Title:
1ENERGY CONSERVATION EFFORTS AT RCF
R. P. SHARMA, Dy. General Manager, R.C.F. Ltd.,
Mumbai
- By
- R. P. Sharma, Dy. G.M.
- TECHNICAL SERVICES
- RASHTRIYA CHEMICALS FERTILIZERS LTD. TROMBAY
UNIT MUMBAI
2MAJOR ENERGY INPUTS
STEAM
ASSOCIATED GAS
ELECTRICITY
FUEL OIL
3AVERAGE CONSUMPTION LEVELS AT FULL LOAD
ASSOCIATED GAS 2.0 MMSCM per Day 660 MMSCM per Year
POWER 1000 MWH per Day 3,30,000 MWH per YEAR
4APPROACH TOWARDS ENERGY CONSERVATION
REPORTING REVIEWING
ENERGY AUDITS
SUGGESTION SCHEMES
5- METHODOLOGY FOR EVALUATION OF ENERGY CONSERVATION
SCHEMES
- Is the scheme Techno-Economically viable ?
- Is adequate space available for the
modification?
- Is proven technology available for the
proposed scheme ?
- Is the scheme adversely affecting plant startups
or shutdowns? - Is the extra pressure drop created by
modification permissible?
6- METHODOLOGY FOR EVALUATION OF ENERGY CONSERVATION
SCHEMES
- Is there a possibility of using some idle
equipment within the factory ?
- Is the downtime required for modification
acceptable ?
- Is the recovery of energy in one plant going to
increase consumption in other plant/section ?
- Is the modification adversely affecting
operational reliability ?
7TECHANICAL INPUTS
- REDUCE CORE LOSSES OF TRASFORMERS.
- MINIMISING AIR CONDITIONG LOSSES.
- PLUGGING COMPRESSED AIR LOSSES.
- USE OF ENERGY EFFICIENT LAMPS.
- REDUCING PRESSURE LOSS IN COMPRESSED AIR
SYSTEMS. - SIZING OF STEAM HEADERS AS PER ACTUAL STEAM
REQUIREMENT. - THOROUGH INSULATION SURVEY.
8TECHANICAL INPUTS
- THOROUGH SURVEY OF STEAM TRAPS FUNCTIONING.
- ANALYSE FOR EXCESS OXYGEN IN ALL FIRED HEATERS.
- IMPROVING CONDENSATE RECOVERY AT ALL POSSIBLE
POINTS. - IMPROVEMENT OF POWER FACTOR.
- INSTALLING ELECTRICAL ENERGY METERS FOR ALL
MAJOR ELECTRICAL ENERGY DRIVES TO KEEP CONSTANT
CHECK.
9TECHANICAL INPUTS
- INSTALLING ELECTRICAL ENERGY METERS FOR ALL MAJOR
ELECTRICAL ENERGY DRIVES TO KEEP CONSTANT CHECK. - IDENTIFY MAJOR HEAT LOSSES THROUGH FLUE GASES IN
STACK. - UTILIZATION OF WASTE HEAT SOURCE AVAILABLE AT
ONE LOCATION FOR HEATING OTHER STREAM OF OTHER
UNITS. - SAVING OF ELECTRICAL ENERGY BY MAXIMIZATION OF
THE OUTPUT i.e. BALL MILL - OPTIMIZATION OF WATER FLOW TO HEAT EXCHANGERS.
10MAJOR SCHEMES / SUGGESTIONS IMPLEMENTED (2008-09)
Sr. NO PLANT SCHEME ENERGY SAVING POTENTIAL (Estimated)
1 Ammonia I Ammonia I Ammonia I
Cooling Tower pumps B D are replaced with higher capacity pumps. This shall enable plant to run with only 2 CT pumps instead of 3 pumps Cooling Tower pumps B D are replaced with higher capacity pumps. This shall enable plant to run with only 2 CT pumps instead of 3 pumps 1.52 Lakh kwH power saving.
Provision is made to take DM Water directly to Ammonia-1 plant Deaerator from Ammonia-V Provision is made to take DM Water directly to Ammonia-1 plant Deaerator from Ammonia-V 0.88 Lakh kwH power saving
2 Methanol Methylamine plant Methanol Methylamine plant Methanol Methylamine plant
11 kW Slope water (P3) pump is kept stopped and slope water is pumped directly form PP-103 Pump to LP Deaerator 11 kW Slope water (P3) pump is kept stopped and slope water is pumped directly form PP-103 Pump to LP Deaerator 0.87 Lakh kwH power saving
Instrument Air Compressor (CPT compressor) is kept stopped and Instrument Air is being taken from Factory IA grid Instrument Air Compressor (CPT compressor) is kept stopped and Instrument Air is being taken from Factory IA grid 5.50 Lakh kwH power saving
11CONTINUED
Sr. NO PLANT SCHEME ENERGY SAVING POTENTIAL (Estimated)
1 Ammonia V Ammonia V Ammonia V
Corro - coating of six cooling tower pumps has been carried out. This has increased throughput of pumps and hence enabled stoppage of one pump. Corro - coating of six cooling tower pumps has been carried out. This has increased throughput of pumps and hence enabled stoppage of one pump. 42.06 Lakh kwH power saving.
Energy efficient coating of refractory in primary reformer resulted in reduction of Reformer fuel consumption by 1. Energy efficient coating of refractory in primary reformer resulted in reduction of Reformer fuel consumption by 1. 6.20 Lakh Nm3 Fuel saving
12ENERGY INTENSIVE PROCESSES
13ASSOCIATED GAS
STEAM
ASSOCIATED GAS COMPRESSORS
BOILER 3 X 170 TPH 105 ATA/510deg
FUEL GAS
FEED GAS
AMMONIA V 1045 MTPD
AMMONIA-I 350 MTPD
NH3
UREA 1000 MTPD
CO2
AMMONIA TO SUPHALA,A.B.C., NITRIC ACID,ANP PLANT
PRODUCT UREA
14Ammonia V
SCHEMES IMPLEMENTED AT RCF TROMBAY
- Revamp of Ammonia V plant
- Reduction in specific energy by 2 MKcal/Mt.NH3
- IMPLEMENTED
- Details of the project are as follows
15The Revamp of Primary Reformer
- Replacement of staggered tube lay out with single
row tube lay out. The furnace extended on the
west side to add one more collector to
accommodate required no. of tubes. - Increase in tube size from OD/ID 143 / 117 to
152 / 129 mm. - Replacement of inlet distributors and pig tails.
- Replacement of outlet hot collectors.
16The Revamp of Primary Reformer
- Installation of combustion air pre-heater in
waste heat section in lieu of BFW preheater. - Installation of combustion air blower with dual
drive (common with fired steam superheater). - Replacement of burners by forced draft type
burners. - Modification of roof and floor along with
refractory. - Installation of triple decker catalyst.
17- Auxiliary steam superheater
- Modification and installation of raw gas
preheater coil and combustion air pre heater in
the waste heat section of Auxiliary steam
superheater to save fuel. -
- Auxiliary steam superheater burners replaced
with forced draft type.
18- LT Catalyst Temp. Control
- L.T. guard catalyst volume could not be used
fully as the inlet temperatures of LT guard and
LT main could not be controlled independently. - This problem was solved by modification in
Primary Reformer convection zone. - BFW pre-heater in primary reformer was replaced
by combustion air preheater and this BFW
preheater is located in between LT guard and LT
main.
19- M.P. Condensate Stripper
- Installation of medium pressure condensate
stripper in place of low pressure condensate
stripper led to following benefits - a. Reduction in ammonical effluent
- b. Reduction of low pressure steam consumption.
- Installation of condensing type turbine on this
low pressure steam enabled to stop motor driven
BFW pump thus saving electricity.
20- CO2 Removal / Methanation
- Modified reformer allowed reduction in steam
carbon ratio to 3.2. This reduced available heat
of regeneration for CO2 removal section. Below
mentioned modifications in CO2 removal section
further reduced energy requirement of this
section. - Installation of 5 stage flash vessel with
mechanical steam compressor. - Installation of hydraulic turbine with generator
on rich solution - Replacement of tower packing by high efficiency
IMTP or equivalent packing.
21CO2 Removal / Methanation
- Installation of additional gas/gas exchanger
(E311B) - Installation of additional DM water pre-heater
for steam generation plant to recover all the
heat available with low pressure CO2. Apart from
saving steam required for de-aerator in steam
generation plant, this modification eliminated
all air cooler fans used for this service.
22Flare System
- Installation of new hot flare system in place of
cold vent stack as pollution abatement measure. -
- In new scenario where no surplus low pressure
steam is envisaged, this may lead to saving due
to reduction in low pressure steam requirement.
23New Synthesis Compressor Revamp
- In this connection following options for the
revamp of Synthesis section are also considered - - Modification of synthesis loop by additional
converter and Installation of loop boiler. - L.P Condensing Turbine for B.F.W Pump.
24- AMMONIA-I
- SCHEME SPARE MOTOR FOR AMMONIA UNLOADING
COMPRESSOR IN AMMONIA STORAGE - EXPENDITURE Rs. 22 LAKHS
- BENEFITS ACHIEVED UNINTERRUPTED OPERATION OF THE
AMMONIA STORAGE FACILITY AND OTHER PLANTS - IMPLEMENTED
25- AMMONIA-I
- SCHEME BATTERY BANK FOR 11 KV SWITCHGEAR
-
- EXPENDITURE Rs. 3 LAKHS
- BENEFITS ACHIEVED TO MEET THE REQUIREMENT OF NEW
11KV SWITCHGEAR OPERATION, CONTROL AND RELAYING - IMPLEMENTED
26AMMONIA-I
- Scheme New purge gas line from Ammonia I Plant
to NSGP boilers to be used as fuel - Saving 0.5MKcal/MT of ammonia (Opportune
saving) - IMPLEMENTED
27INDUSTRIAL PRODUCTS
28FUEL GAS
FEED GAS
METHANOL 150 MTPD
AMMONIA
METHYLAMINES 12 MTPD
METHANOL
METHYLAMINES
29MPNAP
- Scheme Replacing cooling tower pumps of MP
Nitric Acid plant with higher capacity resulted
in stopping of one pump - Savings in Power 27.45 lakh KwH
- (Rs. 142.72 lakhs)
- IMPLEMENTED
30HPNAP
- Scheme Cooling tower pumps of HPNA are also kept
stopped whenever HPNA plant is shutdown. - Savings in Power 3.51 lakh KwH
- (Rs. 18.25 lakhs)
- IMPLEMENTED
31Sulphuric Acid Plant
- Scheme Increasing surface area of plate coolers
and replacing CW pump with new pump - Savings in Power 2.38 lakh KwH
- (Rs. 12.38 lakhs)
- IMPLEMENTED
32Sewage Treatment Plant
- Scheme Installation of low capacity sewage pump
to replace present high capacity pump - Savings in Power 0.65 lakh KwH
- (Rs. 3.38 lakhs)
- IMPLEMENTED
33Sewage Treatment Plant
- Scheme Installation of Online DO meter to
monitor DO in aeration tank on continuous basis.
This has helped in optimizing running of aerators
to maintain DO level between 2mg/l to 3 mg/l. - Savings in Power 3.58 lakh KwH
- (Rs. 18.62 lakhs)
- IMPLEMENTED
34Sewage Treatment Plant
- Scheme Installation of Solar Water Heater
resulting in stopping of 2 Electric Water Heaters
of 22 kW used to heat water from 40 deg C to 60
deg C for 12 hours per day. - Savings in Power 0.33 lakh KwH (Estimated)
- (Rs. 1.60 lakhs)
- Pay Back Period 4 Years
- IMPLEMENTED
35Steam Generation Plant
- Scheme Procurement of Online DO meter to monitor
DO in aeration tank on continuous basis. This has
helped in optimizing running of aerators to
maintain DO level between 2mg/l to 3 mg/l. - Savings in Fuel 6.64 lakh KwH
- (Rs. 34.50 lakhs)
- IMPLEMENTED
36CNA PLANT
- Utilization of Excess chiller capacity available
in CNA plant for cooling CAN control room. - Savings in Power 0.51 lakh KwH (Estimated)
- (Rs. 2.65 lakhs)
- IMPLEMENTED
37Power Factor Improvement
- Carried out Power factor study at various load
centers. - Installed LT HT capacitor banks at various
plants. - Power Factor improved up to 0.98
- Savings- Approx. Rs. 2.4 crores / Year
- IMPLEMENTED
- Additional Capacitor units are being installed to
improve power factor up to unity. - Savings - Expected Rs. 6 crores / Year
38Energy Saving Through Tube Light Fitting
- Replaced conventional tube light chokes (copper
balast 15 w) with electronic chokes (500 nos.) - Saving / fitting 15 watts.
- Energy saving 18000 kwH per year.
- (Rs. 0.95 lakhs)
- IMPLEMENTED
39Energy Saving With Control Voltage Transformers
(CVT)
- CVTs used for lighting purpose.
- CVT maintains constant voltage resulting in
increase of lamp life. - Energy saving 30000 kwH per year.
- (Rs. 1.56 lakhs)
- IMPLEMENTED
40COMPLEX FERTILIZERS
41CO2
AMMONIA
PHOSPHORIC ACID
ANP
NITRIC ACID PLANT
PHOSPHORIC ACID PLANT
ROCK
SUPHALA
CONC. NITRIC ACID
DIL. H2SO4
SULPHURIC ACID
42- SUPHALA
- Scheme - Interconnection of Process Air Header
and Instrument Air Header - Savings in Power 6.64 lakh KwH
- (Rs. 21.50 lakhs)
- IMPLEMENTED
43SUPHALA
- Scheme One transfer pump is being run for
transferring slurry to both RHS DBN sections
instead of two pumps. - Savings in Power 2.21 lakh KwH
- (Rs. 13.50 lakhs)
-
- IMPLEMENTED
44EFFLUENTS CAN BE ASSESTS
HOW?
45Liquid Waste Reduction Measures at RCF, Trombay
- Recycle of rich effluents in producing plants
thus reducing load of ETP. - Recycle of sewage reject water in various
operating plant instead of fresh water for floor
washings, etc. - Use of Sewage reject water in plants and for
horticulture purposes.
46Improvements in Nutrient Efficiencies
47Improvements in Nutrient Efficiencies
48Improvements in Nutrient Efficiencies