Fukushima Daiichi Nuclear Plant Reactor Design - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Fukushima Daiichi Nuclear Plant Reactor Design

Description:

... GE Mark I BWR Slide 4 Reactor and Control Rod Design Slide 6 Slide 7 Slide 8 Reactor Cavity and Fuel Pool Slide 10 Slide 11 Slide 12 Slide 13 Slide 14 ... – PowerPoint PPT presentation

Number of Views:377
Avg rating:3.0/5.0
Slides: 23
Provided by: aparateE
Category:

less

Transcript and Presenter's Notes

Title: Fukushima Daiichi Nuclear Plant Reactor Design


1
Fukushima Daiichi Nuclear PlantReactor Design
Event Summary
  • March 11, 2011 to Present

2
Presentation Overview
Kashiwazaki-Kariwa spent fuel pool during the
earthquake in 2007
3
Reactor Design GE Mark I BWR
Fuel Pool
Drywell Head
Reactor
Containment
Drywell
Suppression Pool
4
Reactor Building Elevation View and Under
Construction
5
Reactor and Control Rod Design
6
GE Mark I BWR Plant System Schematic
7
GE Mark I BWR Reactor System Schematic
8
GE Mark I BWR Fuel Pool
9
Reactor Cavity and Fuel Pool
10
Event Chronology - Initial Station Response
  • Nuclear reactors were shutdown automatically.
    Within seconds the control rods were inserted
    into core and nuclear chain reaction stopped.
  • Cooling systems were placed in operation to
    remove the residual heat. The residual heat load
    is about 3 of the heat load under normal
    operating conditions.
  • Earthquake resulted in the loss of offsite power
    which is the normal supply to plant.
  • Emergency Diesel Generators started and powered
    station emergency cooling systems.
  • One hour later, the station was struck by the
    tsunami. The tsunami was larger than what the
    plant was designed for. The tsunami took out all
    multiple sets of the backup Emergency Diesel
    generators.
  • Reactor operators were able to utilize emergency
    battery power to provide power for cooling the
    core for 8 hours.
  • Operators followed abnormal operating procedures
    and emergency operating procedures.

11
Event Chronology Loss of Make-up Water
  • Offsite power could not be restored and delays
    occurred obtaining and connecting portable
    generators.
  • After the batteries ran out, residual heat could
    not be carried away.
  • Reactor temperatures increased and water levels
    in the reactor decreased, eventually uncovering
    and overheating the core.
  • Hydrogen was produced from metal-water reactions
    in the reactor.
  • Operators vented the reactor to relieve steam
    pressure - energy (and hydrogen) was released
    into the primary containment (drywell) causing
    primary containment temperatures and pressures to
    increase.
  • Operators took actions to vent the primary
    containment to control containment pressure and
    hydrogen levels. Required to protect the primary
    containment from failure.
  • Primary Containment Venting is through a filtered
    path that travels through duct work in the
    secondary containment to an elevated release
    point on the refuel floor (on top of the reactor
    building).
  • A hydrogen detonation subsequently occurred while
    venting the secondary containment. Occurred
    shortly after and aftershock at the station.
    Spark likely ignited hydrogen.

12
Event Chronology Hydrogen Explosions
13
Event Chronology Core Damage Model
Core Uncovered
Fuel Overheating
Fuel melting - Core Damaged
Core Damaged but retained in vessel
Containment pressurizes. Leakage possible at
drywell head
Releases of hydrogen into secondary containment
Some portions of core melt into lower RPV head
14
Event Chronology Cooling Strategy
  • The station was able to deploy portable
    generators and utilize a portable pump to inject
    sea water into the reactor and primary
    containment.
  • Station was successful in flooding the primary
    containment to cool the reactor vessel and debris
    that may have been released into the primary
    containment.
  • Boric acid was added to the seawater used for
    injection. Boric acid is liquid control rod.
    The boron captures neutrons and speeds up the
    cooling down of the core. Boron also reduces the
    release of iodine by buffering the containment
    water pH.

Containment Flooding Effects
15
(No Transcript)
16
Current Station Status Report March 21
These are current reports from the website link
below which is to The Japan Atomic Industrial
Forum,Inc. (JAIF) It was incorporated as the
comprehensive non-governmental organization on
nuclear energy in Japan on March 1, 1956 (much
like WANO)
http//www.jaif.or.jp/english/
Status Report for March 21
Reactor Status Report for March 21
(To open documents, put cursor over document,
double click)
17
What does this mean to OPG and other Canadian
CANDUs?
The following letter was recently sent to OPG and
all other Canadian Power Reactors
(To open document, put cursor over document,
double click)
18
Station Photos of Damage
19
Station Photos of Damage
20
Station Photos of Damage
21
Station Photos of Damage
22
Station Photos of Damage
Write a Comment
User Comments (0)
About PowerShow.com