum cost considerations.

21
Issues specific to APGENCO
  • (SLBPH) Contd
  • At this stage, the State Regulator considered it
    necessary to take this project out from the
    common PPA of APGENCO and ordered to earn its
    revenues on the basis of a separate PPA to be
    entered into.
  • APGENCO pleads for retention of SLBPH in common
    PPA only as the financial fall out on it in case
    of separation is devastating.
  • Or else, GoAP has to directly subsidise APGENCO
    on year-to-year basis to the extent of shortfall
    in revenue collection at a new tariff to be
    agreed upon with APTRANSCO who have already taken
    over a sizeable energy during last year and this
    year but paid nothing so far.

22
  • THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com