Title: Construction and Structures 2 Proposed Warehouse Development
1Construction and Structures 2Proposed Warehouse
Development
- David Addicoat 201195747
- David Leschke 300258955
- Jozsef Kovago 300331001
- Adrian Carmody - 300162847
2Contents
- Flooring
- Portal framing
- Cladding
- Roofing
- Pre-cast
- Other Building Solutions
- Parking
- Proposed Design for BDC
- References
3Footings
John Doak a commercial/residential builder in the
Geelong district from Impact Property
Development, recommended for this development
that we use a concrete raft slab roughly between
200mm and 500mm depending on soil type and an
engineers report.
www.boral.com.au
4Warehouse Surface
- The Installation of a epoxy resin floor finish
will be required. A mixture of polymeric and
polyurethane will provide a durable surface area
to protect against abrasion and chemical
spillage. The floor surface will be around 1mm
thick. This surface system is called F-100 high
performance epoxy resin floor finish. There is
an option of a conductive or an anti static
finish. The floor colour will be a light blue
colour to allow for spills and other hazards to
be detected. This type of flooring system meets
Australian Standards.
5Portal Frames
- Definition A continuous ridged frame with a
restrained joint between the column and beam.
The frame will act as one structural entity. - Source SRT 251 Construction Structures 2
Lecture Notes - Group Definition Large spaning framework
structure consisting of knee joints between the
columns and rafters allowing for a large column
free open space.
6Benefits of Portal Frames
- Large open space
- Easy to assemble
- Cost effective
- Time saving
- Not labour intensive
7Common Usages of Portal Frames
- Large industrial Buildings
- Sports Stadiums
- Warehouses
- Train stations
- Sheds/Garages
- Halls
- etc.
8General Structure - Knee Joint
- The joining between the u.b rafter usually
consists of either a - - Butt weld
- Hit and miss weld, or
- Fillet weld
- As well as large galvanized bolts. This solid
join allows the live loads such as wind loads to
be directed into the footing.
9General Structure - Apex or Ridge
- This is the highest point in the framing. It
is important that appropriate welds and bolts are
used to fix this point together.
10General Structure HD Connection Bolts
- HD bolts are set into the concrete footings
of the slab. The columns then slip over the top
of these and are bolted in place. The bolts are
then welded tight so they cant undo. The
exposed bolts and base of the column are then
encased in concrete up to the level of the slab
floor, sealing them in.
11Cladding
- Alucobond has been an option for cladding in
our building. This product is a light material
and is easy to work with as well as flexible and
smooth. This product is made up of two aluminium
sheets and an inside of plastic. Its weather
resistant and shock resistant witch makes is a
perfect material for external cladding. - It comes in a standard thickness of 4mm but
can be requested at sizes ranging from 3 to 6mm.
Its standard sizes are 1000, 1250, 1500 by
3200mm and it can be requested to a max width of
1575 and length of 8000mm. It comes in a range
of up to 24 different colours witch you can
requested on order. The product has to meet
Australian Standards 1530 when regarding
insulation and fire protection. Other additional
products include Alucobond Plus (one side
stove-lacquered finished) and Alucobond A2 (one
side stove lacquered).
12Cladding
www.onesteel.com.au
www.onesteel.com.au
13Roofing Members
- C Purlins run from rafter to rafter, fixed by
four bolt cleats which are welded to the rafters
and bolted to the purlins. - Fly bracing is also used to strengthen the C
purlins connection with the rafters. This helps
with resistance against wind uplift and other
live loads.
14Roofing Members
www.bluescope.com.au
Z Purlin
C Purlin
15Roofing Members
- Over the purlins we lay safety mesh before
placing insulation over the mesh. The safety
mesh is connected to the purlins using Tech
screws and washers. - The insulation used is industrial glasswool
with thermal foil underside.
16Roofing Members
www.bluescope.com.au
17Roof Cladding
High tensile steel roof sheeting is used for our
roof cladding. It is lightweight has good
spanning capability and is resilient to rough
conditions. It requires four fasteners per sheet
to perform to its required standard. The sheets
are connected using waterproof tech screws which
drill into the purlins.
18Roof Cladding
www.garages.com.au
www.bluescope.com.au
19Pre-cast Panels
- The reason why we chose this system is
because of the following points - Easiness of erection thus saving on labour costs
- Its pre fabricated therefore increasing product
quality, simplicity and time - Used as a structural element
- Elements can be reproduced with ease due to
per-fabricated forme work
20Pre-cast panels
www.hollowcore.com.au
www.hollowcore.com.au
21Pre-cast hollow core flooring
- Our design incorporates the use of hollow
core floor slabs because - - Easiness of erection thus saving on labour costs
- Its pre fabricated therefore increasing product
quality, simplicity and time - Used as a structural element
- Elements can be reproduced with ease due to
per-fabricated forme work - Lightness benefiting to span ratio
22Pre-cast hollow core flooring
www.hollowcore.com.au
www.hollowcore.com
23Other Building Solutions
- The following include a brief summary of
alternative construction solutions - Timber portal frame
- Concrete portals
- Aluminium roof sheeting
- Fibre cement cladding
- Light weight foam insulated wall panels
- Tilt up concrete panels
24Parking
- Disabled parking 3.2 by 5.4 by 2 space
- Normal parking 2.6. by 5.4 by 18 space
- Loading zone 3.2 by 5.4 by 1 space
25Proposed Design for BDC
Site Plan
26Proposed Design for BDC
Warehouse floor plan
Show Room floor plan
27Proposed Design for BDC
Section A-A
28Proposed Design for BDC
Detail 1. Birds eye view of column. Location
Warehouse. (See floor plan)
29Proposed Design for BDC
Detail 2. Footing detail. Location
warehouse. (See Section A-A)
30Proposed Design for BDC
Detail 3. Column and Rafter knee joint with
guttering. Location Warehouse (See Section A-A)
31Proposed Design for BDC
Detail 4. Ventilated Ridge at Apex Location
Warehouse. (See Section A-A)
32Proposed Design for BDC
Detail 5. Column Rafter knee joint with
guttering and connection with showroom
rafter. Location Warehouse/Showroom (See
Section A-A)
33Proposed Design for BDC
Detail 6. Showroom 1st story floor connection
with pre-cast wall panel. Location
Showroom. (See Section A-A)
34Proposed Design for BDC
Detail 7. Showroom 1st story floor mid point
connection between hollow core floor panels with
support beam column. Location Showroom. (See
Section A-A)
35Proposed Design for BDC
Detail 8. Parapet and box gutter
connection. Location Showroom. (See Section A-A)
36References
- SRT 251 Construction Structures 2 Lecture
notes - Economical structural steelwork, fourth
edition, Australian institute of steel
construction, North Sydney, 1997 - www.boral.com.au
- www.onesteel.com.au
- www.bluescope.com.au
- www.hollowcore.com.au
- www.garages.com.au
- www.alucobond.com.au