Title: Design of Ammonia Section in Ammonia Synthesis Plant
1Design of Ammonia Section in Ammonia Synthesis
Plant
United Arab Emirates University Collage of
Engineering Department of Chemical Petroleum
Engineering Industrial Training Graduation
Projects Unit Graduation Project II Course Fall
Semester 2008
Advisor Dr. Nayef Ghasem
- Rashed Khalfan Al Kindi 200235986
- Shabbeer Ali Yusuf 200337936
- El-Hassan Mohammed 200337931
- Ali Saleh Mohammed 200202794
- Hamad Al Zaidi 200200655
2Overview
- Introduction
- Design Equipments
- Heat Exchangers
- Reactors
- Calculations of design
- Hand Calculations (Excel)
- HYSYS design
- Cost Estimation
- Operation Cost
- Capital Cost
- Cost of Manufacturing
- Results by CAPCOST
3Introduction
- Objectives
- Design of ammonia section in ammonia synthesis
plant for a 30 ton/day production of ammonia - Estimate the Cost
- Material and energy balance was done in GPI
4Introduction
- Design of process units theoretically and using
HYSYS software - The units designed were reactor and heat
exchanger
5- Special concerns related to the process was done
- corrective measures
- Safety and environmental impact of the project
were analyzed - Cost estimation was conducted using CAPCOST
software
6Process Flow Diagram
7Reactor Design
- Assumptions
- The rate equation from HYSYS
- No catalyst, no void fraction
- No pressure drop
- Change in temperature
8Derivation
- The design equation of PFR is
- X is the conversion
- V is the volume
- -rN2 is the rate of reaction of the limiting
reagent, nitrogen - FN2o is the input flow rate of the nitrogen
9Derivation
- The rate of reaction
- kf and kb are the forward and backward rate
constants - PN2, PH2, PH3 are the partial pressures of
nitrogen, hydrogen and ammonia
10Derivation
- The partial pressure of component B
- where PBo is the intial partial pressure of
component B - b is the stoichiometric coefficient of the
component B - ?B is the ratio of flow rate of component B to
that of flow rate of basis component.
11Derivation
- So, for our reaction,
- Po is the total input pressure which in this case
is
12Derivation
13Rate vs. Reactor Volume
14Derivation
- Change in temperature through the reactor
15Behavior
16Derivation
- Change in temperature through the reactor
17Derivation
? d
N2 2.90E-02 2.20E-06 5.72E-09 -2.87E-12
H2 2.88E-02 7.65E-08 3.29E-09 -8.70E-13
NH3 3.52E-02 2.95E-05 4.42E-09 -6.69E-12
18Derivation
- Enter these equations to the polymath software to
obtain the volume for 40 conversion
19Results
- The volume of the reactor obtained from Polymath
is 1.78 m3 - Further HYSYS was used to obtain the volume of
the reactor by setting the diameter to be 0.75 m.
Thus the volume obtained was 0.998m3 for the
highest conversion
20Heat Exchanger Design
- Importance ? Heat integration
- Type of heat exchanger to be designed is
countercurrent shell and tube - The most important factor in a heat exchanger
design is the heat transfer area (A)
21Heat Exchanger Design
- Heat Exchanger design procedures
- Inlet and outlet temperatures are
- Flow rates mc mh 0.577 kg/s
Tc,in 49.8 oC
Tc,out 114 oC
Th,in 333.2 oC
Th,out 263.2 oC
22Heat Exchanger Design
- 1- Find the physical properties
- 2- Calculate the heat transfer rate (q)
- q 148680.4 J/s
T (C) ? (kg/m3) µ (kg/m.s) k (W/m.K) Pr Cp (J/kg.C)
Shell 81.9 18.09 0.000115 0.1381 335296.7 4016
Tube 298.2 39.69 0.000168 0.1507 417740.2 3745
23Heat Exchanger Design
- 3- also
- 4- Find (?T)LMTD
- (?T)LMTD 216 oC
- 5- Find F
24Heat Exchanger Design
- R 0.92 and P 0.25
- ? F 0.98
25Heat Exchanger Design
- 6- Assume a value for U 10 50 W/m2.C
- 7- The heat transfer area (A) is
- A 14.6 m2
- 8- choose initial values for L, Do and Di
- L 2.3 m, Do 0.04 m and Di 0.036 m
26Heat Exchanger Design
- Tube side
- 9- Calculate the area of one tube
- Atube 0.37 m2
- 10- Calculate the number of tubes (Nt),
- Nt 40 tubes
- 11- Find the fluid velocity
- uin 9.14 m/s
27Heat Exchanger Design
- 12- Find Reynolds number
- Re 97063.2 ? turbulent flow
- 13- Find Nusselt number (Nu)
- Nu 314.87
- 14- Calculate the pressure drop
- Np number of tube passes (2)
- ?Pt 12.02 kPa
28To find the tube side friction jf
29Heat Exchanger Design
- Shell side
- 15- Choose the pitch type ? Triangular
- 16- Find the bundle diameter
- Db 0.867 m
- 17- Find the shell diameter (Ds), Ds Db
bundle diametrical clearance - Ds 0.92 m
- 18- Calculate the baffle spacing , lB
- lB 0.184 m
30Heat Exchanger Design
- 19- Choose the tube pitch(pt), 1.25Do, and the
baffle cuts, 25 - 20- Calculate the cross flow area As,
- As 0.0121 m2
- 21-Calculate the mass velocity ,
- Gs 47.5 kg / s.m2
- 22- Calculate the equivalent diameter ,
- de 0.043 m
31Heat Exchanger Design
- 23- Calculate the Reynolds number
- Re 17607
- 24- Calculate the Nusselt number
- Nu 1317.6
- 25- Calculate the pressure drop
- ?Ps 128.7 kPa
32To find shell side heat transfer factor, jh
33To find shell side friction factor, jf
34Heat Exchanger Design
- Overall heat transfer coefficient
- 26- Find the local heat transfer coefficient
- hin 1054.5 W/m2.C and ho 4255.3
W/m2.C - 27- Calculate the overall heat transfer
coefficient U - 28- Use Goal Seek
- Set U 50 by changing L ? L 2.35 m
35Heat Exchanger Design
Area (m2) 14.6
Number of tubes 40
Tube in-diameter (m) 0.036
Tube out-diameter (m) 0.04
Shell diameter (m) 0.92
Length (m) 2.3
Pressure drop in the tube side, ?Pt (kPa) 12.02
Pressure drop in the shell side, ?Ps (kPa) 128.7
36Special Concerns
- Special concerns are out of normal operating
conditions. - Specific justification required else dont use
- Normal conditions
- Pressure between 1 10 bar
- Temperatures between 40 C 260 C
37Concerns in Pressure
- Pressures up to 10 bars without much additional
capital investment - Higher pressures
- Thicker walls
- More expensive equipment
- In vacuum conditions
- Large equipment
- Special construction techniques
- Higher cost
38Concerns in Temperature
- At high temperatures common construction
materials like carbon steel lose their physical
strength drastically - high temperature - economic penalty
- more complicated processing equipment
- refractory-lined vessels
- exotic materials of construction
39Operating Conditions
40Reactor
- High Pressure of 196 bars
- Justification
- Thermodynamically
- Kinetically
41Kinetic Justification
- Rate given by
- Concentration becomes by
- Substituting by partial pressure
42Thermodynamic Justification
- _at_ constant temperature
43Heat Exchanger
- Used Heat Integration
- If ?Tlm gt100C
- Else wastage of usable energy
44Cost Estimation
- Profitability of the project
- The feasibility of any project proposal should
pass the stage of preliminary cost estimation
even before any further study can be done on the
technical aspects - Type of costs
- - Capital
- - Operating
45Capital Cost
- Cost of the plant ready for start-up
- Includes
- Design, and other engineering and construction
supervision - All items of equipment and their installation
- All piping, instrumentation and control systems
- Buildings and structures
- Auxiliary facilities, such as utilities, land and
civil engineering work
46Operating Cost
- Cost involved in the day to day operation of the
plant. - Includes
- Direct cost
- Raw Materials
- Utilities
- Operating Labor
- Fixed cost
- Insurance
- Local Taxes
- General Expenses
- Administration cost
- Distribution and selling cost
47Equipments
- Compressors
- Heat Exchangers
- Reactors
48Effect of Capacity on purchased cost
- Cb is the purchased cost of the equipment with
base capacity Ab - Ca is the purchased cost of the equipment with
required capacity Aa - n is the cost exponent
49(No Transcript)
50Effect of time on purchased cost
- C is purchase cost
- I is the cost index
- 1 refers to base time when the cost is known
- 2 refers to time when cost is desired
51(No Transcript)
52Bare Module cost estimation technique
- CBM is bare module equipment cost
- FBM is bare module cost factor
- CPo is the purchase cost for the base condition,
i.e. atmospheric pressure and material of
construction is carbon steel
53Pressure factor - Fp
- C1, C2 and C3 are constants for each equipment
type
54Material FM
55Table A3
56Cost of manufacturing
- Total direct manufacturing costs
- (COM) CRM CWT CUT 1.33COL 0.3COM
0.069FCI - CRM is the cost of raw material
- CWT is the cost of waste treatment
- CUT is the cost of utilities
- COL is the cost of operating labor
- FCI is the fixed capital investment
57CAPCOST
58Results
- - Equipment cost
- 1- Compressor
Equipment Cost
C-101 138000
C-102 380000
C-103 34100
C-104 17200
Total 569300
59Results, cont..
- - Equipment cost
- 2- Heat Exchanger
Equipment Cost
E-101 14200
E-102 12600
E-103 7330
E-104 3380
E-105 17900
Total 55410
60Results, cont..
Equipment Utility used Cost
E-101 Cooling water 1560
E-102 Cooling water 2490
E-103 Cooling water 1380
E-104 Cooling water 160
Total 5590
61Results, cont..
Material Classification Price (/kg) Consumption (kg/h) Material Costs (/y)
Hydrogen Raw Material 2.700 242 5,437,595
Nitrogen Raw Material 0.500 1160 4,826,760
Ammonia Product 5.000 805 33,496,050
62Results, cont..
- The land cost is estimated to be 1,250,000
- The operating labor cost is estimated to be
700,000 per year - Total cost 12,844,655
63Results, cont..
- The cost index for 2006 is 478.7
64Safety and Environmental Impact
- The exposure limit for ammonia is 25 ppm for 8
hours exposure and 35 ppm for a 15 minutes
exposure - Noise
- low-noise let-down valves
- silencers
- Toxic hazard
- Explosion are not extremely dangerous
65Conclusion
- Volume of the reactor
- 1.78 m3 (theoretical calculation)
- HYSYS value was 0.998 m3
- Heat exchanger
- shell diameter of 1m and 60 tubes
- area of heat transfer 39.48 m2 with a length of
2.35 m. - Total capital cost was 15,548,000
66Thank you