Balancing Production Lines - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

Balancing Production Lines

Description:

Facilities Planning - Unit 06 Balancing Production Lines Balancing Production Lines - * Assembly Lines Balancing - Layout Design 1 2 3 4 5 6 7 8 9 10 In Out Workers E ... – PowerPoint PPT presentation

Number of Views:773
Avg rating:3.0/5.0
Slides: 36
Provided by: Rez68
Category:

less

Transcript and Presenter's Notes

Title: Balancing Production Lines


1
Facilities Planning - Unit 06Balancing
Production Lines
2
Factors Affecting Capacity
External Factors Government regulations Union agreements Supplier capabilities Technology Internal Factors Product and service design Personnel jobs Equipment Capabilities Materials management Q.C. Systems Management capabilities Plant layout flow
3
Process Selection and System Design
Facilities andEquipment
Forecasting
CapacityPlanning
Layout
Product andService Design
ProcessSelection
WorkDesign
TechnologicalChange
Capacity is significantly impacted by process
selection and facility layout.
4
Basic Layout Types
  • Product layout
  • Process layouts
  • Fixed-Position layout
  • Group Technology / Combination layouts

5
Product Layout
  • Facility organized around product
  • Design minimizes line imbalance
  • Delay between work stations
  • Types Fabrication line assembly line

6
Product Layout
Fabrication Line
Assembly Line
  • Assembles fabricated parts
  • Uses workstation
  • Repetitive process
  • Paced by tasks
  • Balanced by moving tasks
  • Builds components
  • Uses series of machines
  • Repetitive process
  • Machine paced
  • Balanced by physical redesign

7
Product Type Layout - Requirements
  • Standardized product
  • High production volume
  • Stable production quantities
  • Uniform quality of raw materials components

8
Product Layout - Flow Diagram Showing the
Production Process for Harley Davidson, York, PA.
9
Product Layout
Raw materials or customer
Station 2
Station 3
Station 4
Finished item
Station 1
Material and/or labor
Material and/or labor
Material and/or labor
Material and/or labor
Used for Repetitive or Continuous Processing
10
Product Layout More Examples
11
Line Balancing Problem
  • Work stations are arranged so that the output of
    one is an input to the next, i.e., a series
    connection
  • Layout design involves assigning one or more of
    the tasks required to make a product to work
    stations
  • The objective is to assign tasks to minimize the
    workers idle time, therefore idle time costs,
    and meet the required production rate for the
    line

12
Line Balancing Problem
  • In a perfectly balanced line, all workers would
    complete their assigned tasks at the same time
    (assuming they start their work simultaneously)
  • This would result in no idle time
  • Unfortunately there are a number of conditions
    that prevent the achievement of a perfectly
    balanced line
  • The estimated times for tasks
  • The precedence relationships for the tasks
  • The combinatorial nature of the problem

13
Assembly Line Balancing Steps
  • 1. Determine tasks (operations)
  • 2. Determine sequence
  • 3. Draw precedence diagram
  • 4. Estimate task times
  • 5. Calculate cycle time
  • 6. Calculate number of work stations
  • 7. Assign tasks
  • 8. Calculate efficiency

14
Assembly Lines Balancing Concepts
Question Suppose you load work into the three
work stations below such that each will take the
corresponding number of minutes as shown. What
is the cycle time of this line?
Answer The cycle time of the line is always
determined by the work station taking the longest
time. In this problem, the cycle time of the
line is 7 minutes. There is also going to be
idle time at the other two work stations.
15
Assembly Lines Balancing Example 1
  • Youve just been assigned the job a setting up an
    electric fan assembly line with the following
    tasks

Total Task Times 11.35 Minutes
16
Assembly Lines Balancing Example 1Structuring
the Precedence Diagram
  • Question Which process step defines the maximum
    rate of production?

Answer Task C is the cycle time of the line and
therefore, the maximum rate of production.
17
Assembly Lines Balancing Example 1The
Bottleneck
18
Assembly Lines Balancing Example 1Cycle Time
Determination
  • Question Suppose we want to assemble 100 fans
    per day. What would our cycle time have to be?

Answer
19
Assembly Lines Balancing Example 1Theoretical
Minimum Number of Workstations
  • Question What is the theoretical minimum number
    of workstations for this problem?

Answer
20
Assembly Lines Balancing Example 1Workstations
Tasks Assignment
D (4.2 - 1.2) 3
C (4.2 - 3.25) 0.95
A (4.2 2 2.2)
E (3 - 0.5) 2.5
B (2.2 1 1.2)
F (2.5- 1) 1.5
G (1.2 -1 0.2)
H (1.5 - 1.4) 0.1
Idle 0.1
Idle 0.95
Idle 0.2
21
Assembly Lines Balancing Example 1Efficiency
of Assembly Line
22
Assembly Line BalancingLayout Heuristics for
Assigning Tasks
  • Basic rules
  • Rule 1 Pick the task with the longest required
    time. Save shorter tasks for fine-tuning
  • Rule 2 Select the task with the largest number
    of followers. This preserves options for
    subsequent. stations and tends to reduce idle
    time.
  • Common Practice Use rule 2. When ties exist use
    rule 1

23
Assembly Lines Balancing Example 2
Vickis Pizzeria and the Precedence Diagram
24
Assembly Lines Balancing Example 2
  • Determine output rate
  • Vicki needs to produce 60 pizzas per hour
  • Determine cycle time
  • The amount of time each workstation is allowed to
    complete its tasks
  • Limited by the bottleneck task (the longest task
    in a process)

25
Assembly Lines Balancing Example 2
  • Compute the theoretical minimum number of
    stations
  • Number of stations needed to achieve 100
    efficiency (every second is used)
  • Always round up (no partial workstations)
  • Serves as a lower bound for our analysis

(
)
å
task times
seconds

165



stations

3
or

2.75,
Stations

of
Number
sec/station

60
time
cycle
26
Assembly Lines Balancing Example 2
  • Assign tasks to workstations
  • Start at the first station choose the longest
    eligible task following precedence relationships
  • Continue adding the longest eligible task that
    fits without going over the desired cycle time
  • When no additional tasks can be added within the
    desired cycle time, begin assigning tasks to the
    next workstation until finished

27
Assembly Lines Balancing Example 2
  • Compute efficiency and balance delay
  • Efficiency () is the ratio of total productive
    time divided by total time
  • Balance delay () is the amount by which the line
    falls short of 100

28
Assembly Lines Balancing Example 3
  • Total Work Content, ?t 306 decimal min.
  • Need 450 dolls/day, one shift per day
  • Available time 420 minutes
  • a. Precedence diagram
  • b. Maximum cycle time (c) 420 min x 100 / 450
    dolls 93
  • c. Minimum number of stations (n) 306/93 3.3
    ? 4
  • d. Assigning work elements to workstations (next
    page)
  • e. Balance delay (nc-?t)/nc (4 x 91) 306
    / (4 x 91) 0.159
  • or 15.9
    idleness among the four stations

29
Assembly Lines Balancing Example 3
30
Assembly Lines Balancing Example 3
31
Assembly Lines Balancing Example 3
Station 3
Station 2
Station 4
Station 1
32
Assembly Lines Balancing Example 4 Precedence
Graph for Credit Applications
33
Assembly Lines BalancingBalancing the Work
Through Better Work Flow Design
34
Assembly Lines Balancing - Layout Design
U-Shaped or horseshoe arrangements better enable
workers communications and task sharing
Connections of subassembly islands S feed
parts/components to end-assembly E islands -
each island functions as a separate team
35
Line Balancing Procedure Summarized
  • Determine the cycle time and the minimum number
    of workstations.
  • Make assignments to workstations in order,
    beginning with Station 1. Tasks are assigned to
    workstations moving from left to right through
    the precedence diagram.
  • Before each assignment, use the following
    criteria to determine which tasks are eligible to
    be assigned to a workstation
  • All preceding tasks in the sequence have been
    assigned.
  • The task time does not exceed the time remaining
    at the workstation.
  • If no tasks are eligible, move on to the next
    workstation

36
Line Balancing Procedure Summarized
  • After each task assignment, determine the time
    remaining at the current workstation by
    subtracting the sum of times for tasks already
    assigned to it from the cycle time
  • Break ties that occur using one of these rules
  • Assign the task with the longest task time.
  • Assign the task with greatest number of
    followings.
  • Continue until all tasks have been assigned to
    workstations.
  • Compute appropriate measures (e.g., percent idle
    time, efficiency) for the set of assignments.
Write a Comment
User Comments (0)
About PowerShow.com