Construction Association of Bhutan - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Construction Association of Bhutan

Description:

Presentation by Construction Association of Bhutan * * * * * * * * * * * * Summary of Points Publication of BSR Allocation of Contract durations Departmental ... – PowerPoint PPT presentation

Number of Views:99
Avg rating:3.0/5.0
Slides: 20
Provided by: GAM83
Category:

less

Transcript and Presenter's Notes

Title: Construction Association of Bhutan


1
  • Presentation
  • by
  • Construction Association of Bhutan

2
Summary of Points
  • Publication of BSR
  • Allocation of Contract durations
  • Departmental Execution of Works
  • Publication of Construction Cost Indices
  • Tendering Issues
  • Cost of Tender Documents
  • Informing the bidders in case of re-tendering
  • Compensation for cancellation of work award

3
1. Publication of BSR
  • Problem Statement
  • BSR is published only after few years time.
  • Un-realistic rates in the BSR
  • Cost index calculation is not carried out
    properly and on a project specific basis. Rather
    some fixed cost index is used all year around.

4
1. Publication of BSR
  • Submission
  • BSR may be published annually
  • Instead of three base towns, Phuntsholing,
    Samdrupjongkhar and Gelephu, the rates be may be
    published for Phuntsholing, Thimphu, Bumthang and
    Trashigang.
  • The work of compilation and publication of BSR
    may be tendered out to the private sector and
    accordingly approved by the government.

5
2. Allocation of Contract Duration
  • Problem Statement
  • Contract durations are fixed on an arbitrary
    basis
  • Some contractors are provided with very relaxed
    Contract durations while the contract durations
    of some contractors are un-reasonably
    constricted.
  • Various factors affecting the implementation are
    not considered while framing the contract
    durations

6
2. Allocation of Contract durations
  • Submission
  • The following factors needs to be considered
    while allocating contract durations
  • climatic conditions of project site (conditions
    during rainy season and winter season)
  • project location (remoteness, transportation of
    materials)
  • Availability of materials (materials
    availability in third countries)
  • Complexity of project (installation of heating
    system etc,)
  • Mobilization of resources

7
3. Department Execution of Works
  • Problem Statement
  • Dzongkahgs executing farm road constructions
  • Field Divisions of Department of Roads are
    executing rehabilitation works departmentally.
  • Contractors mostly at Class C and Petty are
    under-absorbed.

8
3. Department Execution of Works
  • Submission
  • CAB would like to request the government to
    contract out all works to the private sector.

9
4. Publication of Construction Cost Indices
  • Problem Statement
  • Bhutan doesn't have our own cost indices to
    calculate cost escalation
  • Some projects use Whole Sale Price Index of India
    which may not reflect the Bhutanese Scenario.

10
4. Publication of Construction Cost Indices
  • Submission
  • The government need to mandate one relevant
    organization to compile construction cost indices
    on a monthly basis.

11
5. Tendering issues
  • Problem Statement
  • Un-uniform application of rules as listed below
  • Bid is not opened in case of single bidder
  • Bids are rejected for simple reasons
  • Qualification criteria applied for works up to
    Nu. 5 million.
  • Extra criteria are set such as requirement of
    proprietor to be present at the bid opening.

12
5. Tendering issues
  • Problem Statement
  • Un-uniform application of rules as listed below
  • Bid is not opened in case of single bidder
  • Bids are rejected for simple reasons
  • Qualification criteria applied for works up to
    Nu. 5 million.
  • Extra criteria are set such as requirement of
    proprietor to be present at the bid opening.

13
6. Cost of Tender Documents
  • Problem Statement
  • Different agencies are setting varying cost of
    tender documents
  • Some procuring agencies are setting un-reasonably
    high cost of tender documents (as high as Nu.
    20,000.00)

14
6. Cost of Tender Documents
  • Submission
  • To have a uniformity in setting cost of tender
    documents.
  • To charge minimal cost covering for petty
    expenses

15
7. Informing Bidders while re-tendering
  • Problem Statement
  • Re-tendering is often imitated by procuring
    agencies
  • Bidders are not informed after a decision has
    been made to re-tender.

16
7. Informing Bidders while re-tendering
  • Submission
  • Bidders may be informed right after a decision
    has been made by the tender committee to
    re-tender.
  • This would enable the bidders to collect their
    bid security and prepare accordingly for the
    next biding.

17
8. Compensation for Cancellation of work
  • Problem Statement
  • Sometimes work award is cancelled due to
    inability to secure funds for the work
  • It becomes a case of complete lapses of the
    client.

18
8. Compensation for cancellation of work
  • Submission
  • Bidding may be initiated only after securing the
    funding.
  • The winning bidder needs to be fairly compensated
    in case of cancellation of work award.

19
Tashi Delek!
Write a Comment
User Comments (0)
About PowerShow.com