Title: Heath Delzell


1
IDNR Engineering
  • Heath Delzell Engineering Bureau

Progress to Date and Timeline for Project
Completion Design and Construction Obstacles
2
Construction Activities
  • Phase 1 Dam and Spillway Renovation
  • Phase 2 - In-Lake Construction
  • Sediment Retention Basins
  • Sediment Removal
  • Shoreline Armoring
  • Universally Accessible Fishing Pier
  • Phase 3 Boat Ramp and Parking Lot

3
Progress Phase 1
  • History
  • 1991 Voids filled under spillway
  • 2007 Contracted French-Reneker Associates to
    determine cause
  • 2008 F-R concluded leak in weathered bedrock
  • Solution Remove weathered bedrock
  • Status
  • F-R Design complete and permitted for
    construction
  • Funding has been secured
  • Currently out for bids Letting date October 21,
    2010

4
Timeline Phase 1
  • Winter 2010
  • Early Start Date December 1, 2010
  • Portion of dam to be removed
  • Tree Clearing
  • Concrete Removal

5
Timeline Phase 1
  • Spring-Summer 2011
  • Excavate Core Trench
  • Construct Principal Spillway Outlet/Drawdown Pipe
  • Place Embankment Fill

6
Timeline Phase 1
  • Summer-Fall 2011
  • Place Embankment Fill
  • Construct Principal Spillway Inlet
  • Auxiliary Spillway Grading
  • Close Drawdown Pipe
  • Winter 2011 No Construction
  • Spring 2012
  • Final Grading
  • Project Complete May 31, 2012

7
Progress Phase 2
  • Sediment Retention Basins
  • Upper Arm Basin
  • Preliminary Design
  • Designed as a Sediment Pond
  • Filled with Dredge Material
  • 1-2 feet deep
  • State Contract for completion
  • Finish Design
  • Apply For Permit
  • Wetland Mitigation Plan

8
Progress Phase 2
  • Sediment Retention Basins
  • Campground Arm
  • Design Complete
  • Increasing Dam Height
  • Same function as Upper Arm Basin

9
Progress Phase 2
  • Sediment Removal
  • Design Complete
  • Removing sediment via mechanical means
  • Scrapers, Bulldozers, Excavators, Etc.
  • Shoreline Armoring
  • Design Complete
  • Placing Riprap in normally inaccessible locations
  • Universally Accessible Fishing Pier
  • Design 95 Complete

10
Timeline Phase 2
  • Winter 2010
  • Design and permit application complete January 1
  • Wetland mitigation
  • Spring 2011
  • Bid Letting March 17, 2011
  • Early Start Date May 1, 2011
  • Summer-Fall-Winter 2011
  • Construction
  • Spring 2012
  • Final Grading and Seeding
  • Project Completion March 15, 2012

11
Progress Phase 3
  • Boat Ramp and Parking Lot
  • Design is 25 complete
  • Schedule dependant on Phase 2
  • 1-2 Months for construction

12
Construction Obstacles
  • RAIN!!!
  • Dam construction would slow
  • Large storms can severely erode a partially
    constructed dam
  • Sediment removal would stop
  • Green Valley lt10 complete

13
Construction Obstacles
  • Perspective

55.3
54.3
48.4
44.0
40.5
Annual Precipitation for Brighton (inches)
30.2
1991 / 2008 1992 / 2009
1993 / 2010
14
Conclusion
  • Dam construction begins in December
  • Phase 2 starts Spring 2011
  • Boat Ramp starts Fall 2011 or Spring 2012
  • All phases should be complete and the lake nearly
    full by the end of May 2012