LAT FSW System Checkout TRR - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

LAT FSW System Checkout TRR

Description:

Sine Vibration Test Objectives Met Were the Sine ... i.e. Changes since PER ACD-to-Radiator and ACD-to-blanket bar interface modified Velcro patches did not ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 29
Provided by: SLAC
Category:
Tags: fsw | lat | trr | checkout | sine | system

less

Transcript and Presenter's Notes

Title: LAT FSW System Checkout TRR


1
GLAST Large Area Telescope LAT Pre-Shipment
Review Mechanical Structure John Ku Design
Integration and Analysis Stanford Linear
Accelerator Center
2
Purpose / Contents
  • Demonstrate structural readiness to ship the
    integrated flight instrument to the spacecraft
    vendor
  • The LAT
  • is compliant with all structural requirements
  • successfully satisfied all test objectives
  • has no outstanding NCRs related to structural
    performance

3
Changes since PER
  • Requirements / Design Update, i.e. Changes since
    PER
  • ACD-to-Radiator and ACD-to-blanket bar interface
    modified
  • Velcro patches did not line up and were
    incompatible (both sides were loop)
  • To solve this, kapton tape was used to attach the
    blankets to the ACD
  • Blankets are lower on ACD by approximately 12.7
    mm, resulting in looser fit.
  • Interface to radiators and blanket bars are okay
  • The new attachment method successfully sustained
    all environmental tests and functioned properly
  • APPROVED This change is documented in NCR00942

4
Requirements compliant
  • All flight system design analyses have been
    successfully completed and demonstrate adequate
    margin
  • Mission System Spec ? 433-SPEC-0001
  • LAT-SC Interface Requirements Spec ? 433-IRD-0001
  • Mission Assurance Requirements Spec ?
    433-MAR-0001
  • LAT Environmental Requirements Spec ?
    LAT-SS-00778
  • LAT Performance Verification Plan ?
    LAT-MD-00408-04c

5
Structural VCRM Summary
6
Successfully Passed Environmental Tests
  • The mechanical tests, highlighted in red boxes,
    are part of the environmental test sequence,
    shown below (see LAT-MD-02717)
  • No liens that require any retest at NRL!

Baseline
Ship to
NRL
F
C
S
NRL Post-Ship
at SLAC
Sine Vibe
Acoustic
Mount
Receive,
C
T
Radiators
Unpack
L
L
L
L
L
L
Pre Post
-
Axis
Final
T
-
Cycle
T
-
Bal
Pre
-
TV
Weight
Ship to
Remove
Pack LAT
CG
Spectrum
Radiators
L
C
L
C
S
S
C
S
F
TESTING IN THERMAL VAC CHAMBER
F
F
L
Limited Performance Test
L
Limited Performance Test
LAT Functional and FSW Test
Comprehensive Performance Test
C
T
TCS Functional Test
Comprehensive Performance Test
C
T
TCS Functional Test
SVAC Test
S
E
EMI/EMC Emissions/Susceptibility Test
SVAC Test
S
E
EMI/EMC Emissions/Susceptibility Test
7
Sine Vibration Test Objectives Met
  • Were the Sine Vibration Test Objectives met?
  • Verify the strength of the LAT and subsystem
    interfaces under PFQ loads and durations
  • Was this be accomplished? YES! Pre- and
    post-test signature overlays show identical
    structural behavior prior to and after PFQ loads
  • Measure primary natural frequencies (fn) of the
    primary modes of the LAT
  • Was this be accomplished? YES! The first mode of
    the LAT was measured to be 60 Hz, which agrees
    with predictions and verifies the design
    requirement to be above 50 Hz
  • Determine transmissibility (Q) of the LAT
  • Was this be accomplished? YES! Low level sine
    sweeps showed a primary mode amplification of
    15, corresponding to a damping ratio of 3.3 of
    critical
  • Validate the math model used for coupled loads
    analysis
  • Was this be accomplished? YES! Data review shows
    that the math model accurately predicts hardware
    performance
  • Verify the workmanship and processes used in the
    manufacture and assembly
  • Was this be accomplished? YES! Pre- and
    post-test signature overlays show identical
    structural behavior prior to and after PFQ loads

8
Sine Vibration Test Configuration
9
Sine Vibration Test Anomaly
  • Y-Axis Sine Vibe Test, June 2, 2006
  • During Run 11 at ½-level, an abort was
    experienced at 31.87 Hz
  • Immediately preceding the abort, three loud
    sounds (described as dull thuds) were noted by
    engineer on the floor
  • The abort itself was not so unusual, but the
    combination with the very unusual sounds, further
    investigation ensued
  • Investigation findings (see backup slides for
    details)
  • A thorough review of the data points to a high
    frequency shock at the strong direction flexures
  • Peak shock (unfiltered data) is 60g while
    inertial acceleration (filtered at 50 Hz) was
    1.4g.
  • Maximum shock (unfiltered) in LAT SSs is 6.67g
    while inertial acceleration (filtered) is 0.14g
  • 6.67g high frequency shock event has very little
    energy content
  • Problems are not expected due to these low shock
    inputs
  • NCR documenting this anomaly has been closed with
    some follow-up actions to be performed by the GPO

10
Sine Vibration Data
Excellent Correlation between test and analysis
11
Acoustic Test Objectives Met
  • Were the Acoustic Test Objectives met?
  • The primary objective is to demonstrate that the
    fully integrated LAT is capable of withstanding
    acoustic noise loads, simulating launch
    conditions.
  • Was this accomplished? YES! Pre- and post-test
    signature overlays show identical structural
    behavior prior to and after PFQ loads.
    Additionally, performance testing showed no
    degradation due to acoustic loads
  • A secondary objective is to verify the acoustic
    analysis, i.e. that the LAT components were
    qualified to high enough levels of random
    vibration.
  • Was this accomplished? YES! The responses show
    subsystem test level specifications were
    conservative

12
Acoustic Test Configuration
13
Acoustic Data
14
Mass Properties Test Objectives Met
  • Were the Mass Properties Test Objectives met?
  • Measure the overall mass and CG of the fully
    integrated LAT
  • Was this accomplished? YES, with caveat. The
    preliminary data analysis does not account for
    GSE tolerances. The adjusted CG calculation will
    be published in the mass properties report
  • Verify the following three IRD requirements
  • LAT mass does not exceed 3000kg. Was this
    accomplished? YES! The mass properties test
    showed the LAT mass to be 2782 kg (2789 kg
    predicted)
  • By Analysis, show Zcg is a maximum of 185mm above
    the LAT Interface Plane (LIP). Was this
    accomplished? Not yet, but will be published in
    the test report. This is considered very low
    risk since prediction error is small when
    compared with measured quantities.
  • By Test, show X-cg and Y-cg are within 20mm of
    the LAT Coordinate System (LCS) Z-axis. Was this
    accomplished? YES! The measured CG is (-0.56mm,
    -1.27mm) the predicted CG was (-1.57mm, -1.2mm).
  • A secondary goal is to verify that the measured
    mass properties coordinate with the math model
    mass matrix Was this accomplished? Not yet, but
    the results will be published in the mass
    properties report.

15
Mass Properties Test Configuration
16
Readiness Statement
  • All Pre-ship related requirements are verified
  • Requirements still needing verification
  • Mass property requirements will be satisfied by
    9/22/06
  • Other requirements will be satisfied at
    Observatory Testing
  • Environmental tests executed successfully
  • Sine Vibration Test completed successfully,
    report pending
  • Acoustic Test completed successfully, report in
    review
  • Mass and CG Test completed successfully, report
    pending
  • The LAT structure is ready for shipment to SC
    vendor

17
GLAST Large Area Telescope LAT Pre-Shipment
Review Back-up Slides John Ku Design
Integration and Analysis Stanford Linear
Accelerator Center
18
LAT Margins of Safety
  • Current calculations for system performance are
    fully compliant with requirements
  • Completed analysis of current design demonstrate
    adequate margin for mechanical loads and stress
    from handling, test and flight environments (ECLA
    and FDLC2 used for flight loads)

19
LAT Margins of Safety
20
Appropriately tested at lower levels of assembly
  • LAT Instrumentation Plan ? LAT-TD-00890-03
  • Flight and ground instrumentation defined
  • LAT Dynamics Test Plan ? LAT-MD-01196-03
  • Sine Vibration, Acoustic, and Mass Properties
    tests described
  • All lower level flight system verification
    activities have been satisfactorily completed and
    all discrepancies are sufficiently understood to
    warrant proceeding
  • Engineering Test Unit testing since CDR are
    documented and the design reflects the results
  • Coupon Tests
  • Insert pullout and shear strength (keensert,
    helicoil, potted inserts, bare threads)
  • torque to preload ratios
  • http//www-glast.slac.stanford.edu/MechanicalSyste
    ms/Analysis/Testing/EM/
  • Flight-like coupon tests
  • Grid wing corner
  • Grid EM1X4 Stiffness Verification Test ? Complete
    ? LAT-TD-02417
  • http//www-glast.slac.stanford.edu/MechanicalSyste
    ms/Analysis/Testing/Component/
  • CAL EM Vibration Test ? Complete ? LAT-TD-01888
  • TKR EM Vibration Test ? Complete ? LAT-TD-04310
  • SC Flexure Strength and Stiffness test ? Complete
    ? LAT-TD-07813-01
  • Flight Subsystem tests ? subsystem EIDP reports
    provide more detailed subsystem test data

21
Appropriately tested at lower levels of assembly
(cont.)
  • Notable fabrication discrepancies and resolution
  • Subsystem EIDP reports provide more detailed
    subsystem manufacturing discrepancy information
  • Shear plates are held in place by a captive stud
    and nut. Substandard nut manufacturing caused
    galling which could lead to stud failure during
    attempted nut removal.
  • Resolution do not remove defective nuts unless
    necessary. If necessary, split nut to preserve
    stud.
  • This anomaly affects 8 out of 64 studs and 4 out
    of 16 Calorimeters
  • Additional information can be obtained from a
    tech note written by J.Ku Use of Subtandard
    Nut, dated 6 Feb 2006.

22
GLAST LAT Sine Vibration TestY-Axis Anomaly
  • John Ku
  • June 2, 2006

23
Problem Statement
  • Y-Axis Sine Vibe Test, June 2, 2006
  • During Run 11 at ½-level, an abort was
    experienced at 31.87 Hz
  • Immediately preceding the abort, three loud
    sounds (described as dull thuds) were noted by
    engineer on the floor (C. Fransen)
  • The abort itself was not so unusual, but the
    combination with the very unusual sounds, further
    investigation ensued
  • The input spectrum was not as expected. The
    expected and tested spectra are shown below
  • Visual Inspection initiated at approximately 2pm
  • A connector saver (on X side) was found
    disconnected from the flight hardware
  • A washer used for lifting was found loose in the
    inner bag (accidentally left in bag)
  • A stone (sharpening stone) was found on the
    shaker armature

24
Anomaly Caused by LAT/SC Interface Slippage
  • A review of the unfiltered time histories showed
    that there was a shock-like event at the X and
    X flexure / LAT interface.
  • The peak responses observed for the X and X
    interfaces were 59.34 and 58.94gs, respectively.
  • Filtered results for the same accelerometer
    channels showed maximum content of 1.347 and
    1.362gs, enforcing the theory that this is a
    high frequency event.

Unfiltered ? Peak 60 g
Filtered ? Peak 1.3 g
X Flexure
Unfiltered ? Peak 60 g
Filtered ? Peak 1.3 g
-X Flexure
25
Energy Release Observed
  • Further examination of the time-phased data of
    the event shows a strain reduction, i.e. energy
    release, immediately prior to the shock event (
    1.5 milliseconds).
  • This enforces a sudden slippage theory.

energy release observed here
26
Energy Release Observed
  • Zoomed-in data showing sudden energy release.

energy release (slippage) observed here
Shock (Impact) observed here
27
Mechanical Joint Design
  • This theory is plausible because
  • There is clearance in the pin to LAT bushing
  • Bushing LAT-DS-02554 ID 0.564 0.002 / -0.000
  • Pin OD 0.5625 0.0000 / -0.0010
  • Max Clearance 5.660 5.615 4.5 mils
  • Expected clearance 3 mils to be confirmed by
    Marc Campell
  • There is clearance in the pin to SC Flexure
  • Undertermined amount
  • Friction holds the joint in static equilibrium,
    but is not reliable as lateral accelerations
    increase.
  • We observed slippage at approximately 1.76 gs at
    the LAT CG.
  • According to this, the joint coefficient of
    friction would be 0.26 (plausible).
  • 64 ft-lb torque 4 7/16 bolts static weight
    41237lbf normal force
  • 1.76 g 2780kg 10787 lbf total
  • This sounds like a major design flaw, but in
    reality, the LAT vibration test subjects the
    suspect interface to significantly more severe
    loads than at the observatory level, so the
    design may be adequate
  • Additional investigation should be performed to
    ensure linear performance at the observatory
    level
  • Manual notching at the LAT first natural
    frequency is okay because the responses will
    still be significantly higher than the
    observatory analysis shows
  • 0.3g MIN _at_ 32.5 Hz _at_ LAT CG based on Observatory
    analysis
  • 0.7g _at_ 32.5 Hz _at_ LAT CG already experienced at te
    ½ level notched run

28
Conclusions and Path Forward
  • Conclusions
  • All the above findings point to a high frequency
    shock at the strong direction flexures
  • Peak shock (unfiltered data) is 60g while
    inertial acceleration (filtered at 50 Hz) was
    1.4g.
  • Maximum shock (unfiltered) in LAT SSs is 6.67g
    while inertial acceleration (filtered) is 0.14g
  • 6.67g high frequency shock event has very little
    energy content
  • Problems are not expected due to these low shock
    inputs
  • Path Forward
  • Conduct intermediate LL sine vibration test and
    overlay with pre-test signature
  • Cable up EGSE and perform LPT over the weekend to
    confirm LAT function
  • Before resuming test on Monday, have an 8am EDT
    tag-up (Ken to send dial-in info)
  • Marc to provide as-built data
  • If intermediate and pre-test signatures are okay,
    AND LPT results are favorable, then continue
    testing Monday morning
Write a Comment
User Comments (0)
About PowerShow.com