Title: THE CMS ALIGNMENT SYSTEM
1THE CMS ALIGNMENT SYSTEM
Task of the align. system Monitor the position
of the m-chambers and the CT detectors with
respect to each other.
Building blocks 4 subsystems - Internal
tracker align. - Internal muon barrel and
endcap - The link tracker Û muons (3
alignment planes)
- Basic components
- Mechanical structures (rigid, stable)
- Light sources (LED, laser beams)
- Light detectors (DPSD)
- Tilt, proximity and temp. sensors
- System requirements
- Physics requirements
- Position accuracy in rf (referred to the tracker
- detector) for muons up to 2 TeV
- - track reconstruction 500 mm
- - for pt measurement 150(350) mm at
MB1(MB4) - 150 mm at ME1 layer
- Operational constraints
- Detector hermeticity
- Large dynamic range (few cm)
- Radiation tolerance and insensitivity to DB
- of the components
2THE CMS ALIGNMENT SYSTEM
3THE CMS ALIGNMENT SYSTEM
4MUON ALIGNMENT SYSTEMORGANIZATION AND
PARTICIPANTS
- Internal Barrel Internal Endcap Link system
- CERN (CMT) USA SPAIN
- Hungary (Debrecen) FERMILAB CIEMAT (Madrid)
- Kossuth L. Univ. North-Eastern Univ. IFCA
(Santander) - ATOMKI
- Austria (Vienna)
- HEPHY Inst. Fur H. der OAW
- Pakistan (Islamabad)
- Optics Labs.
5Link Tracker - Muons
- Working principle
- Translates Tracker co-ordinates (points, f
angles) to the linking points in the external
MABs - The tracker co-ords are defined by the internal
tracker alignment at the TK ends (TK alignment
wheels) - The MAB linking points serve for Barrel and
Endcap connection to the Tracker - Each 1/4 f plane is generated independently. The
whole system is constrained at the TK volume - Points (3D co-ords) are measured with laser beams
semitransparent sensors for the co-ords
perpendicular to the beams, and by mechanical
tubes and proximity sensors for the co-ords along
the beams - The f angle is measured at each structure (TK
wheel and MABs) by Laser Level units - Measures directly ME1/2 chambers (CSCs crossed by
a secondary link line) and the ME1/1 CSC disk
(using a ME1/1 transfer platform to bend by 90
the laser beam) -
6Barrel muon alignment
- Working principle
- 36 rigid mechanical structures called
- MABs are holding TV-cameras
- (typically 10 cameras/MAB). These
- cameras are observing LEDs
- mounted on both sides of the barrel
- muon chambers ( 40/chamber) and
- on the so called Z-bars (the reference
- in Z-direction).
- A high level of redundancy is
- achieved by multiple observations
- and loops which make the system
- robust and reliable.
- The barrel system is connected to the
- TK via linking lines.
7Endcap muon alignment
- Connect Endcap CSCs to Tracker
- Tracker co-ordinates (points, f angles) from the
MAB modules (via link system) - 6 axial lines (transfer lines) pass through the
MABs and run outside each CSC station - Connection between axial lines and SLMs on
transfer plates. - Z distance measured by mechanical tubes and
optical gap sensors - Radial measurements from transfer plates to CSCs
by potentiometers - CSCs alignment design
- 3 laser lines per CSC station (SLM) are linked to
the axial transfer lines - SLM measures location of CSCs (on 1/6)
- SLMs are 60 degrees apart, mount on CSCs at same
point on each chamber - Precise location of sensors on CSCs using
internal calibration and photogrammetry - Precise relationship of strips, alignment pins,
and sensors on CSCs
8Endcap muon alignment Transfer lines and Z
measurements
9Endcap muon alignment SLMs
ALIGNMENT SCHEMATICS
Transfer Sensor
Transfer Laser
EMU Transfer line
M
M
1
2
SLM Laser
P
1
Transfer Plate
MAB
SLM sensor
LHC Beam
CSC
CSC SLM-line
2-D
P
2
sensor
Transfer Plate
EMU Transfer line
Alignment Schematics. Only one transfer laser is
shown, at the top-left corner, defining the EMU
transfer line. Similarly for the SLM line, only
one laser beam, coming from the top is shown. The
other laser beams coming from the opposite
directions have been omitted for clarity.
10Barrel alignment status
- Mechanics MABs and LED holders
- Minimal system test
- Readout electronics
11MAB Modules (External MABs)
- Barrel cameras
-
-
- Link sensors
-
Endcap transfer sensors
12MAB development
- Aluminum prototype used for first tests.
- New prototype under construction (Portugal)
- Glass fiber 1.5 1 m2
- Study deformations at the junctions (data by
June) Þ define final geometry and materials - 3D design of the different MAB structures most
of integration problems (inside the Mu-detector
and at boundary region) have been identified.
13LED holders in the MB chambers
-
-
-
- - Four forks /chamber
- - Each fork
instrumented with 10 LED (4/6) - - LED
positions within the holder -
16 mm (x,y), 60 mm
(z) -
Total number of
LED 10000 -
- Mounting of
precalibrated forks and LED driver
electronics during chamber assembly at the
production sites. - -
Calibration of each chamber at Cern before
installation in the detector -
Estimated
calibration precision - 55-65 mm (x,y) 470 mm (z)
14LED Holder mechanical repeatability
- Deviation wrt to a mean of a series of
position-reposition tests
15- BARREL alignment stand (CERN ISR I4-hall)
- Layout of the Minimal test of the barrel
alignment disposition of alignment - components as for the central muon barrel wheels
16Minimal barrel test results Accurate
reconstruction of LED positions with a floating
calibrated MAB referenced by external system
- s(D5) 18 mm
- s(D4) 38 mm
- s(M5) 11 mm
- s(M4) 25 mm
- s(G5) 20 mm
- s(G4) 52 mm
17Readout electronics
Control room
Slow control
Ethernet
MAB
Chamber
Slow control for barrel muon chambers
Board computer
AMPRO Littleboard P5i (PC104 type) 146x203x30 mm3
CAN
- 100/166 MHz Pentium processor
- PC/AT compatible system on a single board
- Up to 128M bytes onboard DRAM
- PC/104 with PCI extension
- Floppy, IDE, EPP, Parallel, 4 Serial ports
- PCI UltraSCSI
- PCI Super VGA LCD/CRT local bus controller
- with GUI accelerator
- High speed Ethernet LAN interface
- Extensive embedded feature set ruggedized
- BIOS, bootable solid state disk,
- watchdog timer, powerfail NMI, locking I/O
- connectors, Advanced Power Management
- Small size 5V only operation, low power
- requirement, extended temperature operation
I2C
Barrel muon chamber slow control unit
Temperature Sensors (4 to 16)
MAB - LEDs (0 to 20)
Z bar - LEDs (0 to 4)
Cameras (16 to 24)
4 LED holders (lt20 LED-s/holder)
18Minimal barrel test results Accurate
reconstruction of LED positions with a floating
calibrated MAB referenced by external system
- s(D5) 18 mm
- s(D4) 38 mm
- s(M5) 11 mm
- s(M4) 25 mm
- s(G5) 20 mm
- s(G4) 52 mm
19Readout electronics
Control room
Slow control
Ethernet
MAB
Chamber
Slow control for barrel muon chambers
Board computer
AMPRO Littleboard P5i (PC104 type) 146x203x30 mm3
CAN
- 100/166 MHz Pentium processor
- PC/AT compatible system on a single board
- Up to 128M bytes onboard DRAM
- PC/104 with PCI extension
- Floppy, IDE, EPP, Parallel, 4 Serial ports
- PCI UltraSCSI
- PCI Super VGA LCD/CRT local bus controller
- with GUI accelerator
- High speed Ethernet LAN interface
- Extensive embedded feature set ruggedized
- BIOS, bootable solid state disk,
- watchdog timer, powerfail NMI, locking I/O
- connectors, Advanced Power Management
- Small size 5V only operation, low power
- requirement, extended temperature operation
I2C
Barrel muon chamber slow control unit
Temperature Sensors (4 to 16)
MAB - LEDs (0 to 20)
Z bar - LEDs (0 to 4)
Cameras (16 to 24)
4 LED holders (lt20 LED-s/holder)
20Barrel alignment summary
- Prototypes of components exist
- Mechanical design of LED holders and video
cameras is ok - Final MAB design under development
- Neutron irradiation of the opto-electronic
components up to highest barrel doses (fluences
2.6 1012 n/cm2) ok - Magnetic field tests (up to 1T) of cameras, LED,
and board computer prototype ok - Readout electronics (prod. version) under
development - DAQ Software test version ready
- First test of the system concept ok consistent
with expectations - Full simulation of system performance (as for the
TDR)
21Endcap alignment status
- Mechanical progress
- Sensor developments
- DAQ and software
22Mechanical progress and Sensor technology
- Layout
- Most conflicts resolved
- Required some changes to the disk and cart
designs - SLM lines change z position due to RPC chambers
layout - Mount positions on CSCs defined Prototype mount
plates and towers constructed for ME23/2 chamber - Roughly 50 of transfer plate production drawings
finished -
- Sensor development
- The SLM design requires up to 10 sensors in line
- ALMY Semitransparent a-Si sensors (see later)
- DCOPS Digital CCD optical position sensor
- 4 linear CCDs mounted in a window frame
cross-hair laser beam - Readout with DSP processor and serial I/O
- Good test results on resolution stability
- Radiation test Test CCDs in 4 MeV proton beam
(neutron fluences of 1.3 1013 n/cm2 Þ Present
version of the CCD and readout are acceptable
(safety factor 3)
23DCOPS sensor board
24DCOPS neutron irradiation
25CCDs neutron irradiation
26DCOPS neutron irradiation
27Endcap DAQ and Software
- DAQ system (C in window98 env.) has two
branches - DCOPS readout chain
- Line of DCOPS boards read out through serial
interface - 1 serial processor / disk
- (Note that the read-out DAQ will be very much the
same for DCOPS and ALMY) - HP readout chain
- HP readout unit contains all multiplexers,
switches and signal conditioning hardware - 1 HP readout unit /disk
- Two steps offline analysis
- FLAP (First Level Analysis Program, C, OO
design on UNIX platform ) - Takes raw data from DAQ as input and fits data to
find centroid in CCD pixel numbers. - Convers HP DC voltage read out appropiate
position and temperature units - SLAP (Second Level Analysis Program)
- Takes FLAP output as input and converts the CCD
centroid pixel numbers to the real space
positions using the position calibration
constants - .... Design in progress
28Link system status
- Mechanical progress
- Sensor developments (ALMYs and Laser Level)
- DAC system and Software
29Mechanical progress
- Layout
- Mechanical drawings in the endcap/barrel region
(MAB and ME1/2) ready - ME1/1 transfer and mounts on ME1/1 CSCs prototype
drawings exits -
- Re-design of the h 3 region in accordance with
the EE calorimeter support - TK region in standby ... (position and size of
passage re-defined for new geometry) - Complete prototypes for the ISR tests (tests of
mechanical behaoivor) - Laser box, Laser Level, distance meas
(mechanical tube optical and potentiometers),
periscope -short size, 40 cm-, DPSDs mounts,
re-positionings platforms - .
30Sensors develpoment (1)
- ALMY Semitransparent a-Si sensors
- Performance
- Linearity and resolution 5 mm
- Sensor fiducilization 1 mm (2D configuration)
- Radiation hardness
- - g (CIEMAT) up to 10 Mrad ok
- - n (ATOMKI) total fluence 1015 n/cm2 ok
- - p (24 GeV/c PS CERN) total fluence 1013
n/cm2 sensors still cooling down ... - Optical properties gt75 transmission
- Serial readout electronics
- New prototypes development
- Stuttgart succeeded to produce test structures
with dark currents as low as required. They
proceed now with the fabrication of the first
set of complete test sensors with final layout
and bonding pads until beginning of July. - This effort is carried out -within CMS- by
Spain. It is done in collaboration with the MPI
(Munich), institute involved in the alignment
of the muon chambers of the ATLAS experiment. - Minnesota produced (by Feb 2000) two complete
prototypes (with identical geometry as the old
EGG sensors). Their optical and electrical
properties have been studied at CIEMAT-Madrid. - The electrical test was not satisfactory the
sensors did not show the typical diode curve.
Instead, they yield IV curves rather symmetric
with respect to the (0,0) point which correspond
to two mutually inverted Schottky barriers.
This behavior was understood given the high
symmetry of the structure (ITO/intrinsic
a-Si/ITO) of the prototypes. Two lines of
actions have been identified for the new
prototypes to be built. - The optical test was instead rather
satisfactory. The measured transmission for both
devices was over 75 and quite flat over the
whole working region (wavelength 750-900 nm). - New prototypes ( 8 units) will be ready by
summer. We will be testing mainly the electrical
properties of the junction and charge division
between strips, given that the optics is already
properly understood. - This effort was supported -within CMS- by US
and Spain until beginning of 2000. It will
continue mainly by Spanish institutes.
31Semitransparent aSiH sensors (ALMY)
- Thickness aSi 1 mm
- Thickness electrodes 100 nm
- Thickness glass substrate 500
mm - Number of electrodes 64 horizontal, 64
vertical - Active area 20 mm 20 mm
- Strip pitch 312 mm
- Low Hall mobility Þ B field insensitive
- Amorphous Si Þ Rad. hardness
- Glass substrate Þ Multi-point meas.
19 mm dia.
32Sensors develpoment (2)
- Laser Level units
- Consist of
- A laser source a tiltmeter (AGI and AOSI) one
or two dimensional -
-
- Performance
- Linearity and resolution 10 mrad (independent
tilt calibration) - Stability of the assembly lt5 mrad
- Radiation hardness and insesitivity to B to be
tested - - From manufacters (AGI) ok up to 10 Mrad g
doses -
insensitive to uniform fields, and ok up to 80
gauss/mm
33Tiltmeter (AGI-756) calibration linearity,
resolution and stability
V(mV) 460.35 mV/mrad ?(mrad) - 16.39 mV
After stabilization ? 1.9 ?rad TOTAL 6.7 days
34Laser level calibration and mechanical stability
35DAQ and Control system Software
- DAC configuration
- Level 1 includes sensors and local electronics
boards(LEB) - LEB microcontroler with flash program memory and
data memory CAN controler chip - The microcontroler is equiped with ADC
convertors to handle the signal coming from the
diferent sensors used (temperatutre, DPSD,
tiltmeters,..), a serial port, timers for signal
generation and several digital I/O ports to
control the 2D position sensors. - It will perform basic treatment of the signals
(center of gravity, gaussian fits..) - At the moment each LEB handles up to 4? sensors
(any type) sitting at lt xx m from the actual
devices. - Level 2 comunication via CAN bus between L1 and
industrial PC - Each LEB comunicates via CAN bus protocol with
the PC using a Main Controler Interface (a CAN
controler board with two ports) placed in the PC - PC for data storage and processing
- Level 3 comunication via Ethernet between
align. PC and Detector Control System (DCS) - Software
- Level 1 LabView (programming graphic platform)
for data acquisition and control. Fully developed
for system tests - Level 2 CMS OO code for optical alignment
(COCOA). Simulation and reconstruction
package.(ISR version available)
36Planned activities (Y2000)
- Complete test with Link system, Barrel and Endcap
alignment (ISR-I4) - The installation of components and DAQ started
last week (May 10th) - 5 weeks for individual calibration of parts
- First common data taking by 20 June.
- The full setup will stay in place up to end of
the year - EDR foreseen for October
- Endorse the general scheme
- LED holders for the DT chambers first to go into
production -
37(No Transcript)