Title: Eric S. Petersen, Law Partner Hawkins Delafield
1United States Conference of MayorsUrban Water
Council2005 Urban Water SummitSeptember 30,
2005Albuquerque, New Mexico
Hawkins
Delafield Wood LLP
DESALINATION DESIGN-BUILDTHE SAN JUAN CAPISTRANO PROJECT
- Eric S. Petersen, Law PartnerHawkins Delafield
Wood LLPNew York, NY
2PROJECT ELEMENTS
- 4 MGD reverse osmosis treatment plant with
pretreatment - 8 groundwater extraction wells
- 5,000 acre feet annual production
- Raw and finished water pump stations and
transmission lines - Brine disposal line
3CHALLENGES
- Limited staff availability
- Limited expertise in groundwater treatment
technologies - Aggressive schedule to meet deadlines for 250
per acre foot subsidy from Metropolitan Water
District
4PROJECT GOALS
- Assure adequate water supply through local
sources - Avoid constructing large water reservoir
- Accelerated schedule
- Improved technology
- Single source responsibility
- Performance based contract
- Private sector financing risk
5PROCUREMENT GOALS (1) EARLY PRICE CERTAINTY
- DBB
- City design costs 6 -10 of construction cost
- Bidder's price may exceed designer's estimates
- Project may be delayed or re-designed
- DBO
- City design costs 1-3 of construction cost
- Proposers design to level necessary to guarantee
price - City obtains price and performance guarantees for
low cost
6PROCUREMENT GOALS (2)CHANGE ORDERS MINIMIZED
- DBB
- Bid protests can be common
- Construction monitoring is 6-8 of construction
cost - Change orders can be prevalent
- Litigation often accompanies contract awards and
change order disputes - DBO
- Proposals protests are uncommon
- Construction monitoring is 1-2 of
construction cost - Change orders are rare
- Procurement Litigation is rare
7DBO PROCUREMENT
- CA Government Code 5956
- RFQ/RFP Process
- Concurrent Price, Non-Price Review
- Best Value
- Staff Selection
- Council Contract Approval
8TIMEFRAME
- 1993 2000 planning
- 2000 RFQ Process (Eco Resources, Earth Tech,
Ionics) - 2001 RFP Process
- 2002 Contract Execution and Financing
- 2003 - 2004 Permitting Construction and
Commissioning - 2005 Operations
9PARTICIPANTS
- City of San Juan Capistrano (CVWD)
- Advisors Pirnie and Hawkins
- Contractor Team Eco Resources, Boyle
Engineering, and ARB, Inc. - Guarantor Southwest Water
- Financing Lehman Brothers and AMBAC bond
insurance
10CITY RETAINED RIGHTS AND RESPONSIBILITIES
- Ownership of assets
- Ownership of system revenues
- Setting user rates
- Capital planning
- Bond financing (tax-exempt)
- Securing sites and rights-of-way
- Obtaining water rights (San Juan Basin)
- Obtaining MWD Subsidy
11PRICING AND PERFORMANCE GUARANTEES
- Fixed Design-Build Price (25 million)
- Fixed Annual Service Fee (1.1 million)
Electricity (1.0 million) - Water Treatment (7 enhanced standards)
- Water Delivery (5,280 acre feet/year)
- Production Efficiency (80)
- Hydraulic Transients
- Electricity Usage (Guaranteed Maximum Utilization
of 9,092,300 KWH/year and Guaranteed Max Demand
of 1,275 KWH)
12RISKS TRANSFERRED (1)
- Internal disputes among designer, builder,
operator, and equipment supplier - Design, permitting, construction and operating
cost overruns - Scheduled Acceptance Date (2 years permitting,
design, construction, commissioning, acceptance
testing) - Extension Period
13RISKS TRANSFERRED (2)
- Subsurface geotechnical risk
- Regulatory compliance (fines, penalties)
- Capital maintenance risk (major maintenance,
repair and replacement) - Energy consumption excesses
- Loss of MWD subsidy due to Company
non-performance
14FOCUS ON PERMITTING RISKS
- DHS Domestic water supply permit
- Pilot testing
- Terms and conditions
- Delay
- Non-issuance
- Payment for permitting design costs
15RISKS NOT TRANSFERRED (1)
- Uncontrollable Circumstances
- Pre-existing environmental conditions
- Specified site conditions
- Buried infrastructure repair costs
- Changes in law
- Force majeure
16RISKS NOT TRANSFERRED (2)
- Raw water quality exceedencers
- General electricity rates (Indexed)
- General price inflation (Indexed)
- General interest rates
17SECURITY FOR PERFORMANCE
- Southwest Water
- (Parent Guaranty)
- Performance and bonds
- Letter of credit (1.5 years debt service for
AMBAC) - No stated monetary limit on liability
18DBO SAVINGS
- Source of savings
- Core competency
- Competition as to design operator-driven
- Competition as to operation
- Cooperative relationship between designer,
builder and operator - Smaller contingency allowances
- Bulk consumables buying power
- Broader technology access
- Preventive v. breakdown maintenance
- Optimized balance between capital and operating
costs - Excessive redundancy eliminated
19FINANCING PLAN
- No SRF funding
- City revenue debt
- Enterprise fund
- Tax-exempt (IRS Rev. Proc. 97-13)
- Ambac Bond Insurance
- Feasibility study
20CONTRACTOR FINANCING SUPPORT
- City debt cancelled if Company defaults
- Directly transfers completion and performance
risks to Company - Southwest repays Ambac up to 6.0 million
- Ambac has cure rights
21MUNICIPAL CONTROL
- Comprehensive asset development and management
- Minimum design requirements and quality standards
- Performance guarantees (repairs, fines, damages)
- Costs guaranteed
- Management by full-service contract
- Vigorous, broader competition and cooperation
- Convenience termination rights (10 years)
22LESSONS LEARNED
- Allow full vendor comment on proposed transaction
and listen - Private financing and siting complicates the
transaction - Minimum design requirements are key
- Early pilot testing is advisable
- Attempted transfer of excessive risk is counter
productive
23INGREDIENTS FOR SUCCESS
- Initial strategic planning
- Thoughtful, well developed RFQ/RFP
- Creative and responsive proposals
- Clear, comprehensive contract
- Full proposer due diligence opportunity
- Fair and balanced risk allocation
- Outstanding leadership