Title: FIDIC 2005 Beijing Workshop 13 Design - Build
1FIDIC 2005 BeijingWorkshop 13 Design - Build
- Opportunities and Challenges in Australasia
Tony Barry, President Association of Consulting
Engineers Australia Director Connell Wagner Pty
Ltd
2Project Delivery
- Traditional Construct Only
- Design Construct (DC)
- Design, Construct Maintain (DCM)
- Build Own Operate (BOO)
- Build Own Operate Transfer (BOOT)
- Public Private Partnerships (PPP)
- Alliances
3Design Construct
- Design-Build Design Construct
- There is a DC Contract embedded in every PPP,
BOOT, BOT, DCM contract - DC is the most common form of project delivery
in the Building, Urban Infrastructure and Power
Generation Markets in Australia - Construct Only Contracts most common in NZ, DC
increasing
4Roles for the Consulting Engineer in DC
- Owners Planner and Engineer
- Bankers Engineer
- Contractors Designer
- Contractors Verifier
- Proof Engineer (Principal Contractor)
- Construction Verifier (Principal Contractor)
- Independent Reviewer (Principal Contractor)
5Why Design Construct ?
- Initially
- Reduce claims by contractors against Principals
- Innovation without risk
- Larger projects contractors perceived with
greater capacity to manage than government - Speed of Delivery
- Cost and program, both risks to politicians
6Why Design Construct ?
- Now
- Total risk transfer from Principal to Contractor
very few claims - Innovative Solutions
- Successful delivery, great projects
- Even larger projects
- Speed of Delivery
- Projects delivered in one political term
7The Risk Environment for Consultants
- Legal framework Common Law, Contract Law, Trade
Practices Act, Occupational Health Safety Acts - Onerous Agreements
- Contractors capacity
- Contractors plan to deal with commercial loss
8The Risks
- Client risk dumping
- Risks inherent in Design Construct
- Tender process suppresses risk
- Client Information risk
- The risks are commercial risks
- Losses crystalise in the DC team
- Contractor has no avenue to claim against client
- Claim against consultant
- PI cannot support commercial risks
9Onerous Terms
- High standards of care
- Responsibility for client supplied information
- Absolute Fitness for Purpose warranties
- Strict compliance
- Open ended Indemnities
- Duty of Care to multiple parties
- Liability for delays outside control
- Disclosing terms of PI Policy
10The Solution
- Dont accept unreasonable terms walk away
- Negotiate a good contract to maintain a good
relationship and a good business - Use Limits of Liability above which Clients carry
the risk - Adopt commercially sustainable PI Insurance
levels and guidelines - Negotiate scope carefully and exclude others
responsibilities
11The Future
- More Design Construct
- Bigger projects
- Fewer contractors
- Higher cost to Principals
- More work and more opportunity for Consulting
Engineers - More claims and litigation
- Better risk management by all parties
12Better Risk Management
- Open identification and pricing in tenders
- Risk sharing with agreed specified outcomes
- Limitation of liability for contractors and
consultants - Risk management record and tender evaluation
criteria
13Design Construct Business Model
Principal
Total Risk Transfer
D C Contractor
Risk Transfer
Risk Transferred or Managed
Consultant
Subcontractors
14ContractorConsultant Liability Transfer Model
- Master servant relationship
- Head contract conditions passed down
- Risk transfer through onerous terms
- Impossible and impractical notice requirements
- Representations designed to create TPA breaches
- Certify compliance or breach contract
- Excessive and protective administration
- Aggressive and manipulative behaviours
- Designers site role suppressed / limited
- Post-contract claims and disputes
- Careers destroyed
15ContractorConsultant Liability Managed Model
- Co-operative integrated relationship
- Methods of managing Head contract conditions
agreed without transfer to consultant - Consultant carries negligence risk
- Consultant assists Contractor to identify and
manage risks - Contractor to certify compliance or
non-conformance - Consultant to retain independent judgement
- Consultant uses Contractor administrative systems
- Co-operative behaviours and excellent performance
- Designers site role expanded and integrated
- Post-contract awards
- Careers enhanced
16Tony Barry Connell Wagner Pty Ltd on behalf
of Level 12, 75 Miller Street North
Sydney NSW 2059 (02) 99224711 www.acea.com.au
acea_at_acea.com.au