Title: SAACE Membership survey June 1998
1Welcome to CESA Presentation Best Practice
Guideline - Procurement of Consulting Engineering
Services
2- Introduction
- Background
- The seminar is a culmination of the CE
Procurement Indaba conducted under the banner of
CESA during Feb 2008. - A task team was established to draft a
simplified step-by-step Best Practice Guideline
Manual for Procurement Consulting Engineering
Services. - To be rolled-out to all the twelve regions of
CESA. - George - marks the 11th roll-out, where the
manual is being launched. - The manual was drawn up in collaboration with
the CIDB, (many thanks to CEO Programme
Manager Procurement and Delivery).
3- Introduction (contd)
- Objectives
- To inform and capacitate clients and consulting
engineers (trusted/ independent advisor / agent
of client) with best practice in procurement - Enable CEs to appropriately respond to calls for
consulting engineering services and to deliver
these services in a true valueadded context - To assist both Client and CE to better understand
and implement the requirements of procurement
contracts ito CIDB Treasury legislation - To provide CEs and clients a platform to make
suggestions to the best practice procurement
guideline manual (living document), which will be
updated regularly to reflect the challenges faced
by our industry. - Manual is available on http//www.cesa.co.za/
at no charge. - Comments to wallym_at_cesa.co.za
4- Introduction (contd)
- Outline of the CESA Guide/Briefing
Chapter 1. Project Life-cycle background of typical project life cycle
Chapter 2. Consulting Services - typical CES provided by CEs
Chapter 3. Procurement of Consulting Services - legislation and objectives
Chapter 4. Scope - expanded description of elements of scope
Chapter 5. Tender Documentation for CES - preparing tenders for CES
Chapter 6. Value Added Services value of additional CES
Chapter 7. Evaluation of tenders - Guidelines on evaluation of CES tenders
Chapter 8. Performance monitoring Suggested framework for CPE.
5- The technical briefings are geared towards
creating a conducive sustainable procurement
environment to enhanced infrastructure delivery. - Ensure that the right firm(s) are appointed for
the right job - Appointment at a reasonable level of
compensation - ensure continued existence and development of
firm(s) and industry - serve the best interests of public
- Hence the theme of our Technical Briefing today
is, Walking together towards a Sustainable
Procurement Environment.
Introduction Re-cap
6Right firm for the right job
Example right firm for the right job Three
relatively easy questions for a House Bridge
Consulting Engineer Question 1 How much
does a house weigh? Question 2 How much
weight can a rural two-lane bridge Hold???
7Qualified firm for the right job
otherwise house becomes a bridge
8Competent firm for the right job
a bridge that cannot be used
9Appropriate Consultant for the right job
a house that cannot be used
10Right firm for the right job
And Question 3 Would this be covered by
PI, Home insurance, car insurance, or, does
it come under the roadside accident fund
??? ----------------------------------------------
--------------------------------------------------
----------------
We can all relate to this, e.g. 40 000 defective RDP houses to be flattened and rebuilt at a cost gt R1-billion.
delivers questions rather than intended
product
11Right firm for the right job
We can relate to this R4 million bridge swallows
a taxi!
delivers questions rather than intended
product
12(No Transcript)
13- SESSION 1
- 1.1 Consulting Engineers South Africa
- 1.2 Consulting Engineering Industry
- 1.3 The Foothold Definitions
- 1.4 The Project Life-Cycle
- 1.5 Overview of Consulting Services
14- 1.1 Consulting Engineers South Africa
-
15- CONSULTING ENGINEERS SOUTH AFRICA (CESA)
- History
- SA Association of Consulting Engineers (SAACE)
established in 1952 - Voluntary association of independent CEs in
private practice - August 2008 - SAACE transformed to CESA
- Employing more than 22 000 people
- Members interests
- CESA seeks to promote interests of Members and
Clients by - Regular liaison meetings
- Publication of documents relating to profession
- Compiling Advisory Notes for Members and
Clients - Guidelines to Members on professional practice
matters
16- CONSULTING ENGINEERS SOUTH AFRICA (continued)
- Professionalism and Integrity of Members
- 1. In general
- ECSA registers professional individual
engineers, technologists etc - CESA registersprofessional CE Firms through
membership - 2. Credibility of applicants
- In business gt 12 months
- Nominated by an existing CESA member
- CIPRO registered - bona fides, directors
governance structures - Not fly-by night
- 3. Ongoing requirements
- Subject to CESA Code of Conduct gives Clients
recourse - Disciplinary Committee - non-compliance
- Ownership/principals gt 50 Pr Engrs/Technos
engineering focus - No contracting work (construction) - no
conflict of interest
17- 1.2 Consulting Engineering Industry
- Consulting Engineering Industry Overview
- Construction Industry - Enabler Regulator
-
18 Consulting Engineering Industry Overview
19- THE CONSULTING ENGINEERING INDUSTRY
- The birth
- The word engineer first appeared in the 15th
Century, in - reference to a particular group of
professionals in the military - Associations formed to exchange experiences and
to improve - the status of engineers
- It was then legalised to safeguard the health
and welfare of the - general public
- The licensing procedures were intended to stop
people from - selling engineering services when they were not
trained or - qualified in the practice of engineering.
20- THE CONSULTING ENGINEERING INDUSTRY (continued)
- The present
- Take-over of engineering services by the
un-qualified - (e.g. Tenderpreneurs, tender syndicate, etc)
- Due to tendering process
- Which disregard engineering ability/technical
competence of CE
21- THE CONSULTING ENGINEERING INDUSTRY (continued)
- The future
- Competitive tendering is here to stay
- it must not be used to drive professional fees
down - The struggle continues professionalism,
reservation of - engineering work and use of appropriate
procurement methods - FIDIC Report Engineering Our Future
Change is upon us there is no future in the
status quo industry must adapt. --- Firms must
grow in capability and scope of services to meet
the client demands. We must move up the food
chain to a new set of value-added services for
our clients.
22THE WORLD WITHOUT ENGINEERS
23THE WORLD WITHOUT ENGINEERS
24 The Construction Industry Enabler and Regulator
25- The Construction Industry Development Board
(CIDB) - Established by and gets its mandate from the CIDB
Act (38 of 2000) - Aims
- Promote sustainable growth of the construction
industry and sustainable participation of the
emerging sector in the industry - Promote improved performance and best practice
of public and private sector clients, contractors
and other participants - Promote procurement and delivery management,
the uniform application of policy throughout all
spheres of government, uniform and ethical
standards all guided by a Code of Conduct - Establish registers as a tool to systematically
regulate and monitor the performance of the
industry and its stakeholders - Register of Contractors(RoC)
- Register of Projects (RoP)
- Register of Professional Service Providers
(RoPSP)
26- CIDB (continued)
- Register of Professional Service Providers
(RoPSP)
27- CIDB (continued)
- CIDB documentation/prescripts (www.cidb.org.za)
- Standard of Uniformity (SFU)
- Code of Conduct
- Practice notes
- Legislation
- Code of Conduct establishes certain standards of
behaviour - Behave equitably, honestly and transparently.
- Discharge duties and obligations timeously and
with integrity. - Comply with all applicable legislation and
associated regulations - Satisfy all requirements established in
procurement documents - Avoid conflict of interest
28- CIB (continued)
- Monitoring role - CIDB can
- Conduct investigations
- Sanction offenders
- Suspend offenders from the CIDB RoC
- Issue fines to Employers up to R100 000
- Intergovernmental Relations Framework Act
liaises with - Treasury
- Public Protector
- Auditor General
- CESA/ CIDB Collaboration
- CESA consulted extensively with CIDB in compiling
the Manual/Guide for Procurement of CES because
CIDB - Regulates public sector procurement (large CESA
Client base) - Complies with applicable legislation/
regulations - Authority to enforce compliance
- Good working relationship
29- 1.3 The Foothold Definitions
30- THE FOOTHOLD DEFINITIONS
- Conformity of Terminology
- Terminology in Manual conforms with CIDB
documentation and - ECSA Guideline Scope of Services and Tariff of
Fees - Mainly aligned with CIDBs Revised SFU in
Construction Procurement - Noteworthy Examples
- Bid Tender
- Client he/she who engages the Consulting
Engineer (CE) - Construction Monitoring (administration of
Construction Contract for - verification only) new term
- Contract Agreement between Client and CE
31- Noteworthy Examples (contd)
- Engineering and Construction Works contract
includes construction, - repair, maintenance, alteration, demolition
etc of building and - engineering infrastructures
- Normal Services Typical services as in ECSA
guideline tariffs - Quality Totality of features of a service
that bears on its ability to - satisfy stated or implied needs
- Scope of Services Services undertaken by the
CE in relation to the - Scope of Work
- Scope of Work Portion of the Works for which
the CE is engaged - Tender Price Price submitted including all
payment conditions, costs - and disbursements
32- 1.4 The Project Life Cycle
-
33(No Transcript)
34- THE PROJECT LIFE CYCLE (contd)
- Steps 1 to 3 Identification, Definition,
Feasibility - Identifying the potential project often by
Owner, Specialist assistance - And Defining the best project to meet the need
- Reject unsuitable solutions, shortlist suitable
alternatives - Select the best project, based on technical and
financial feasibility - Steps 4, 5, 6 Concept Viability, Design,
Procure - Developing the project through all concept and
viability stages, confirm viability - Detail design of the project to procure
construction - Design can be a maintenance/operation assignment
- Procuring a contractor to construct proper
tender/contract documents, proper evaluation of
tenders
35- THE PROJECT LIFE CYCLE (contd)
- Steps 7, 8 Construct, Operate and Maintain
- Construction - from site handover to when Owner
takes possession of the constructed project - Final handover after Defects Liability Period
expired and defects rectified - Operation and Maintenance
- Usually by Owner - According to manuals and own
procedures - O M - May be contracted out
- Note CE may be appointed for any one, or all,
of the steps 1 to 8
36- 1.5 Overview of Consulting engineering
- services
-
37CONSULTING ENGINEERING SERVICES
- Consulting engineering services include many
Engineering Disciplines inter alia - Agricultural
- Civil
- Construction Management
- Construction Project Management
- Electrical
- Geotechnical
- Mechanical
- Structural
- Transportation
- Specialist Engineering Services
-
38- CONSULTING ENGINEERING SERVICES (contd)
- Deliver Value
- 1. Early project stages
- Services deliver most value
- Functionality quality of the proposed service
more important than Cost (Steps 1 to 3) - 2. After project is well defined
- Services are easier to determine
- Role of high level expertise reduces as project
develops - Efficient more routine tasks more important
- Correct/comprehensive contract documentation is
vital
39REQUIRED EXPERTISE OVER THE PROJECT CYCLE
40(No Transcript)
41- SESSION 2
- 2.1 How to Procure Engineering Services
42HOW TO PROCURE CONSULTING SERVICES
43HOW TO PROCURE CONSULTING SERVICES (Contd)
- Important that Government recognises
- CEs are an important pool of expertise and
skilled resources - High standard of engineering and Infrastructure
development vital for growth - National Treasury policy statements
- It is necessary that certain minimum standards
of quality and efficiency be achieved when
appointing consultants - Need to maintain a basic policy of competitive
selection - Legal Environment for consulting engineering
services - Constitution of South Africa
- System is to be Fair, Equitable, Transparent,
Competitive, Cost effective - Adopted by ISO in ISO 10845 series for
construction procurement
44HOW TO PROCURE CONSULTING SERVICES (Contd)
- TABLE PILLARS OF PROCUREMENT
45HOW TO PROCURE CONSULTING SERVICES (Contd)
- Procurement - Need to maintain a reasonable
Balance between Competition Compensation
46HOW TO PROCURE CONSULTING SERVICES (Contd)
- Primary Legislation Regulating Procurement
Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective Constitution of the Republic of South Africa (Act No. 108 of 1996) - Section 217 states that government procurement systems must be Fair, Equitable, Transparent, Competitive and Cost Effective
Fair, Transparent, Competitive, Cost Effective Fair, Transparent, Competitive, Cost Effective Fair, Transparent, Competitive, Cost Effective Equitable Equitable
Public Finance Management Act (Act No. 1 of 1999) Municipal Finance Management Act (Act No. 56 of 2003) Construction Industry Development Board Act (Act No. 38 of 2000) Preferential Procurement Policy Framework Act (Act No. 5 of 2000) Broad Based Black Economic Empowerment Act (Act No. 53 of 2004)
PFMA MFMA CIDB PPPFA BBBEE
Public Sector Clients Public Sector Clients Public and Private Sector Clients Public Sector Clients Public and Private Sector Clients
Point to Note Compliance with CIDBs Standard
for Uniformity in Construction
Procurement (SFU) compulsory for organs of
state
Refer to Table 3.2 (pg 11-12) in Manual - 10 Acts)
47HOW TO PROCURE CONSULTING SERVICES (Contd)
- Objectives of Procurement
- Procurement is engaging skilled professionals
not purchase of a - commodity
- Purpose of competitiveness is to ensure long
term value for money not - short term low cost design
- Transparency must encourage professionals to
develop maintain - their skills and expertise
- CIDB Guidelines can provide the necessary
results - Methods of Procurement
- 1. Financial Offer
- 2. Financial Offer plus
Preference - 3. Financial Offer plus Quality
(Functionality) - 4. Financial Offer plus Quality
plus Preference - Prescribed by CIDB Standard for Uniformity
(SFU) - Services must provide cost-effective
value-added performance
48 HOW TO PROCURE CONSULTING SERVICES (Contd)
- CESA Recommends - Method 4
- Quality and Cost-based Selection (QCBS)
- Accords with CIDBs SFU (Standard for Uniformity)
- Based on CIDBs Best Practice Guidelines for
Competitive Selection - CIDB states - Method 4 applies in all but small
minority of cases - Method 4 is MANDATORY for public bodies
- However,
- the KwaZulu Natal High Court, Pietermaritzburg,
case no 10878/2009 relegates functionality/
Quality to a pre-qualification criteria(using a
minimum threshold). Thus rendering Method 4 to
be invalid.
49HOW TO PROCURE CONSULTING SERVICES (Contd)
Competitive Selection Procedures
50HOW TO PROCURE CONSULTING SERVICES (Contd)
- Points to Note
- 1. Quoting from CIDB Best Practice Guideline A7 -
Procurement of professional services should be
undertaken on - demonstrated competence qualifications (for
type of services required) - capacity capability (to provide the quality
of the service) - fair reasonable Financial Offers (not only
least cost) - 2. Constitution requires procurement to be cost
effective have best value outcomes in terms of - quality,
- downstream life cycle costs,
- timing
- Financial Offer
- least resources to effectively manage control
the procurement process. - 3. Selection on basis of quality does not
necessarily mean the best quality available but
quality appropriate for the assignment.
51HOW TO PROCURE CONSULTING SERVICES (Contd)
- Points to Note (contd)
- 4. Calling for/ preparation of Tenders
- Scope of Work and Services (SOWS)
- fully describe SOWS - comparable tenders are
received - fully describe SOWS - reduce time effort for
tender preparation - Total Input Cost
- can be considerable - small projects can be gt
potential fee jeopardise - finances of the service provider
- overall economy of the project.
- Guideline
- CEs potential fee should be 20 times gt cost of
preparing tender - alternatively, cost to prepare tender should
not gt 5 of potential CE fee - potential CE fee has to cover - Staff costs,
overheads, expenses and profit - hence tenders should not be solicited for small
projects,
52HOW TO PROCURE CONSULTING SERVICES (Contd)
- 4. Calling for/ preparation of Tenders (contd)
- The following procedure should preferably adopted
by client or CE (as agent of client) - Consider grouping small projects together
- Request proposals for term contracts - where
consulting engineer can support the client on a
partnership basis for all small to medium
projects over a longer period - Listing manuals and procedures as requirements
so lengthy technical proposals are not required
(only proposed staffing track record)
53(No Transcript)
54- SESSION 3
- 3.1 Scope of Services
- 3.2 Tender Documentation for Consulting
- Services
55 56SCOPE OF SERVICES
- Definition
- Scope of Services Services which a CE must
provide in relation to scope of Work - MUST be clearly defined to ensure proper pricing
and clear and unambiguous understanding by
tenderer - In many instances this is lacking uncertainty
and unrealistic pricing result - Recommended listing DELIVERABLES to be produced
by the CE, i.e. products of his work (studies,
reports, designs, drawings, documents etc) -
57SCOPE OF SERVICES (contd)
- Planning Studies, Investigations and Assessments
- (i) Consultation with the client or clients
authorized representative. - (ii) Inspection of the site of the project.
- (iii) Preliminary investigation, route location,
planning and a level of design - appropriate to allow decisions on
feasibility. - (iv) Consultation with authorities having rights
or powers of sanction as well - as consultation with the public and
stakeholder groups. - (v) Advice to the client as to regulatory and
statutory requirements, including - environmental management and the need for
surveys, analyses, tests and - site or other investigations, as well as
approvals, where such are required - for the completion of the report, and
arranging for these to be carried out - at the clients expense.
- (vi) Searching for, obtaining, investigating and
collating available data, - drawings and plans relating to the works.
- (vii) Investigating financial and economic
implications relating to the - proposals or feasibility studies.
58SCOPE OF SERVICES (contd)
- Scope of Services Stages for a Typical Project
59SCOPE OF SERVICES (contd)
- Detailed examples (Appendix A)
- Refer to Appendix A, Numerous Normal Services
tasks under Stages 1 to 6 - Includes Activities/Deliverables
- Recommended as a reference or checklist per stage
- Principal Consultant
- Refer to Appendix A, Additional Services to
Normal Services - Includes Activities/Deliverables
- Recommended as a reference or checklist per stage
60SCOPE OF SERVICES (contd)
- Key Factors common to every scope, in Developing
the Scope of Services - Obligations of the Parties
- Health and Safety
- Sustainability
- Information Available
- Scope MUST reflect Clients intentions to enable
tenderers to identify tasks and estimate times to
be spent by personnel, and hence to quantify and
price the tender - Failure to prepare Scope of Services in
sufficient detail - Tenderer has to make assumptions
- Misinterpret Clients requirements
- Price unnecessarily for Risks
- Resultant prices too low or too high
- Fails the interests of Client, Consulting
Engineer and Project
61SCOPE OF SERVICES (contd)
Key Factors in Developing Scope Services - TABLE
62THE SCOPE OF WORK
- Definition
- Not the same as Scope of Services of the
Consulting Engineer - Scope of Work portion of the Works for which
the Consulting Engineer is engaged or the
document which specifies and describes the
supplies, services engineering and construction
works to be provided (by the Contractor)
including special requirements, constraints etc. - Example
- A client wishing to construct a Casino complex
consisting of three distinct components being the
Building, a Parking Area and an access road, may
appoint a consulting engineer to undertake Stages
3-6 of the normal engineering services for the
Parking Area. In this case the scope of services
can be defined as set out in Appendix A while the
scope of work may only involve the Parking Area.
Some thought will have to go into preparing the
scope of work as it interfaces with other works
such as stormwater runoff from the building and
the interface with the access road and gate
house.
63THE SCOPE OF WORK (contd)
- Points to Note
- The scope of work for each service provider
should be carefully - determined to ensure that no overlaps and
duplication in terms of scope of work exist. - In some cases the consulting engineer will be
required to - appoint specialist sub-consultants in which case
the consulting engineer will ensure that no
duplication in terms of scope occurs.
64THE SCOPE OF WORK (contd)
- Examples of Scope of Work
65THE SCOPE OF WORK (contd)
- Examples of Scope of Work (contd)
66- 3.2 Tender Documentation for Consulting
- Services
67TENDER DOCUMENTATION
- Purpose
- In line with principles and documentation of the
CIDB - To achieve uniformity, in interests of a more
efficient industry - Model for Uniformity
- CIDBs Construction Procurement Toolbox
- Process of Offer and Acceptance
- Tenderers provide inputs to complete their
submissions (offers) - These inputs to the contract to be concluded
after acceptance of offer - Separation of component documents
- Complete enquiry documentation critical to
projects success - CIDB tables to assist compiling documentation
See Appendix B
68TENDER DOCUMENTATION contd
- Documents relating to the Tender
-
69TENDER DOCUMENTATION contd
- Documents relating to the Form of Agreement
-
70- TENDER DOCUMENTATION (contd)
- Standard Coloured Pages/Dividers
- T1.1 Tender Notice and Invitation to
Tender White - T1.2 Tender Data Pink
- T2.1 List of Returnable Documents Yellow
- T2.2 Returnable Schedules Yellow
- C1.1 Form of Offer and Acceptance Yellow
- C1.2 Contract Data Yellow
- C1.3 Form of Guarantee/Securities White
- C1.4 Adjudicators contract White
71- TENDER DOCUMENTATION (contd)
- References
- Revised Standard for Uniformity in Construction
Procurement (SFU) - CIDB Construction Procurement Best Practice
Guideline C3 Adjudication - CIDB Professional Services Contract
- PROCSA Form of Agreement
- FIDIC Client/ Consultant Model Services Agreement
- Standard Professional Services Contract by NEC
72(No Transcript)
73- SESSION 4
- 4.1 Value-added Services
74- VALUE ADDED SERVICES
- Value, Financial Offer, Quality
- Acceptance of lowest price denies opportunity to
assess value - Consulting Engineers are accustomed to tendering
competitively - Professional services, unlike products, are not
well defined - Requires careful descriptions in Scope of
Services, Scope of Work - Still a tendency to rely on price, ignore quality
(Treasury Functionality) - Remuneration should reward desirable performance
- What performance is achieved from the lowest
price? (examples..) - Life-cycle costs Eng. 2, Constr. 18, OM 80
(2 dictates 98 !) - Financial offers should reflect effort to
optimise costs of project - Relationship between Financial Offer Quality
(Effort) is not linear
75VALUE ADDED SERVICES
76VALUE ADDED SERVICES contd
- Life-Cycle Cost and impact on Project Success
- The procurement of consulting engineering
services has the greatest impact on the
life-cycle cost of the project, yet it is the
least costly component - Life-Cycle Cost
- Impact on Project Success
- Engineering
Construction Operations
Maintenance
10
50
40
60
20
20
77VALUE ADDED SERVICES contd
- The Concept of Value
- Value should
- secure for the client value-for-money services
- achieve minimum life-cycle costs (long term value
for money) - Ensure the project will fulfill its intended
purpose - The tender process must allow the tenderer to
show that - value-for-money services are offered
- minimum life-cycle costs are critical to the
projects success - The Financial Offer will demonstrate the value of
inputs offered - Take Clients quality evaluation criteria into
account - Quantifying Value
- Needs to be a factor in considering tenders
- Include in determination of tender score
- Assess Preference, Quality, and Financial Offer
(Price) individually - Consulting Engineer to tender accordingly
78VALUE ADDED SERVICES contd
- Guidelines for Pricing of Tenders the Golden
Rules - Project success relies on acceptance by client
of the Consulting Engineers financial offer and
conditions - Consulting Engineer needs to have his interests
protected - Client needs to be comfortable with contract
financial arrangements - Golden Rules apply to preparation of the
financial offer - Golden Rule No. 1 Know the project requirements
- No two projects the same offer
- Must be a clear and unambiguous Scope clarify
if necessary - Determine methodology, inc. innovation,
value-adding procedures - Take Clients quality evaluation criteria into
account
79- ILLUSTRATION OF TOTAL COSTS
- Golden Rule No.2 Know your costs involved
80- VALUE ADDED SERVICES (contd)
- Golden Rule No. 3 Know the Clients situation
- Able to produce and adhere to a clear and
sufficient scope - Ability to fund or timeously secure funding for
the project - Adequate resources to administer the contract
- History of fees paid on time
- Sufficient technical capability for reviews and
approvals - Need for development (training, mentoring, etc)
- Experience in using consulting engineering
services - Able to responsibly evaluate award
consulting/construction contracts - Finalising the Tender Price
- Feedback from Golden Rule No 3 is to be
considered where aspects within Clients ambit
must be examined, for influence on level of the
financial offer
81- VALUE ADDED SERVICES (contd)
- Adjustments from Golden Rule No 3
- Profit mark up
- Pricing for contingencies or risk
- Pricing work not called for but necessary (if not
done by Client) - Pricing for unrealistically tight or slack
deadlines - Pricing for work assumed but not required
- Adding a margin in lieu of qualifying the tender
- Provision for productivity delays to be expected
in executing the work for the client - Price Benchmarks
- Important to test pricing against a norm and
indicate adequacy of price - Appropriate Benchmark ECSA Guideline Tariff of
Fees - Percentage of Project Cost (sliding scale) x
Factor for Stage and Type - Also ECSA recommended hourly rates arrive at
Benchmark Fee - Adjust up or down for project concerned, with a
Benchmark Multiplier, to get an Adjusted
Benchmark Fee considering specific circumstances
82VALUE ADDED SERVICES contd
- Benchmark Multipliers
-
-
-
-
-
- Specific circumstances
- Is scope complete and clear?
- Is Client well versed in procuring consulting
services? - Does Client have adequate resources for competent
tender evaluation? - Does Consulting Engineer have a successful
project record with the Client?
Multiplier Circumstances
0.6 1.0 Favourable
1.0 Normal or Reasonable
1.0 1.6 Negative
83VALUE ADDED SERVICES contd
- Specific circumstances (contd)
- Is project location advantageous for the
Consulting Engineer? - Will the risks perceived be easy or difficult to
handle? - Is level of complexity of the project normal or
will it be very complex? - Will the risks perceived be easy or difficult to
handle? - Is level of complexity of the project normal or
will it be very complex? - Does the Consulting Engineer have a low order
book and need the work? - Will start date and duration require price
adjustment, if no escalation?
84VALUE ADDED SERVICES contd
Specific circumstances Benchmark Multipliers Benchmark Multipliers Benchmark Multipliers
Favourable (0.6 1.0)/ Reasonable ( 1.0) / Negative (1.0 1.6) F R N
Is scope complete and clear? 1.0
Informed client 0.9
Previous appointments 1.2
Savings Previous experience 0.6
Project location 1.0
Staff cost, suited competent 0.8
risks perceived be easy or difficult to handle? 1.3
level of complexity of the project normal or will it be very complex? 1.0
Does the Consulting Engineer have a low order book and need the work? 0.7
AVERAGE ( this example) 0.94 0.94 0.94
85VALUE ADDED SERVICES conclusion(1)
- Adjusted Benchmark (Yardstick) Fee
- Average of the sum of all the particular fees
used - Still based of ECSA recommended fee scales
-
- THERE IS NO SUCH THING AS A DISCOUNTED FEE
86VALUE ADDED SERVICES conclusion(2)
87(No Transcript)
88- SESSION 5
- 5.1 Evaluation of Tenders
89- EVALUATION OF TENDERS
- References
- CIDB Best Practice Guideline No. A4 Evaluating
Quality in Tender Submissions (guidelines) - CIDB Inform Practice Note No. 9 Evaluation of
Quality in tender Submissions (overview) - Evaluation of Tenders
- Applies where Quality consideration is an
essential part of the evaluation process which
should apply to the vast majority of tenders for
Consulting Engineering services - Procurement Method 4 generally appropriate for
Consulting Engineering services (Quality and
Cost-Based Selection)
90- EVALUATION OF TENDERS
- Method 4 Financial Offer plus Quality plus
Preference - Score Quality, rejecting all offers that fail to
score minimum points for Quality, stated in
Tender Data - Score tender evaluation points for Financial
Offer - Confirm tenders eligible for preferences claimed
and if so score tender evaluation points for
preferencing - Calculate total tender points
- Rank tenders from highest number of tender
evaluation points to lowest - Recommend Tender with highest tender evaluation
points for award, unless compelling reasons not
to do so
91- EVALUATION OF TENDERS (contd)
- Evaluation criteria
- Essential that tender documents state evaluation
criteria and scoring systems to be used in tender
adjudication - If a criterion is stated, clarity required how
the criterion will be adjudicated and weighted,
relative to other criteria - CIDB Standard for Uniformity Sect. 4.4.3 calls
for specific Tender Data - Method to be used in evaluation
- Weighting between Financial Offer (W1), Quality
(W2), and Preference (W3) - Quantified descriptions of preferences incl. how
granted and scored - (Refer also to Construction Scorecard
(Construction Sector Charter, Govt Gazette Board
Notice 862 of 2009) - Details of Quality Criteria and Sub-criteria and
manner of scoring
92- EVALUATION OF TENDERS (contd)
- Recommended Approach, to be Fair, Equitable,
Transparent, Cost-effective - Quality of outputs/deliverables to satisfy client
requirements - Service with reasonable skill and care of
professionals - Advice independent of any affiliation causing
conflict of interest - Repeat/straight forward projects
Cost-effective design important - Feasibilities, Complex projects experience,
expertise important - Weighting, Quality / Financial Offer is less for
repeat type projects - All tenders to have a minimum number of Quality
points, to proceed - Ratio Quality / Financial Offer plus Preferences
depends on project value - Preferential Procurement Framework Act
- Assignments under R500k value, Ratio 8020
mandatory - For higher value assignments, Ratio 9010
mandatory - (Threshold as in Pref. Procurement Policy
Framework Act Regs) - Refer Tables based on CIDB references with
certain CESA adjustments, pertaining to Scoring
against Ratings
93- EVALUATION OF TENDERS (contd)
- Recommended Detail Procedure
-
- Score Quality with 3 Quality reviewers, adjust if
major scoring differences - Reject tenders not attaining minimum Quality
score, inform them in writing - Inform tenderers of time date for opening
Financial Offers and announce these at the
meeting - Calculate Final Evaluation Scores according to
CIDB Standards for Uniformity - Apply Definitions and formulae (see next slide)
- Mutually exclusive criteria recommended, to limit
duplication - Black persons are addressed in allocating
Preferences - Reviewers need to be experienced. If not
available in the Client, then specialists or
Consulting Engineers (unconnected with the
tender) should be retained by the Client to
assist with evaluations - See recommended Tables and Examples
94- EVALUATION OF TENDERS (contd)
- Definitions and formulae used
- Nev Total evaluated score
- Nm Score for Price
- Nq Score for Quality
- Np Score for Preferencing
- W1 Weight assigned to price
- W2 Weight assigned to quality
- Nm W1 x Pm/P where Pm is lowest qualified
tender price received and P is tender price under
consideration (2 decimal places) - Nq W2 x S/Ms - where Ms is maximum possible
quality score and where S is quality score for
tender under consideration - Nev Nm Nq Np - Tenders ranked from highest
to lowest Nev with - tender awarded to tenderer with highest Nev
95- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
- Table 7-1 Nature of Projects (5 types are
defined) - Feasibility Studies and Investigations (require
specialised skills deliverable a report) - Innovative Projects (require innovation,
creativity, expertise and skills specialist
advice needed is often identified in the project) - Complex Projects (require high level of technical
skills and resources may require skills other
than normal engineering) - Straightforward Projects (comprise straight
forward tasks with standard technologies may
need strong capacity and resources if project is
large) - Repeat Projects (Straightforward tasks with
routine/periodic activities, eg maintenance to
maintain Clients assets - The Descriptions of each type show that the
tenderers experience and - capability are key, particularly in types 1 to 4
96- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
(contd) - Table 7-2 Quality Criteria and Points Scale for
small projects - Quality plus Financial Offer/Preference ratio
8020 (i.e.. 20 points for BBBEE) - Maximum points shown for 5 Project Types from
Table 7-1 for BBBEE, Quality and Financial Offer,
Financial Offer and Quality - Higher points used for Quality in more complex
projects and lower points for Financial Offer - 9 Quality Criteria listed, from Adequacy of work
plan to Demonstrable managerial ability - Quality maximum points from (2) allocated to 9
Quality criteria allocation to 5 of the 9
Quality Criteria should suffice
97- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
(contd) - Table 7-3 Quality Criteria and Points Scale for
large projects - Quality plus Financial Offer/Preference ratio
9010 (i.e.. 10 points for BBBEE) - Maximum points shown for 5 Project Types from
Table 7-1 for BBBEE, Quality and Financial Offer,
Financial Offer and Quality - Higher points used for Quality in more complex
projects and lower points for Financial Offer - 9 Quality Criteria listed, from Adequacy of work
plan to Demonstrable managerial ability - Quality maximum points from (2) allocated to 9
Quality criteria allocation to 5 of the 9
Quality Criteria should suffice - Operation similar to Table 7-2
98- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
(contd) - Table 7-4 Indicators to be used when scoring
tenderers on Quality Criteria - Ratings, very good/good/satisfactory/poor
(100/70/50/0) with descriptors, listed for 9 x
Quality Criteria - Note poor scores zero criteria are
unacceptable for Consulting Engineering services
(see descriptors) - Ratings for 9x Quality Criteria are common to all
Project types
99- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
(contd) - Table 7-5 refers to Qualification and Competence
of Key Staff - To be completed by Client when issuing tenders
- Shows 6 x typical staff posts Project Leader,
Design Engineer, Materials Engineer, Contracts
Engineer, Resident Engineer and Assistant
Resident Engineer - Shows 5 x Project types (Table 7-1) for each post
- Lists 6 x attributes for each post
(qualification, experience thereafter ,
registration, experience thereafter, involvement
on comparable projects (past 10 years), project
values (past 6 years) - Client able to list preferred and minimum
attributes, Tenderer fills in the Offer column - Although Titles of Job posts state Engineer,
Client may choose to use Registered Engineering
Technologist or Registered Engineering
Technician, depending on nature of project
100- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
(contd) - Table 7-6 Assessment example
- Shows a worked example for a complex project in
the 9010 points system range with 5 of 9 x
Quality Criteria addressed - Weight assigned to each Quality Criterion
addressed. Total maximum points for Quality - Rating indicators from Table 7-4 applied to each
Quality Criterion by 3 reviewers to give
Reviewers scores and average scores - Weights applied to average scores to give points
for Quality, with total Points for Quality for
tender under consideration - Table shows 2 x sets of points for Quality
results 1st set 2 outliers, 2nd set no
outliers, after a repeat review by the reviewers
101- RECOMMENDED TABLES FOR EVALUATION OF TENDERS
- CESA recommended changes to CIDB Tables
- (in using Tables 7-1 to 7-6)
-
- Table 7-4 Ratings, very good/good/satisfactory/poo
r CIDB uses 100/90/70/40. CESA recommend
100/70/50/0 because - Descriptors for Poor (0) confirm unsatisfactory,
i.e. unacceptable - Good/Satisfactory mean nearly the same decrease
Good to 70 to compare with Very Good (100)
decrease Satisfactory 70 to 50. - Actual application of weightings, Quality /
Financial Offer depends on relative value of the
two criteria, e.g. Quality scoring 80 to 85 and
Financial scoring 50 to 100, Financial scoring
can outweigh Quality scoring
102(No Transcript)
103- SESSION 6
- 6.1 Performance Monitoring Consulting
- Services
104- PERFORMANCE MONITORING
- This presentation
- Performance Quality Assurance
- Evaluation of CEs Performance process
- Pillars of PM
- Consultant performance evaluation scorecard
- Points to Note
105- PERFORMANCE MONITORING
- Introduction
- Performance Evaluation of CEs is crucial in
upholding advancing the standards of service
from Consultants - Benefits of performance evaluation.
- The client will know the level of service being
delivered or delivered - The client will get an indication as to whether
his choice for consultant was correct - Ensures integrity of the QCBS process
- Assist in the pre-selection and bid evaluation
- raise the standard of consulting engineering
industry
106- PERFORMANCE MONITORING
- Introduction
- Other uses (by Client, CIDB, ECSA, NT, CESA, etc)
- Disciplinary action warning
- Suspension of firm(s) registration
- Cancellation of registration
- Black listing the firm
- Black listing the professional
107- PERFORMANCE MONITORING
- Performance Quality Assurance
- CE have a Quality Management System ISO 9001
2008 QMS or of similar levels ( a condition of
CESA membership) - ISO requires firms to conduct Client Satisfaction
surveys, analyse to show trends and confirm
improvement. - Enable flaws to be detected, thus avoiding more
costly deviation corrections - CE have adopted the principles of a Business
Integrity Management System, ( Part of CESA
members Code of conduct)
108- PERFORMANCE MONITORING (contd)
- Evaluation of CEs Performance process
- NT assigns PM to CFO suggest done with Project
Manager or Town Engineer - The process must commence from the time of
appointment and must continue until final
completion of the project. - Points to note during the initial briefing of
the consultant - The briefing must set a standard for performance
and discuss the evaluation process, as well as
describing the method of reporting required. - Client should provide feedback, so that the
consultant could improve if necessary
109- PERFORMANCE MONITORING (contd)
- Pillars of performance monitoring
- Criteria must relevant
- Criteria clearly defined to allow consistent
application confidential, rigorous and objective
manner - Conducted according to the Pillars of procurement
and CIDBs Code of Conduct
110- PERFORMANCE MONITORING (contd)
- Consultant performance evaluation scorecard
- CESA is proposing a comprehensive set of
evaluation criteria for gauging the performance
of CE.
111- PERFORMANCE MONITORING EVALUATION SCORECARD
112- PERFORMANCE MONITORING (contd)
- Points to Note
- Attributes choosing engineering consultants
- Technical competence
- Managerial ability
- Experience on similar projects
- Dedicated personnel available for the projects
duration - PROVEN PERFORMANE
- Local and/or local knowledge
- Professional independence integrity
- Conclusion - Turn to page 44
113(No Transcript)
114- CLOSING REMARKS
- This technical briefing has been presented in the
interests of a more efficient construction
industry, enhanced through the use of more
effective and uniform procurement -
- would like to thank
- Consulting Engineers and their Clients for
attending, and we wish you a safe onward journey
This technical briefing has been presented in the
interests of a more efficient construction
industry, enhanced through the use of more
effective and uniform procurement