Title: SRIPADASAGAR PROJECT (YELLAMPALLY PROJECT)
1SRIPADASAGAR PROJECT (YELLAMPALLY
PROJECT) AYACUT MAP
2(No Transcript)
3(No Transcript)
4(No Transcript)
5SRIPADA SAGAR PROJECT
PKG No. Description Awarded Bid Amount Rs. in Crs.
1 Construction of Sripada Sagar Project acress Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt. (Stage-I) SCANSKA Cementation Ltd. 408.85
2 Excavation of approach channel Construction of pump house, Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations, Pressure mains Supply and layers of pipelines from Barrage to NTPC Balancing Reservoir. M/s.Subhash Projects Marketing(P) Ltd. 98.92
3 Stage-II, Phase-I of Sripada Sagar Project- supply, installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) M/s. IVRCL-SEW- Navayuga (JV) 1737
TOTAL TOTAL 2244.77
6SRIPADASAGAR L. I. SCHEME
1 Project Profile Project Profile Construction of Sri Padasagar Project across river Godavari (St-I) Ph-I Supply of 8.5 TMC of water to NTPC (St-I, Ph-II) Lifting 12 TMC to irrigate 2 Lakh Acres (St-II, Ph-I)
2 Administrative Sanction Administrative Sanction G. O. Ms. No. 71, I CAD (PW) GVI, Dt 16-7-2004 for Rs. 900 Crores
3 No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos.
4 Agt. Value of 3 Pkgs Rs. 2244.77Crs.
5 Budget Provision for 2006-07 (For GWUA) Budget Provision for 2006-07 (For GWUA) Rs. 1240 Crs.
6 Expenditure of the Project
2004-05 2004-05 Rs. 20.44 Crs.
2005-06 2005-06 Rs. 202.07 Crs.
TOTAL Rs. 222.51 Crs.
7 Utilisation ( Stg-I, Ph-I, Ph-II Stg-II,Ph-I) Utilisation ( Stg-I, Ph-I, Ph-II Stg-II,Ph-I) 20.5 TMC
Ultimate 180.50 TMC
8 Ayacut New Ayacut 2,00,000 acres
7SRIPADASAGAR L. I. SCHEME
9 Lift-I Lift Height 96 M
No. of Pumps 4 Nos.
Total pumps capacity 10.8 MW
10 Lift-II
Lift Height 120 M
No. of Pumps 4 Nos.
Total pumps capacity 13 MW
11 Lift-III Lift Height 80 M
No. of Pumps 4 Nos.
Total pumps capacity 5,25 MW x 2, 8.26 MW x 2
12 Lift-IV
Lift Height 50 M
No. of Pumps 2 Nos.
Total pumps capacity 0.50 MW
13 Power required (Stg-I, Ph-II) water supply to NTPC Power required (Stg-I, Ph-II) water supply to NTPC 9 MW
14 Power required (Stg-II, Ph-I) Irrigation 2L Acs Power required (Stg-II, Ph-I) Irrigation 2L Acs 137 MW
8SRIPADASAGAR L. I. SCHEME
15 Land Acquisition
Required 15,981 acres
Acquired 430 acres
Requisitioned 15,981 acres
16 Est. Cost for LA Rs. 222.00 Crores
17 Est. Cost for R R Rs. 500.00 Crores
18 Mobilisation Advance Paid Recovered
2004-05 Rs. 20.44 Crs.
2005-06 Rs.106.05 Crs. 3.31 Crs.
Total Rs. 126.49 Crs. 3.31 Crs.
19 Target date for completion 10/2007
9SRIPADASAGAR PROJECT
Name of the Contractor ITD Cementation India
Ltd. Agreement Amount Rs. 408.85Crs. Agreement
Date 07-11-2004/17-2-2005 Period of
Completion 36 Months(10 milestones) Date of
completion 06-11-2008
Package No. 1 (Stg-I Ph-I) Construction of
Sripada Sagar Project across Godavari river at
Yellampally (V), Ramagundam(M), Karimnagar Dt. to
store 20 TMC at FRL 148M.
- Survey work Completed
- Designs Alignment of barrage - FINALISED
- Earth bunds approved by CE/CDO
- Spillway under approval in CE/CDO
- Execution
- Drilling of exploratory bore holes
- in river for spill way earth bund Completed
- Excavation of Cutoff trenches for
- right side left side earthen
- bunds Completed
- Exc. of Cutoff trenches for spillway In
progress - Qty. of Earthwork done 2.43 L Cum against
3.062 L Cum. - Expenditure Rs. 63.59 Crores. (including Mob.
Advance Rs.36.04Crs.)
against Rs. 408.85 Crores. - Land Acquisition Required 8745 Acres
Acquired225 Acres Requisitioned 8456
Acs.
10SRIPADASAGAR PROJECT
Water Supply to NTPC
Name of the Contractor M/s.Subhash Projects
Marketing(P) Ltd. Agreement Amount Rs.
98.92 Crs. Agreement Date 07-04-2005 Period of
Completion 18 Months (6 milestones) Date of
completion 06-10-2006
- Package No.2 (Stg-I Ph-II)
- Excavation of approach channel
- Construction of pump house
- Supply and commissioning of pumping machinery to
lift 8.5 TMC, Transformers, sub-stations - Pressure mains
- Supply and laying of pipelines to NTPC Reservoir
- Survey work Completed
- Designs Designs for pressure mains submitted
to CE/CDO are under scrutiny - Designs for pump houses, pumps etc. to be
submitted by Agency - Designs of pipelines Yet to be furnished by
the Agency. - Execution Fabrication Unit erected at site
for manufacture of pipes - Alignment of pressure mains, location
- of approach channel and intake well under
approval by CE/CDO - Expenditure Rs.12.48Crs. (incl. Mob. Adv.)
against Rs.98.92Crs. - Land acquisition Required 70 Acres,
11SRIPADASAGAR PROJECT (Stg-I, Ph-II)
Water Supply to NTPC
1 Expenditure
2005-06 Works Rs. 7.53 Crs.
Mob. Adv. Rs.4.95 Crs.
Total Rs. 12.48 Crs.
2 Land Acquisition
Total Required 55 acres
Acquired Nil
Requisitioned 15 Acres
3 Utilization 8.5 TMC
4 Lift-I Lift-I
Lift Height 50 M
No. of Pumps 4
Total pumps capacity 3300 HPs.
5 Power required Power required Power required 9 MW
12SRIPADASAGAR PROJECT STAGE-II, PHASE-I
(Irrigation)
SALIENT FEATURES SALIENT FEATURES
1 PROJECT PROFILE Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.)
2 Admn. Sanction G. O. Ms. No. 149, I CAD, Dt 16-8-2005 for Rs. 1688.86 Crores
3 Expenditure
2005-06 Rs.146.44 Crs.
4 Land Acquisition
Total Required 15,000 acres
Acquired Nil
Requisitioned 407 Acres
13SRIPADASAGAR PROJECT STAGE-II, PHASE-I
5 Forest Land Forest Land 285 Acres
6 Utilisation 12 TMC
7 Ayacut New Ayacut 2 Lakhs acres
Stabilisation
8 Lift-I
Lift Height 96 M
No. of Pumps 4 Nos.
Total pumps capacity 10.8 MW
9 Lift-II
Lift Height 120 M
No. of Pumps 4 Nos.
Total pumps capacity 13 MW
10 Lift-III
Lift Height 80 M
No. of Pumps 4 Nos.
Total pumps capacity 5,25 MW x 2, 8.26 MW x 2
14SRIPADASAGAR PROJECT STAGE-II, PHASE-I
11 Lift-IV
Lift Height 50 M
No. of Pumps 2 Nos.
Total pumps capacity 0.50 MW
12 Power required Power required 137 MW
13 Mobilisation Advance 2005-06 Mobilisation Advance 2005-06 Paid Recovered
Rs. 85.50Crs Rs. 3.31Crs.
15SRIPADASAGAR PROJECT
Package No.3 Stage-II, Phase-I of Sripada Sagar
Project- supply, installation and commissioning
of pumping machinery, transformers, sub-stations,
pressure mains including construction of pump
house all civil structures to irrigate 2.00 Lakh
acres in upland areas of Karimnagar (Dist.)
Name of the Contractor M/s. IVRCL-SEW-
Navayuga (JV) Agreement Amount Rs.
1737Crs. Agreement Date 03-04-2005 Period of
Completion 30 Months(10 milestones) Date of
completion 02-10-2007
- Utilization 12 TMC (Lifting)
- Power Required 137 MW
- Investigation Pressure mains completed
- Pump house gravity canal under progress
- Designs Designs of pressure mains and
alignment submitted to CE/CDO for approval - Mobilization Advance paid 85.50 Crores
- Mob. Advance recovered Rs. 3.31 Crs.
- Land Acquisition Required 2000 Acres
Requisitioned 437 Acres. - (Rs. 5.00 Crores deposited with Revenue
Authorities)