1Fall Infrastructure Update 2004
- SAPbiz Presentation June 23, 2004
2Overview
3Scope
- IN SCOPE
- SAP Support Packages
- Database Upgrade Oracle 8i to Oracle 9i
- SAP Kernel patches
- SAPGUI 6.20 4.6D
- SAP infrastructure enhancements
- NOT IN SCOPE
- ITS Upgrade Migration to Linux
- O/S Upgrade
- EHS, PI Space Registration Phase
- Web Application Server 6.40
- SAPbud (Nimbus Replacement)
- SAP Hardware Renewal
4Proposed Key dates
Step Date(s)
Pre-Development evaluations (Pre-staging, Staging) July 26 August 12
Snapshot of Production for Integration system refresh Aug. 7 (130am)
Update Development (SF2, SF8) Infrastructure Aug. 12-16
Refresh Integration system (SF6), Update its Infrastructure, and prepare for testing Aug. 16 27
HR-specific integration testing Aug. 30 Sept. 2
Integration testing resolution Sept. 717 (Labor Day is Sept. 6)
Go / No-go decision Sept. 21
Update Production (PS1) Infrastructure Sept. 25-26
Execute Production validation Sept. 26-27
Production (PS1) available Sept. 27th (Monday)
Refresh Update of Test/QA (SF5) from Production (PS1) Oct. 9-10
Chg to 9/20