Title: LAT FSW System Checkout TRR
1GLAST Large Area Telescope LAT Pre-Shipment
Review Mechanical Structure John Ku Design
Integration and Analysis Stanford Linear
Accelerator Center
2Purpose / Contents
- Demonstrate structural readiness to ship the
integrated flight instrument to the spacecraft
vendor - The LAT
- is compliant with all structural requirements
- successfully satisfied all test objectives
- has no outstanding NCRs related to structural
performance
3Changes since PER
- Requirements / Design Update, i.e. Changes since
PER - ACD-to-Radiator and ACD-to-blanket bar interface
modified - Velcro patches did not line up and were
incompatible (both sides were loop) - To solve this, kapton tape was used to attach the
blankets to the ACD - Blankets are lower on ACD by approximately 12.7
mm, resulting in looser fit. - Interface to radiators and blanket bars are okay
- The new attachment method successfully sustained
all environmental tests and functioned properly - APPROVED This change is documented in NCR00942
4Requirements compliant
- All flight system design analyses have been
successfully completed and demonstrate adequate
margin - Mission System Spec ? 433-SPEC-0001
- LAT-SC Interface Requirements Spec ? 433-IRD-0001
- Mission Assurance Requirements Spec ?
433-MAR-0001 - LAT Environmental Requirements Spec ?
LAT-SS-00778 - LAT Performance Verification Plan ?
LAT-MD-00408-04c
5Structural VCRM Summary
6Successfully Passed Environmental Tests
- The mechanical tests, highlighted in red boxes,
are part of the environmental test sequence,
shown below (see LAT-MD-02717) - No liens that require any retest at NRL!
Baseline
Ship to
NRL
F
C
S
NRL Post-Ship
at SLAC
Sine Vibe
Acoustic
Mount
Receive,
C
T
Radiators
Unpack
L
L
L
L
L
L
Pre Post
-
Axis
Final
T
-
Cycle
T
-
Bal
Pre
-
TV
Weight
Ship to
Remove
Pack LAT
CG
Spectrum
Radiators
L
C
L
C
S
S
C
S
F
TESTING IN THERMAL VAC CHAMBER
F
F
L
Limited Performance Test
L
Limited Performance Test
LAT Functional and FSW Test
Comprehensive Performance Test
C
T
TCS Functional Test
Comprehensive Performance Test
C
T
TCS Functional Test
SVAC Test
S
E
EMI/EMC Emissions/Susceptibility Test
SVAC Test
S
E
EMI/EMC Emissions/Susceptibility Test
7Sine Vibration Test Objectives Met
- Were the Sine Vibration Test Objectives met?
- Verify the strength of the LAT and subsystem
interfaces under PFQ loads and durations - Was this be accomplished? YES! Pre- and
post-test signature overlays show identical
structural behavior prior to and after PFQ loads - Measure primary natural frequencies (fn) of the
primary modes of the LAT - Was this be accomplished? YES! The first mode of
the LAT was measured to be 60 Hz, which agrees
with predictions and verifies the design
requirement to be above 50 Hz - Determine transmissibility (Q) of the LAT
- Was this be accomplished? YES! Low level sine
sweeps showed a primary mode amplification of
15, corresponding to a damping ratio of 3.3 of
critical - Validate the math model used for coupled loads
analysis - Was this be accomplished? YES! Data review shows
that the math model accurately predicts hardware
performance - Verify the workmanship and processes used in the
manufacture and assembly - Was this be accomplished? YES! Pre- and
post-test signature overlays show identical
structural behavior prior to and after PFQ loads
8Sine Vibration Test Configuration
9Sine Vibration Test Anomaly
- Y-Axis Sine Vibe Test, June 2, 2006
- During Run 11 at ½-level, an abort was
experienced at 31.87 Hz - Immediately preceding the abort, three loud
sounds (described as dull thuds) were noted by
engineer on the floor - The abort itself was not so unusual, but the
combination with the very unusual sounds, further
investigation ensued - Investigation findings (see backup slides for
details) - A thorough review of the data points to a high
frequency shock at the strong direction flexures - Peak shock (unfiltered data) is 60g while
inertial acceleration (filtered at 50 Hz) was
1.4g. - Maximum shock (unfiltered) in LAT SSs is 6.67g
while inertial acceleration (filtered) is 0.14g - 6.67g high frequency shock event has very little
energy content - Problems are not expected due to these low shock
inputs - NCR documenting this anomaly has been closed with
some follow-up actions to be performed by the GPO
10Sine Vibration Data
Excellent Correlation between test and analysis
11Acoustic Test Objectives Met
- Were the Acoustic Test Objectives met?
- The primary objective is to demonstrate that the
fully integrated LAT is capable of withstanding
acoustic noise loads, simulating launch
conditions. - Was this accomplished? YES! Pre- and post-test
signature overlays show identical structural
behavior prior to and after PFQ loads.
Additionally, performance testing showed no
degradation due to acoustic loads - A secondary objective is to verify the acoustic
analysis, i.e. that the LAT components were
qualified to high enough levels of random
vibration. - Was this accomplished? YES! The responses show
subsystem test level specifications were
conservative
12Acoustic Test Configuration
13Acoustic Data
14Mass Properties Test Objectives Met
- Were the Mass Properties Test Objectives met?
- Measure the overall mass and CG of the fully
integrated LAT - Was this accomplished? YES, with caveat. The
preliminary data analysis does not account for
GSE tolerances. The adjusted CG calculation will
be published in the mass properties report - Verify the following three IRD requirements
- LAT mass does not exceed 3000kg. Was this
accomplished? YES! The mass properties test
showed the LAT mass to be 2782 kg (2789 kg
predicted) - By Analysis, show Zcg is a maximum of 185mm above
the LAT Interface Plane (LIP). Was this
accomplished? Not yet, but will be published in
the test report. This is considered very low
risk since prediction error is small when
compared with measured quantities. - By Test, show X-cg and Y-cg are within 20mm of
the LAT Coordinate System (LCS) Z-axis. Was this
accomplished? YES! The measured CG is (-0.56mm,
-1.27mm) the predicted CG was (-1.57mm, -1.2mm). - A secondary goal is to verify that the measured
mass properties coordinate with the math model
mass matrix Was this accomplished? Not yet, but
the results will be published in the mass
properties report.
15Mass Properties Test Configuration
16Readiness Statement
- All Pre-ship related requirements are verified
- Requirements still needing verification
- Mass property requirements will be satisfied by
9/22/06 - Other requirements will be satisfied at
Observatory Testing - Environmental tests executed successfully
- Sine Vibration Test completed successfully,
report pending - Acoustic Test completed successfully, report in
review - Mass and CG Test completed successfully, report
pending - The LAT structure is ready for shipment to SC
vendor
17GLAST Large Area Telescope LAT Pre-Shipment
Review Back-up Slides John Ku Design
Integration and Analysis Stanford Linear
Accelerator Center
18LAT Margins of Safety
- Current calculations for system performance are
fully compliant with requirements - Completed analysis of current design demonstrate
adequate margin for mechanical loads and stress
from handling, test and flight environments (ECLA
and FDLC2 used for flight loads)
19LAT Margins of Safety
20Appropriately tested at lower levels of assembly
- LAT Instrumentation Plan ? LAT-TD-00890-03
- Flight and ground instrumentation defined
- LAT Dynamics Test Plan ? LAT-MD-01196-03
- Sine Vibration, Acoustic, and Mass Properties
tests described - All lower level flight system verification
activities have been satisfactorily completed and
all discrepancies are sufficiently understood to
warrant proceeding - Engineering Test Unit testing since CDR are
documented and the design reflects the results - Coupon Tests
- Insert pullout and shear strength (keensert,
helicoil, potted inserts, bare threads) - torque to preload ratios
- http//www-glast.slac.stanford.edu/MechanicalSyste
ms/Analysis/Testing/EM/ - Flight-like coupon tests
- Grid wing corner
- Grid EM1X4 Stiffness Verification Test ? Complete
? LAT-TD-02417 - http//www-glast.slac.stanford.edu/MechanicalSyste
ms/Analysis/Testing/Component/ - CAL EM Vibration Test ? Complete ? LAT-TD-01888
- TKR EM Vibration Test ? Complete ? LAT-TD-04310
- SC Flexure Strength and Stiffness test ? Complete
? LAT-TD-07813-01 - Flight Subsystem tests ? subsystem EIDP reports
provide more detailed subsystem test data
21Appropriately tested at lower levels of assembly
(cont.)
- Notable fabrication discrepancies and resolution
- Subsystem EIDP reports provide more detailed
subsystem manufacturing discrepancy information - Shear plates are held in place by a captive stud
and nut. Substandard nut manufacturing caused
galling which could lead to stud failure during
attempted nut removal. - Resolution do not remove defective nuts unless
necessary. If necessary, split nut to preserve
stud. - This anomaly affects 8 out of 64 studs and 4 out
of 16 Calorimeters - Additional information can be obtained from a
tech note written by J.Ku Use of Subtandard
Nut, dated 6 Feb 2006.
22GLAST LAT Sine Vibration TestY-Axis Anomaly
23Problem Statement
- Y-Axis Sine Vibe Test, June 2, 2006
- During Run 11 at ½-level, an abort was
experienced at 31.87 Hz - Immediately preceding the abort, three loud
sounds (described as dull thuds) were noted by
engineer on the floor (C. Fransen) - The abort itself was not so unusual, but the
combination with the very unusual sounds, further
investigation ensued - The input spectrum was not as expected. The
expected and tested spectra are shown below - Visual Inspection initiated at approximately 2pm
- A connector saver (on X side) was found
disconnected from the flight hardware - A washer used for lifting was found loose in the
inner bag (accidentally left in bag) - A stone (sharpening stone) was found on the
shaker armature
24Anomaly Caused by LAT/SC Interface Slippage
- A review of the unfiltered time histories showed
that there was a shock-like event at the X and
X flexure / LAT interface. - The peak responses observed for the X and X
interfaces were 59.34 and 58.94gs, respectively. - Filtered results for the same accelerometer
channels showed maximum content of 1.347 and
1.362gs, enforcing the theory that this is a
high frequency event.
Unfiltered ? Peak 60 g
Filtered ? Peak 1.3 g
X Flexure
Unfiltered ? Peak 60 g
Filtered ? Peak 1.3 g
-X Flexure
25Energy Release Observed
- Further examination of the time-phased data of
the event shows a strain reduction, i.e. energy
release, immediately prior to the shock event (
1.5 milliseconds). - This enforces a sudden slippage theory.
energy release observed here
26Energy Release Observed
- Zoomed-in data showing sudden energy release.
energy release (slippage) observed here
Shock (Impact) observed here
27Mechanical Joint Design
- This theory is plausible because
- There is clearance in the pin to LAT bushing
- Bushing LAT-DS-02554 ID 0.564 0.002 / -0.000
- Pin OD 0.5625 0.0000 / -0.0010
- Max Clearance 5.660 5.615 4.5 mils
- Expected clearance 3 mils to be confirmed by
Marc Campell - There is clearance in the pin to SC Flexure
- Undertermined amount
- Friction holds the joint in static equilibrium,
but is not reliable as lateral accelerations
increase. - We observed slippage at approximately 1.76 gs at
the LAT CG. - According to this, the joint coefficient of
friction would be 0.26 (plausible). - 64 ft-lb torque 4 7/16 bolts static weight
41237lbf normal force - 1.76 g 2780kg 10787 lbf total
- This sounds like a major design flaw, but in
reality, the LAT vibration test subjects the
suspect interface to significantly more severe
loads than at the observatory level, so the
design may be adequate - Additional investigation should be performed to
ensure linear performance at the observatory
level - Manual notching at the LAT first natural
frequency is okay because the responses will
still be significantly higher than the
observatory analysis shows - 0.3g MIN _at_ 32.5 Hz _at_ LAT CG based on Observatory
analysis - 0.7g _at_ 32.5 Hz _at_ LAT CG already experienced at te
½ level notched run
28Conclusions and Path Forward
- Conclusions
- All the above findings point to a high frequency
shock at the strong direction flexures - Peak shock (unfiltered data) is 60g while
inertial acceleration (filtered at 50 Hz) was
1.4g. - Maximum shock (unfiltered) in LAT SSs is 6.67g
while inertial acceleration (filtered) is 0.14g - 6.67g high frequency shock event has very little
energy content - Problems are not expected due to these low shock
inputs - Path Forward
- Conduct intermediate LL sine vibration test and
overlay with pre-test signature - Cable up EGSE and perform LPT over the weekend to
confirm LAT function - Before resuming test on Monday, have an 8am EDT
tag-up (Ken to send dial-in info) - Marc to provide as-built data
- If intermediate and pre-test signatures are okay,
AND LPT results are favorable, then continue
testing Monday morning