Project - PowerPoint PPT Presentation

About This Presentation
Title:

Project

Description:

Project & Quality Management Day 3 Technology Project Management Syllabus Core: PQM Three main topics Project Management Quality Management Reliability Management ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 58
Provided by: Elizabet477
Category:
Tags: project

less

Transcript and Presenter's Notes

Title: Project


1
  • Project Quality Management
  • Day 3 Technology
  • Project Management

2
Syllabus Core PQM
  • Three main topics
  • Project Management
  • Quality Management
  • Reliability Management

3
Structure of the Presentation
  • Project Management
  • Overview of project management,
  • Project planning
  • Work Breakdown Structure,
  • The Gantt Chart,
  • Network Diagram,
  • Critical Path Diagram,
  • Project planning for Technology projects,
  • Using Microsoft Project to generate charts.

4
What is Project Management?
  • A set of techniques used for managing projects
  • Origins in industry - large projects
  • Bridge Building
  • New Product Development
  • Road Building

5
What is a Project?
  • Any task within an organisation that does not
    fit neatly into business-as-usual
  • Port Tunnel
  • Luas
  • Development of New Engine
  • Set up a Quality System in Company
  • Technology Design Make project.

6
What is a Project?
  • Projects have the following characteristics
  • Each project is specific and unique.
  • Each project has a specific deliverable item when
    complete.
  • This deliverable is aimed at meeting a specific
    need or purpose.
  • There is usually a specific due date for
    completion of the project.
  • Design is not necessarily a central part of the
    project activity.

7
What is Managed?
  • PM focuses on the management of resources and
    time in a systematic manner.
  • The administration of the project
  • The supervision of the project
  • The organisation of the project

8
What is Managed?
  • For the student it means
  • Analysing the objectives of the project,
  • Defining the tasks needed to achieve these
    objectives,
  • Controlling the execution of them.

9
Who manages the projeect?
  • Large projects usually involve a project team.

10
What do Project Managers do?
  • Projects have 3 objectives,
  • Finish on time.
  • Meet the specifications that satisfy
  • the brief.
  • Meet the budget.
  • Students are the project managers of their own
    tasks!

11
Importance of Planning
  • Unexpected events may happen during the
  • project and may cause delays.
  • Breakdown of machinery,
  • Problems with resources/supplies,
  • Labour shortages, etc.
  • Project planning can minimise the effect of these
    unexpected delays.

12
Project Planning
  • What is a project plan?
  • Can be as simple as a list of sequences for a
    small project
  • Can be more complex with charts, tables, costings
    etc. for a larger project

13
Project Planning
  • Analyse the brief,
  • List the steps involved,
  • Draw up a Work Breakdown Structure (WBS).
  • A WBS is a diagram that shows
  • Primary Tasks
  • Sub-Tasks

14
Example
  • Draw up a Work Breakdown Structure for the
    erection of a garden shed.
  • The shed will come prefabricated but will need to
    be assembled.
  • A foundation will need to be prepared in advance.

15
List of Tasks
No. Activity
1 Order Shed
2 Buy Blocks, Sand Cement
3 Build Foundation
4 Assemble Shed
16
WBS for Garden Shed
17
The Gantt Chart a Preview
  • A Gantt Chart is a horizontal bar chart showing
    the times for each task

18
Looking at the Gantt Chart
  • Delivery time for the shed is nine days,
  • One day for buying materials,
  • Two days for making the foundation,
  • One day for assembly.
  • Note
  • Making the foundation is timed so that it is
    ready just in time for the delivery of the shed
  • Could have been completed at an earlier date if
    desired.

19
Exercises
  • Redraw the Gantt chart so that the maximum
    amount of time is allowed for the curing of the
    foundation.


20
Exercises
  • Shown is a picture of a Christmas Tree Star
  • Draw a WBS for the Star
  • Draw a Gantt chart for manufacturing the Star

21
List of TasksStar
No. Activity Time
1 Mark Out Star 1
2 Drill Holes 1
3 Cut Out File 3
4 Solder Circuit 2
5 Assemble 2
6 Test 1
22
WBS for Star
Mark Out
Drill
Cut Out File
Structure
Sub Task
Star
Assemble
Test
Sub Task
Solder Circuit
Circuit
23
Gantt Chart for Star
Day
0 1 2 3 4
5 6 7 8 9
10
Mark Out
Drill
Cut Out File
Solder Circuit
Assemble
Test
24
Network Diagrams
  • For larger or more complex projects a network
    diagram is required.
  • Network Diagrams show
  • The relationships between the tasks,
  • 2. The sequence in which each task is
    performed,
  • 3. The interdependencies between the tasks.

25
Drawing up a Network Diagram
WBS
Network Diagram
Gantt Chart
  • Start with task list and draw up a WBS
  • Decide on the order of tasks

26
Sample WBS
A WBS needs to be analysed and redrawn frequently
to arrive at the best production sequence. (Use
Post its)
27
Network Table
Task Predecessor
A -
B -
C A
D B
E B
F C,D
G E


The tasks and theirpredecessorscan be drawn as
a table
28
Part Complete Network Diagram
Note that task C has A as a predecessor D and E
have B as predecessors. A and B have no
predecessors and are connected to the starting
node.
29
Complete Network Diagram
Task Predecessor
A -
B -
C A
D B
E B
F C,D
G E


ExerciseComplete the diagram using the
remainder of the tasks
30
Network Diagram for Garden Shed
  • Draw up a network diagram for the garden shed
    project described previously.

31
Some Definitions and Terms
  • Terms used for network diagrams
  • Activity A task or set of tasks required by the
    project.
  • Network Diagram of nodes representing
    activities connected by directional arrows that
    defines the project and shows the relations
    between all of the activities. Networks are
    usually drawn with a Start node on the left and
    a Finish node on the right.
  • Path A series of connected activities in the
    network
  • Critical Path the set of activities on a path
    from the projects start event to its finish
    event that if delayed, will delay the completion
    date of the project.
  • Critical Time The time required to complete all
    activities on the critical path.

32
Adding Times to the Network Diagram
  • Duration of each task can be added to network
    diagram
  • From this, start and finish times can be found
    for each task
  • Some tasks can be allowed to vary their start and
    finish times without affecting overall time taken

33
Example
Consider the following project
Task Predecessor Duration
A - 5 (days)
B - 4
C A 3
D A 4
E A 6
F B,C 4
G D 5
H D,E 6
I F 6
J G,H 4
34
Network with Tasks Times
35
Adding Further Information
  • We can add the following information to each node
    in the diagram
  • Earliest Start Time (EST)
  • Earliest Finish Time (EFT)
  • Latest Start Time (LST)
  • Latest Finish Time (LFT)

36
Critical Path Diagram
  • Critical path in orange

See notes for a detailed explanation
37
Conclusions from Critical Path Diagram
  • Critical path is path that requires the most time
    (A-E-H-J)
  • Critical time is 21 days which is the earliest
    possible completion time
  • Any delay on critical path will delay the project
  • Some delay (within limits) can be tolerated on
    other tasks.

38
Critical Path Diagram for the Garden Shed
Complete the critical path diagram for the garden
shed State critical path and critical time
39
Solution
  • CP Order Shed Assemble
  • CT 10 Days

40
Calculating Activity Slack

Slack or Float is the amount of time a
non-critical task can be delayed Slack Latest
Finish Time Earliest Finish Time or
Latest Start Time Earliest Start Time
Slack LFT-EFT LST-EST
41
Slack Times from Shed Example
  • Both non-critical tasks have a slack of
  • (9-3)(7-1)(7-1)(6-0) 6 days

42
The Gantt Chart
  • Generated from network diagram
  • Gives visual representation of activities and
    times
  • Gantt charts can show
  • Timeline for each task
  • Dependencies of tasks
  • Critical path

43
Network Diagram
  • Using the Network Diagram from previous example

44
(No Transcript)
45
(No Transcript)
46
Application of PM to Tech. Projects
  • Now we will apply the techniques we have met to a
    hypothetical LC project.
  • The procedure for project work is
  • List the tasks and sub-tasks involved
  • Draw up a WBS
  • Draw up a Network Table
  • Draw up a Network Diagram
  • Insert times and determine the Critical Path

47
Consider the following project brief
  • Design and manufacture a personal alarm that will
    incorporate an electronic circuit as well as a
    suitable casing
  • From analysing the brief
  • General plan on how to approach the project
  • Identify the main tasks involved
  • Derive a Work Breakdown Schedule
  • Draw up a Network Diagram
  • Add times and find the critical path, critical
    time and slack for the activities.

48
A possible WBS for the project
Research Circuit
Design Circuit
Order Components
Circuit
Sub Task
Personal Alarm
Manufacture Assemble
Test
Sub Task
Casing
User Survey
Design Casing
Design Specification
Order Materials
49
Network Table
  • First draw up a list of tasks and preceding tasks

Task Description Duration Predecessor
A Research Circuit 14 -
B User Survey 7 -
C Device Spec 1 B
D Circuit Design 3 A
E Order Components 10 D
F Design Casing 7 C
G Order Materials 7 F
H Manufacture and assembly 7 E,G
I Test 4 H
50
Network Diagram
7
7
51
Critical Path Diagram
CP Circuit Research -Circuit Design-Order
Components-Build-Test CT 38 class periods
52
Gantt Chart for Project
53
Student Workbook
List the tasks needed to complete the project
54
Example 2
  • List the tasks
  • Estimate the times
  • Draw up WBS and Gantt chart

55
Example Contains circuit
  • List the tasks Estimate times
  • Order tasks and optimise them
  • Draw up WBS and Gantt chart
  • Estimate project duration

56
Example
57
Example
Write a Comment
User Comments (0)
About PowerShow.com