Title: Comparison of Planned and Real State of Building Order
1Lecture was elaborated with the help of grant
project of Ministry of Education, Youth and
Sports, FRVÅ n. 2005 Innovation of Subject
Financing of Building Order
- Comparison of Planned and Real State of Building
Order
2Principle of Comparison
Managerial operations
Planned state
Analysis of defferences
Finding out of real state
Comparison of plan and realty
3Principle of Building Order Costs Management
- Plan of building order
- Documentation of building order realization
- Identification of differences between plan and
realty in in advance defined indexes (costs,
outputs, returns, profit) - Note For possibility of management it is
necessary to have the same structure of planed
and real information
4Phases of Building Order Management
- Trading phase
- Searching for orders on building market, creation
of offers, attendance in selection procedures,
obtaining of orders - Preparative phase
- Preparation of order for realization, assurance
of productive sources, harmonogram of works
(horizontal bar chart) - Realization phase
- Realization of building order
- Guarantee phase
- Handover of finishes building objects to
investor, guarantee based on legislation
5Building Order Costs
- Overhead costs
- Phase trading, preparative, realization,
guarantee - Production costs
- Phase realization
6Realization Phase Production Costs
- Costs on order arise for works realized by
- Own employees
- Indicator of costs is in the form of amount of
consumption of planed productive sources - Direct material for production (m.u.)
- Outputs of employees in the production
- Outputs of working machines and machinery
- Sub-suppliers
- indicator are total costs for sub-supply
(delivery)
7Realization Phase Production Costs (realized
by own employees)
- Indicators of costs for production material
- Amount of material consumption in m.u.
- Planed consumptions of particular materials
defined according to the norms of consumption - Consumptions of particular materials according to
the operative evidence of inventory (trade
invoice) - Unit prices of materials in CZK/m.u.
- Purchase prices purchase prices from price
catalogues or order from suppliers unit
purchase costs - Price invoiced in trade invoices by suppliers to
investor
8Realization Phase Production Costs (realized
by own employees)
- Indicators of costs for production wages
- Amount of outputs in productive hours
- Planed for realization, defined according to the
normative base in productive hours per m.u. of
output (building work) - Real amount of outputs in productive
- Wage tariff in CZK/h
- Planed according to the firm's tariffs
- Paid to particular productive workers
9Realization Phase Production Costs (realized
by own employees)
- Indicators of costs for production machines and
- machinery
- Amount of machines outputs in productive hours
- Planed for realization of outputs (from normative
base) - Real outputs in productive hours
- Hour tariffs of machines run in CZK/m.u.
- Hour tariffs of costs planed
- Hour tariffs of costs real
10Realization Phase Production Costs (realized
by sub-suppliers)
- Indicators of costs for sub-supplies
- Planed costs for sub-supplies including costs for
their assurance defined according to the
contractual settlements with sub-suppliers -
- Real costs from invoices from sub-suppliers and
costs connected with department ensuring
sub-supplies
11Realization Phase Overhead Costs
- Overhead costs in CZK
- Planed
- Real according to the evidence
12Outputs on Building Order
- Indicators of outputs on building order
- Kinds of building works
- Amount of outputs (amount of building works, vice
works) - Delivery times (fulfillment of time harmonograms)
- Fulfillment of quality (technical standards,
technological standards)
13Outputs on Building Order
- Indicators of amount of output realized on
building - order
- Physical amount of realized works in m.u.
- Found out from documentation of building order
that will be realized - Found out by direct measuring of realized
constructions - Unit prices of building works in CZK/m.u.
- Planed on order
- Invoiced to investor
14Result of Costs Management
- Result of management is achievement of planed
profit on order - Plan
- price planed costs profit
- Reality
- returns from sale real costs profit
15Controlling
- Possible to express as supervision, monitoring,
management (mainly from economic and financial
aspect) - In the frame of various particular building
orders - In the frame of the whole company
- Includes several partial phases
- Obtaining of relevant information needed for next
valuation - Transformation of this information into next
information areas or forms - Documentation of this information into tables,
templates or models - Suggestion of operations for improvement
- It is possible to differentiate following kinds
of controlling - Financial
- Economic
- Technical
16Financial Controlling
- Main aim is monitoring, controlling and next
management of cash-flow in the area of financial
and capital structure - Based on particular indexes of financial analysis
it is possible to monitor - Payment ability of a company, its payment
morality or payment morality of debtors for
assurance of financial circulation - Management of efficient indebtedness rational
indebtedness from the aspect of more efficient
production, control of the amount of debts from
the aspect of the payment ability of the company
in the period of repayments of foreign financial
sources - Controlling of profitability of inserted
finances, profitability of the whole capital or
profitability of revenues
17Cost Controlling
- The main objective is complex monitoring of costs
of - Company
- Monitoring of costs from the aspect of their
amount related to the economic result - Departments of the company
- In relation to the production direct and
indirect costs, fixed and variable costs - Building order
- Continuous controlling of costs during the
realization of the building order comparison of
preliminary calculated costs with costs arising
in the real situation -
18Technical Controlling
- Control of terms and milestones
- On the level of particular building orders from
two aspects - Technical/constructional monitoring of
particular building parts based on following
documents site diary, documentation of real
realization - Payment deducibility of just realized payments,
control of terms of maturity of invoices - Quality control
- Assurance of quality according valid norms and
standards (ISO 9001, 9002)