LCLS Commissioning Schedule and Startup Plan - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

LCLS Commissioning Schedule and Startup Plan

Description:

LCLS Commissioning Schedule and Startup Plan Schedule Overview Startup Test Plan PRD 1.1-002 Spells out our plan for turning on the LCLS systems. – PowerPoint PPT presentation

Number of Views:68
Avg rating:3.0/5.0
Slides: 16
Provided by: JamesW154
Category:

less

Transcript and Presenter's Notes

Title: LCLS Commissioning Schedule and Startup Plan


1
LCLS Commissioning Schedule and Startup Plan
2
Schedule Overview
Start XTOD commissioning
Time Now
1st beam on Linac axis
Start Undulator commissioning
Start of Operations (X-Rays to Far Hall)
UV Beam To cathode
Start LTU commissioning
CD-2a
CD-2b
2002
2003
2004
2005
2006
FY2008
FY2009
FY2003
FY2004
FY2005
FY2006
FY2007
FY2010
Construction
Operation
Project Engineering Design
Long-Lead Procurement
CD-3a
CD-3b
CD-4

CLOC
BTH, FH
Beneficial Occupancies
UH
DUMP
NH
3
(No Transcript)
4
12/06 UV Beam to Cathode
7/07 First Beam on Linac Axis
4/08 Start LTU Commissioning
7/08 Start Undulator Commissioning Start XTOD Commissioning
6 MeV
150 MeV
250 MeV
4.54 GeV
14.35 GeV
Single beam Dumper
Linac-X
rf gun
Linac-0
new
Linac-1
Linac-2
Linac-3
X Ray Diag.
Far Hall
25-1a 30-8c
21-1b 21-1d
21-3b 24-6d
X
Undulator
DL-2
BC-1
BC-2
DL-1
BSY
Tune up Dump
Dump
SLAC linac tunnel
LTU
5
Startup Test PlanPRD 1.1-002
  • Spells out our plan for turning on the LCLS
    systems. Currently working on rev-1.
  • Evolved from "Commissioning Document" discussed
    at previous workshop.
  • The editors continue to welcome your
    contributions!

6
(No Transcript)
7
(No Transcript)
8
Startup Phases
  • Phase I - low beam quality
  • BBA, radiation reduction, x-ray diagnostics, SR
    measurements
  • Phase II - high beam quality
  • low emittance tuning, gain curve measurement,
    precision x-ray measurements
  • Phase III - transition to operation
  • Full rep rate, stable operating conditions, full
    energy range, finalize operational procedures

9
End of Startup
  • Startup Plan goes well beyond "Start of
    Operations" which is met when X Rays are detected
    at the Far Hall
  • At the end of Phase III we leave the machine with
    operators who are then able to provide users with
    required beams on a daily basis.

10
Phase I Performance Goals
11
Phase I Demonstrates
  • Bunch compression and bunch length control
  • Orbit control and stability
  • Xray diagnostics functionality
  • SR measurement capability
  • Beam collimation and radiation protection

12
Phase II Performance Goals
13
Phase II Demonstrates
  • SASE FEL process is working
  • Requires
  • FEL quality orbit straightness and stability
  • Good linewidth
  • Good emittance
  • High bunch current
  • Gain length measurements
  • Areas of physics concern CSR, instabilities,
    wakefield effects, new physics effects,

14
Phase III Performance Goals
15
Completion of Phase III Demonstrates
  • We are ready to turn the machine over to the
    operators and the users
  • We need another project!
Write a Comment
User Comments (0)
About PowerShow.com