Title: CE403 Construction Methodology
1CE403Construction Methodology
- Earthwork
- Volume Calculations
2Three Views Presented in Contract Documents to
Show Earthwork Construction Features
3Three Views Presented in Contract Documents to
Show Earthwork Construction Features
4Three Views Presented in Contract Documents to
Show Earthwork Construction Features
5(No Transcript)
6(No Transcript)
7Earthwork Volume Calculations
- Cross Sectional Methods
- Trench Excavations
- Average End Method
- Plan Area Methods
- Four Corner Method
8Trench Excavations
- Volume Cross Sectional Area X Length of Trench
- Eg. Find the volume (bank measure) of excavation
required for a trench 3 ft (0.92 m) wide, 6 ft
(1.8m) deep, and 500 ft (152 m) long. Assume
that the trench sides will be approximately
vertical - Solution
- X-section area 3x6 18 sf
- Volume 18x500/27 333 BCY
9Average End Method
10Reminder
11Average End Area Method Example
Calculate the area between two end areas, 100 ft
apart.
12Average End Method
13Average End Method
14Average End Method
15Average End Method
16Average End Area Example 2
Station End Area (sf) Distance (ft) Volume (cy)
15000 360
15100 10,200 100
15200 18,000 100
15300 23,500 100
15400 12,600 100
15500 5,940 100
15600 400 100
Total Volume
17Average End Area Example 2
From 15000 to 15100 volume
(1001/2(36010200))/27 19,556 CY From 15100
to 15200 volume (1001/2(1020018000))/27
52,222 CY From 15200 to 15300 volume
(1001/2(1800023500))/27 76,852 CY And so on
and so on.
18Average End Area Example 2
Station End Area (sf) Distance (ft) Volume (cy)
15000 360
15100 10,200 100 19,556
15200 18,000 100 52,222
15300 23,500 100 76,852
15400 12,600 100 66,852
15500 5,940 100 34,333
15600 400 100 11,741
Total Volume 261,556 cy
19(No Transcript)
20Earthwork Volume Calculations
- Cross Sectional Methods
- Trench Excavations
- Average End Method
- Plan Area Methods
- Four Corner Method
21 Four Corner Method
22 Four Corner Method
23 Four Corner Method
24(No Transcript)
25 Grid Method
- Volume is the area of grid multiplied by the
difference between the existing and the proposed
elevations.
26Grid Method
Volume by Layers
27Contour Method
UK Reservoir Finish Elevations Scale 1 40
28 Contour Method
29Contour Method
UK Reservoir Finish Elevations Scale 1 40
30Mass Diagrams
- Shows two curves
- A continuous curve representing the profile of
the existing grade. - A continuous curve representing the accumulated
volume of earthwork plotted against the linear
profile of the roadway. - Tells Us
- Quantities of Materials to cut and fill
- Average Haul Distances
- Types of Equipment that should be considered
31Mass Diagrams
32Mass Diagrams - Definitions
- Cut volume of excavation for a given cut
- Fill volume of material to be added to an
existing terrain for a given fill - Waste volume of material that is required to be
hauled off site - Borrow volume of material that is required to
be brought on site.
33Mass Diagram
Cut
Borrow
Fill
34Mass Diagrams
- The vertical coordinate of the mass diagram
corresponding to any location on the roadway
profile represents the cumulative earthwork
volume from the origin to that point. - Within a cut, the curve rises from left to
right. - Within a fill, the curve falls from left
to right.
35Mass Diagrams
Cut
Fill
36Mass Diagrams
- A peak on the curve represents a point where the
earthwork changes from cut to fill. - A valley (low point) on the curve represents a
point where the earthwork changes from fill to
cut. - When a horizontal line intersects the curve at
two or more points, the accumulated volumes at
these points are equal.
37Mass Diagrams
Turning Points
Balanced Points
38Mass Diagrams
- The average length of haul for a balanced
section. - The location and amount of borrow and waste for
the project.
39Mass Diagrams
40(No Transcript)