Title: TEAC14
1 TEAC14
Thursday, January 23, 2003 Radisson Hotel
Marlborough Marlborough, Massachusetts Version
for posting on the ISO-NE website. Certain
information as been redacted for security
reasons. Other corrections/changes made are
noted.
2SWCT Reports Available
- To obtain paper or electronic version of the
following reports contact ISO-NE Customer Service
at 413 540 4220 - Southwestern Connecticut Electric Reliability
Study - Volume 1 - Final Power - Flow, Voltage
and Short circuit - Southwestern Connecticut Electric Reliability
Study - A Comparative Analysis of 345 kV
Plumtree-Norwalk Overhead versus 2 -115 kV Cables
from Plumtree - Norwalk.
3TEAC14 Agenda
- Welcoming Remarks
- RTEP03 Scope Overview
- Planning Assumptions
- Update on Transmission Studies
- SEMA/RI Export
- Boston /NEMA -
- Downtown
- North Shore
- RTEP Projects
4RTEP03 Scope
- Reliability and Economic Assessments
- Updated planning assumptions
- MARS analysis by RTEP sub-area
- SCED bus by bus analysis at selected load levels
- Expanded IREMM analysis to reflect SMD
- Historical Losses
- Unit Commitment
- Uplift
- Several Cases to be studied
- Incremental MARS IREMM Analysis -2004
5RTEP03 Cases
6Case ID Case Description IREMM MARS SCED
1 Base, Sub-Area Transfer limits with RTEP02 Appendix 13.5.C Interface Transmission Elements (updated to include Upgrades anticipated by 04.01.03 )and RTEP03 load, generation, fuel cost, and other Control Area assumptions Fuel Based Bids Y 50,60, 70,80, 90 100 Percent Load Levels 2004
1A Case 1 Higher Bids NA TBD
1B Case 1 Fuel Oil Cost 25 NA TBD
1C Case 1 Gas Costs 25 NA TBD
1D Generator Attrition Case Y Y Y
1E HQ Ph II at 2000 MW Y Y TBD
7 Case ID Case Description IREMM MARS SCED
2 Glenbrook Statcom Y Y TBD
3 SWCT 345 kV Ph I Y Y TBD
4 SWCT 345 kV Ph II Y Y TBD
5 SEMA/RI Export Improvement Y Y TBD
6 ME Export Improvement Y Y TBD
7 NEMA/Boston Import Improvement Y Y TBD
8 NW VT Improvement Y Y TBD
9 Improvements Cases 2-8 Y Y TBD
9A Case 9 w/ higher bidding Y N TBD
8RTEP03 Scope
- Transmission Planning Studies
- SEMA/RI Export Improvement
- ME Export Improvement
- NEMA/Boston Improvement
- Support Approved RTEP02 Projects
- SWCT 345 kV
- NW Vermont
9RTEP03 Scope
- Fuel Diversity Study
- Analysis of Air Emission Impacts
- Distributed Resources
- LRP
- Interregional Coordination
10RTEP 03 Congestion Cost Methodology
Presentation to the Transmission Expansion
Advisory Committee January 23, 2003 Wayne
Coste Principal, IREMM, Inc.
11Where We Have Been - RTEP 01
- RTEP01 identified key transmission constraints
- Economic congestion was estimated
- Economic congestion created higher prices for
some sub-areas - Interface ratings were significant (static)
- Focus was on LMP effect of price volatility
during high loads - ISO-NE Congestion Management System
- Assumed SMD in place at the start of 2002
- - ARR / FTR revenue reallocation same as
RTEP01/02 - Various assumptions tested using sensitivity
cases - Tested the impact on several alternative bidding
strategies - Did not include transmission uplift (generally
off-peak),losses,load forecast uncertainty or
sub-area internal limits - Tested relaxation of transmission constraints
12Where We Have Been - RTEP 02
- Used basic RTEP01 economic framework
- Modeling refinements
- Assumption updates for
- fuel
- new units
- transmission upgrades
- interchange assumptions
- Interchange combination of fixed import and CC
based value - Effect of full unit outages on congestion
- Limited representation of operating reserve
- Monthly hydro profile developed
- RTEP02 quantified impact of relaxation of
transmission constraints
13RTEP03 Goals
- Forecast on-peak congestion (same as RTEP02)
- Quantify off-peak uplift
- Renamed in SMD Operating Reserve Charges and
Credits - Will remain due to need to securely dispatch the
system - Market screens approved by FERC on Dec 20th
- Develop a more secure unit commitment
- Include N-2 considerations
- Loss of largest unit
- Loss of second transmission element
- Incorporate Transmission Losses
- Transmission losses under SMD may be relatively
high - Roll up results to SMD Reliability Zones
14Improve Secure Dispatch Representation
- ISO-NE has always operated under a secure
dispatch - SMD will continue this operating practice
- RTEP03 should reflect this practice
- RTEP02 respected N-1 transmission limits
- Operations also considers N-2 transmission
limits - Typically transmission outages are the most
constraining - For second contingency transmission outages
- Interface ratings are lower
- Count a portion of quick-start resources
- Include ramp-rate from on-line units
- Include OP-4 actions
- Include allowable amounts of load shedding
15Unit Commitment Process
- Three (or more) passes for unit commitment
- First pass - all units can operate at any level
when needed - Interfaces at N-2 limits.
- Identify units that could be flagged ON for
economics - Remaining uneconomic units flagged OFF
- Second pass with flagged OFF units, price
spikes occur - Interfaces at N-2 limits.
- Identify units that are needed to avoid price
spikes - Remaining uneconomic units flagged OFF
- Third pass with units flagged ON typically at
LOL - Interfaces at N-1 limits.
- Committed min block bids in at zero
16Unit Commitment Data
- Relatively few units can be added in unit
commitment process -
- We will examine the following for impacts
- Start-up cost
- Minimum run hours
- Low operating limit
- Incremental heat rates
- Use physical limits for LOL (typically 25)
17LMP
- LMPs have three components
- Energy Clearing Price
- Congestion
- - in areas of bottled generation
- in load pockets
- Losses
- close to load center
- - in remote exporting areas
18Proxy CT Bid Screens in Constrained in Areas
- Allowable safe harbor bids into import
constrained areas - Addressed in FERC Dec 20th order
- FERC desires to allow limited scarcity pricing
- Based on cost of hypothetical new Proxy CT
- Reduction due to prevailing ICAP revenue offset
- Net difference in fixed cost is allocated over
500 or 2000 hr - At 500 hours - adder can be in the range of 300
- At 2000 hours - adder can be in the 50 - 80
range
19Indicative LMPs by Load Zone - Energy Component
- Energy component is
- uniform in all zones
- (HISTORICAL
- DATA)
20Indicative LMPs by Load Zone - Congestion
Component
- Congestion
- component can be
- significant when
- transmission
- contingency is
- binding
- (HISTORICAL DATA)
21Indicative LMPs by Load Zone - Loss Component
- Loss component is
- very non-linear and
- affect importing and
- exporting regions
- Differently
- (HISTORICAL DATA)
22Indicative LMPs by Load Zone - Loss Component
- Maine has lowest loss
- component while Vermont
- has the highest.
- (Sept 2002)
23Including Losses in RTEP03
- We will use historic loss data by unit
- Implications of loss component
- Need to develop loss changes due to transmission
upgrades - Distant generation may be penalized
- Prevailing prices may rise if marginal units are
- Electrically distant and
- High losses
24SCED Analysis
- SCED - Security Constrained Economic Dispatch
program developed by PTI - GOAL To identify the specific transmission
facilities that may constrain and cause
congestion on the New England system
25SCED Basics
- Analysis focuses on optimal operation of the
system (generator dispatch phase shifters) - Transfers and dispatches are calculated as part
of an optimization process - Uses network load flow model employing a dc
linearized powerflow calculation - Provides estimates of costs incurred to securely
operate around transmission constraints - Identifies reliability problems when secure
system operation is infeasible - Identify HUB price divergence
26SCED Analysis Assumptions
- Similar Analysis performed as part of RTEP01
- 2004 Summer Peak to be analyzed at a number of
varying load levels (50, 60, 70, 80, 90 and 100) - Sensitivities will be studied with larger units
out of service
27InterregionalSystem Planning ProcessImplementat
ion Plan
28Goals
- Reduce Both Physical and Process System Planning
Seams - Issue Draft Coordinated NY/NE System Plan by 1st
Qtr. 2004 - Expand upon NPCC planning process
- Include MAAC/PJM
- Increase coordination under NY and NE agreements
with IMO and New Brunswick
29Existing Physical and Process System Planning
Seams
- Tie Line Capabilities
- Phase II HVdc vs. Central East and PJM Interfaces
- Interconnection and Tariff Studies
- Queues
- Interconnection Standards
- Cost Allocation
- Single Coordinated Plan
30Process Issues
- Timing of FERC Decisions
- SMD Rule
- Planning
- Pricing
- Interconnection Rule
- Queuing
- Cost Sharing across ISO Borders
- TO/ITC Issues
- Differences in NY License Plate vs. NE Network
Tariffs - Obligation to Build
- Accommodation of Potential ITC(-s)
- Formalization of Planning Process
- State Issues
31Opportunities to Address Physical Issues
- Identify and Address Physical Seams
- Form Initial Plan based upon Existing Procedures
- RTEP02 and RTEP03
- NY Power Alert
- Existing NY and NE Interconnection Procedures
- NPCC Annual Reviews
- NPCC CP-10 Studies
- Initiate Joint Studies
- NY-NE Transfer Analysis
- Loss of HQ Phase II Project
- UPNY-SENY Impact on NE
- Identify Small Ticket Improvements
- Develop Preliminary Designs for Further Analysis
32Process to Address Physical Seams
- Establish NY-NE Liaison Committee
- Define Plan
- Transmission Plan
- Initially utilize existing planning procedures as
approved by FERC - Coordinate with Regulatory Agencies
- NYS DPS
- NECPUC
- FERC
- Engage MP Committees
- NEPOOL Participants Committee
- NY Operating Committee
- TEAC
- Utilize agreements with IMO and NB to increase
regional planning scope - Coordinate with NPCC and MAAC/PJM
33Scope of Work
- Assessment
- Study Assumptions
- Load Forecast
- Generation I/S and Availability
- Transportation Limits
- Transmission Projects
- Load Response/Distributed Resources
- Establish Common Databases
- MARS
- IREMM/MAPS Congestion Projections
- Transmission Analysis
- NPCC Studies
- Annual Reviews
- CP-10
- CP-8
- Other TFSS Activities
- Transmission Plan
- Summary of Transmission Planning Studies
- Include Project Status
34RTEP03 Assessments Overview Assumptions Peter
K. Wong
35RTEP03
- Reliability Analysis 2003 - 2012
- Economic Impact Assessment 2003 - 2012
36Reliability Analysis
- Reliability analysis (Resource Adequacy
Assessment) to identify NEPOOL system reliability
based on meeting the 1 Day in 10 Years Loss of
Load Expectation criterion (disconnection of firm
customers). - GE Multi-Area Reliability Simulation (MARS)
program will be used for this analysis.
37Economic Impact Assessment
- Congestion cost assessment to identify possible
congestion trend is based on meeting NEPOOL
energy requirements. - Congestion cost assessment will be conducted
using a market based energy production simulator
(IREMM).
38Economic Impact Assessment
- Estimate congestion cost as result of
transmission constraints identified in
transmission studies. - Estimate congestion cost as result of different
bidding strategies. - Congestion based on price differences between
sub-areas (market areas) - Estimate LMP losses component
- Estimate Uplift impacts
39Load and Existing Resources
- Load and existing generating resource capability
assumptions will be based on the 2003 CELT Report
forecast. - Interruptible/dispatchable load and demand
response assumptions will be based on the latest
ISO-NE Settlement data. -
40Unit Addition Assumptions
- Generating unit additions are based on approved
18.4 Applications and reflect those that have
started construction as of January 2003.
41Unit Addition Assumptions
- Summer Rating (MW)
- AES Granite Ridge (NH) 678
- Milford Units 1 2 (SWCT) 490
- Mystic Units 8 9 (BOSTON) 1,414
- Fore River (SEMA) 700
- English Station 7 8 (CT) 70
- Great Northern Hydro (BHE) 126
- Total 3,478
- All assumed in service by June 1, 2003
- 18.4 Application submittal expected in Feb/Mar
2003
42Generation Out of Service
- Devon 7 and 8 are assumed deactivated when
Milford units are in service. - New Boston 1 is assumed retired when Sithe Mystic
9 is in service. (corrections in red) - No other generation deactivations or retirements
are assumed in the base case.
43Generating Unit Energy
- Generation from fossil fueled units will be
calculated as a function of their short run
marginal costs. - Generation from hydro units are modeled using a
historical monthly generation profile. - Generation from pumped-storage units will reflect
an assumed 10 capacity factor and 75
efficiency.
44RTEP AssumptionsGeneration Other Adjustments
- CELT Capacity Changes
- Change in effective MW due to different forced
outage rates
45Generating Unit Availability
- Generator unit availabilities are based on 5-year
average of historical data (1998 - 2002). - Data Sources are as follows
- NABS for 1998 thru April 1999.
- ISO Short Term Generator Outage Data Base for May
1999 thru April 2000. - ISO Unit Availability Database for May 2000 thru
December 2002.
46Generating Unit Availability
- For new units, unit immaturity is assumed for
first 3 years of operation. After this period,
unit historical data and TUA is used to develop
the 5 year average. - Forced outage assumptions for nuclear units with
extended outage are based on NEPOOL Target Unit
Availabilities except for the first year of the
long outage.
47Generating Unit Availability
- For the first year of the long nuclear outage,
any outage longer than 6 months would be
represented by 6 months of forced outage averaged
with either historical data or TUA (TUA is used
if the unit is on outage the remainder of the
year).
48 Existing Generating Unit Availability(Perce
nt) (edited to indicate gas turbine and jet
statistics separately)
49 Interchange Assumptions for Base Economic
Impact Analysis
- Updated RTEP02 methodology with base plus price
sensitive transactions - LI sound cables (Scenario Based)
50Fuel Price Assumptions
- Fuel Price Forecast Based on Energy Information
Administrations - Annual Energy Outlook (Dec 2002 AEO) for 2004
- Short term outlook for 2003, 2004
- Reference Case forecast was used
51RTEP Assumptions - Fuel Costs
52RTEP Assumptions - Fuel Costs
53RTEP Assumptions - Fuel Costs
54RTEP Assumptions - Fuel Costs
55RTEP Assumptions - Fuel Costs
56Interface Limits
- Update for
- Impacts of Upgrade Timing
- Results of Planning Studies
57Draft 4/03 Forecast ofNet Energy for Load and
Seasonal Peaks
- David Ehrlich
- ISO New England
- Principal Analyst, Load Forecasting,System
Planning
58(No Transcript)
59(No Transcript)
60(No Transcript)
61(No Transcript)
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68Summer Peaks for States Selected Operating
Companies
2003
2008
CAGR
CONNECTICUT
6900
7253
1.0
ISO State peaks Operating Company 2002 Weather
Normal
CMEEC
328
343
0.9
UI
1367
1460
1.3
CLP
4682
4880
0.8
MAINE
1970
2114
1.4
BHE
316
308
-0.5
CMP
1833
1804
-0.3
MASSACHUSETTS
11510
12468
1.6
BECO
3233
3563
2.0
EED
691
729
1.1
FERC715 Operating Company 2003 2008 Forecasts
MECO
3980
4277
1.4
WMECOHWP
773
803
0.7
NEW HAMPSHIRE
2110
2326
2.0
UNITIL
260
306
3.3
GSE
182
202
2.1
PSNH
1472
1508
0.5
RHODE ISLAND
1730
1851
1.4
BVE
343
354
0.7
NEC
125
137
1.9
NECO
1334
1418
1.2
VERMONT
975
1020
1.9
VELCO
975
1102
2.5
69(No Transcript)
70(No Transcript)
71(No Transcript)
72(No Transcript)
73(No Transcript)
74(No Transcript)
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)
79STATUS OF RTEP STUDIES
80FOCUS
- NEMA / Boston
- North Shore
- Downtown
- SEMA / RI Export
- Update on remaining RTEP studies
81NEMA/Boston Planning Study
- TEAC Update
- January 23, 2003
82Study Objectives
- Assess local reliability and dependence on local
generation - Identify short term projects that could be
completed by 2006 or earlier - Identify long term projects as required
83Areas of Concern map redacted
84Generation
- North Shore
- 1150 MW of load
- Salem Harbor 1-4 743MW
- Downtown Boston
- 1000 MW of load
- Mystic4-6 379MW
- Mystic7 565MW
- Mystic Block8 800MW
- Mystic Block9 800MW
- New Boston 380MW
85Analyses Performed
- Thermal Voltage Load Flow Analysis
- Short Circuit
86Initial Conditions Studied
- 25800 Load Level
- Reduced Generation at Salem for North Shore Cases
- Cases with and without 115kV Generation in
Downtown Boston - Various system stresses and dispatches
87Problems Found
- Reliability
- North Shore Transmission Overloads
- Downtown Boston Transmission Overloads
88North Shore Current Conditions
- Overloads occur for load levels experienced today
- North Shore Import limit determined to be
approximately 500 MW - All North Shore generation needed to assure
transmission adequacy
89Transmission Facility Overloads
- North Shore (low generation cases)
- REDACTED
90Two Alternatives Investigated for the North Shore
- Package 1 Straightforward Replacement of
Overloaded Facilities - Package 2 Addition of 345kV Ring Bus at Ward
Hill, second Ward Hill 345/115kV Transformer, and
replacement of the remaining overloaded facilities
91Package Comparison
- Package 1
- Allows for 1100MW of imports
- Eliminates the dependency on North Shore
generation - Uses Non-Standard sized transformers which would
have no system spare - More expensive
92Package Comparison
- Package 2
- Allows for 1000MW of imports
- Would require 112 MW of generation at North Shore
- Uses Standard Size Equipment
- Better Voltage and Thermal Performance
- Better platform for implementing long term
solutions
93Ward Hill One Line Diagram for Package 2
redacted
94Downtown Boston Conditions
- Overloads occur for load levels experienced today
- 1000 MW of load in downtown Boston
95Transmission Facility Overloads
- All 115kV generation off
- Numerous overloads in Downtown Area
- 115kV generation on
- redacted
- Loading on several other 115kV facilities
slightly over LTE
96Recommended Solutions (Downtown Boston)
- Upgrade of circulation equipment of two Downtown
Boston cables - redacted
- Still requires generation on Downtown Boston
115kV system
97SEMA / RIEXPORT CAPABILITYENHANCEMENT
98Objective
- Assess the existing stability and thermal export
limits, determine major (long term) and minor
(short term) upgrades to enhance the export
capability.
- Address congestion and reliability issues
associated with locked-in and locked-out
generation - Address locked-in generation in SEMA/RI Eastern
New England - Address line loading, voltage, stability and
torsional reclosing issues - Increase CT and NEMA/Boston import capabilities
- Increase East to West transfer capability
99Current Status - Stability
- Report complete on existing stability limits
(2002/03 Southeast Massachusetts / Rhode Island
Export and Short Term Upgrade Analysis) - Report is available from ISO-NE Customer Service
100Current Status - Thermal
- Preliminary analysis to assess the thermal export
capability for the system as planned is ongoing. - Ongoing analysis to assess the benefit of various
345kV projects.
101Results Stability Performance Analysis
- Stability limits were based on the result of
three-phase fault with delayed clearing extreme
contingency which resulted in a transiently
unstable response - All applicable contingencies were evaluated
102Results Stability Performance Analysis
- The existing simultaneous stability transfer
limits were found to be - E/W 850
- SEMA/RI 2400
- SEMA 400
103Recommendation Stability Performance Analysis
- Modify the following breakers for Independent
Pole Tripping operation - West Medway 111, 112 (completed)
- Millbury 314 (Completed)
- West Walpole 104, 105, 108, 109 (2003)
- Sherman Road 142 (Complete)
- IPT Modification results in improved stability
limits - E/W 2400
- SEMA/RI 3000
- SEMA 2300
104redacted
105redacted
106redacted
107redacted
108Follow-Up Stability Analysis
- Upgrades to the Canal breakers or reducing the
backup breaker clearing time would eliminate the
possibility of an extreme contingency involving
those breakers causing a total source loss over
2200 MW. - Upgrading Brayton Point circuit breaker 15-300T
and 03-300T to IPT would eliminate the
possibility of an extreme contingency involving
those breakers causing a total source loss over
2200 MW.
109Results Thermal Performance Analysis
- The existing thermal transfer limits for the 2006
As Planned system were found to be 2200 - 3000
MW. - Range limit determined by varying (1) sources in
SEMARI and sinks in NEPOOL and (2) levels of E/W
transfer in the base case. - SEMA/RI Exports limit is highly dependent on
- East/West Transfers
- CT Import
- NEMA Import
110Results - Thermal
- These projects studied to date can improve
SEMA/RI East West and CT Import Capabilities - Project Thermal Export Range
- Option 1
- Card-West Farnum-Sherman-Millbury 345kV 2700
4200 - Option 2
- Mntvlle-Kent-W Farnm-Shrmn-Milbry 345kV 2700
4200 - Existing 2200 - 3000
111SEMARI (CT Import) Option 1
redacted
112SEMARI (CT Import) Option 2
redacted
113Follow-Up Thermal
- Currently evaluating the benefit of two separate
options which improve SEMA/RI to NEMA Boston area
Transfer Capabilities - Option 1
- Tapping the 316 Line between Holbrook and West
Walpole at Canton, adding a 345kV line from
Canton to Hyde Park, 115kV from Hyde Park to
Dewar St with a 345/115kV transformer at Hyde
Park. - Option 2
- Adding 345kV line from Holbrook-Edgar-K St-Mystic
with 345/115kv transformers at Edgar, K St, and
Mystic.
114SEMARI ( NEMA Import) Option 1
redacted
115SEMARI ( NEMA Import) Option 2
redacted
1164.13 Northwest Vermont Reliability Study
- TEAC 12 - 11/19/2002 Rutland
- Focus on Vermont Issues
- Major reports, including 4.13, complete
- ISO Board Approval
- Vermont Regulatory Process continuing
1174.26 Southwest Connecticut Area Reliability
Assessment
- TEAC 13 - 12/5/2002 New Britain
- Focus on Connecticut Issues
- Final Thermal, Voltage, Short Circuit Report
discussed made available - Comparison of Towns proposal to 345kV discussed
made available - Stability 15.5 Review work continuing
118Maine/New Hampshire Studies
- 4.2 Keswick GCX SPS alternatives assessment 2003
- 4.3 Maine Independence Station L/O Section
- 396 SPS Arming or Removal Study 2003
- 4.4 MEPCO Corridor SPS Design Review
2003 - 4.5 BHE Down East Transmission Reliability
- Improvement Assessment (Line 61)
2003 - 4.6 CMP Autotransformer Reliability
- Assessment 2003
119Maine/New Hampshire Studies
- 4.7 Maine-New Hampshire Voltage Performance
Assessment - Minor/short-term upgrades (Stage 1)
Complete - Major/long-term upgrades (Stage 2) 2003
- 4.8 Maine-New Hampshire North South Transfer
Capability Enhancement - Minor upgrades (Stage 1) Complete
- Major upgrades (Stage 2) 2003
120Maine/New Hampshire Studies
- 4.9 Central New Hampshire Western Maine
- Transfer Capability Enhancement
- (Y138 closing) 2003
- 4.10 Southern New Hampshire Area Import
- Capability Enhancement Complete
121Vermont Studies
- 4.11 Essex Capacitor Study Complete
- 4.12 Vermont Long Range Study Complete
- 4.13 Northwest Vermont Reliability Study Complete
- 4.14 Vermont Northern Loop Study Complete
- 4.15 Southwest Vermont / Southeast New
- Hampshire / Central Massachusetts
- Regional Study 2003
122Western / Central MA Studies
- 4.16 Greater Metro-West Transmission Supply
- Study Complete
- 4.17 Central MA Reliability Study 2003
- 4.18 Springfield/Western Massachusetts Area
- Reliability Assessment 2003
- 4.30 Western MA Fault Duty Studies Complete
123Northeastern MA/Boston Studies
- 4.19 NEMA/Boston Import Capability
- Enhancement
- Near-term Limitations (Part 1) Complete
- Long-term Limitations (Part 2) 2003
- NEW NEMA Area NPCC Bulk Power System
- Assessment 2003
124Northeastern MA/Boston Studies
- 4.20 Norwood M.L.D. Station Addition Complete
- 4.21 Auburn Area Study Complete
- NEW North Shore / Merrimack Valley
- Reliability Study 2003
125Southeastern MA/Rhode Island Studies
- 4.23 Southeastern MA/RI Export Capability
- Assessment
- Stability Limit Assessment Short Term
Upgrades Complete - Major/Long Term Upgrades 2003
- NEW Southeastern MA/RI Reliability Study
2003 - 4.22 Cape Cod Supply Study 2003
126Connecticut Studies
- 4.24 Northwest Connecticut Area Import
- Capability Enhancement Complete
- 4.25 Glenbrook STATCOM Complete
- 4.26 Southwest Connecticut (SWCT) Area
- Reliability Assessment 2003
- 4.27 1385 Cable Replacement Study Complete
- NEW Middletown, Connecticut Area
- Reliability Assessment 2003
- NEW Eastern Connecticut Area Reliability
- Assessment 2003
- 4.29 CLP Fault Duty Studies Complete
127New England Regional
- 4.28 East-West Oscillation Analysis 2003
- NEW Excitation System Tuning Study 2003
128STATUS OF RTEP PROJECTS
129Projects gt 20M
-
Cost 18.4 Projected - ISD
- 4.13 NW Vermont Reliability Project 156.3 Yes 200
4-7 - 4.26 SWCT 345 kV Phase I 150.0 No 2005
- 4.26 SWCT 345 kV Phase II 450.0 No 2008
- 4.27 Norwalk Harbor Northport
- 138 kV line 1385 replacement 40.0 Yes 2004
- Updates of cost and In Service Dates (ISD) based
on representations of - the Transmission Owners
130 20M gt Projects gt 1M
-
Costs 18.4 Projected -
ISD - 4.7 Maxcys Western Maine
- Capacitors 6.0 No 2003
- 4.7 Ocean Road Three Rivers
- Capacitors 2.5 No 2003-4
- 4.8 Quaker Hill to Three Rivers
- 115 kV 197 line upgrade 3.0 No 2003
- 4.8 Maguire to Three Rivers 115kV
- 250 line upgrade TBA No 2003
- 4.9 Projects A/W Y138 Line Closing 7.0 No 2005
- 4.10 Deerfield to Garvins 115 kV
- G146 Line rebuild 8.5 Yes 2003
- Updates of cost and In Service Dates (ISD) based
on representations of - the Transmission Owners
131 20M gt Projects gt 1M
-
Cost 18.4 Projected -
ISD - 4.10 Rebuild Scobie 115 kV substation
9.5 Yes 2005 - 4.10 Second 345/115 kV Scobie
- autotransformer 7.0 Yes 2004
- 4.14 Vermont Northern Loop Project 17.0 Yes 2004
- 4.16 Reconductor W-23 Woodside-
- Northborough / Fitch Rd 69kV TBA Yes Complete
- 4.16 Northborough 115 kV Capacitor
1.3 Yes Complete - 4.16 Millbury 115 kV Capacitor Bank
1.1 Yes Complete - 4.16 Second Wachusetts 115/69
- Autotransformer TBA No 2004
- Updates of cost and In Service Dates (ISD) based
on - representations of the Transmission Owners
132 20M gt Projects gt 1M
- Cost 18.4 Projected
- ISD
- 4.16 Reconductor Fitch Rd to Pratts
- Junction 69kV Line N40 TBA No 2004
- 4.20 Norwood Station Addition 11.4 Yes Complete
- 4.21 Auburn Area Improvements TBA Yes 2002-6
- 4.22 Cape Supply Improvements 9.0 No 2003
- 4.23 Replace West Walpole 104,105,108,
- 109 with IPT breakers 2.5 NR 2003
- Updates of cost and In Service Dates (ISD) based
on - representations of the Transmission Owners
133 20M gt Projects gt 1M
- Cost 18.4 Projected
-
ISD - 4.24 Reconductor Canton-North
- Bloomfield 115 kV line 1732
- and add shunt capacitors at
- Franklin Drive and Canton 12.7 Yes 2003
- 4.25 Glenbrook Static VAR
- Compensator 16.0 Yes 2004
- 4.29 Replace CLP Overstressed
- Breakers 5.4 Yes 2003
- 4.30 Replace Western MA
- Overstressed Breakers 1.5 Yes 2003
- Updates of cost and In Service Dates (ISD) based
on - representations of the Transmission Owners
134Projects lt 1M
-
-
Cost 18.4 Projected -
ISD - 4.8 Schiller to Three Rivers 115 kV
- N133 line upgrade 0.3 NR 2003
- 4.11 Essex Capacitors 0.7 Yes Complete
- 4.16 Install Woodside breaker TBA No 2003
- 4.16 Install tie breaker 2nd radial
- NorthboroughHudson 115 kV 0.5 Yes 2003
- 4.23 Re-wire West Medway 111, 112
- to IPT 0.0 NR Complete
- 4.23 Modify Millbury 314
- Sherman Road 142 to IPT 0.2 NR Complete
- Updates of cost and In Service Dates (ISD) based
on - representations of the Transmission Owners