Title: PCI 6th Edition
1PCI 6th Edition
2Presentation Outline
- Planning Discussion
- Stripping Process Design and Analysis
- Prestress / Post Tension Effects
- Handling Devices
- Stripping Stress Examples
- Storage Discussion
- Transportation Discussion
- Erection Discussion
3Introduction
- The loads and forces on precast and prestressed
concrete members during production,
transportation or erection will frequently
require a separate analysis - Concrete strengths are lower
- Support points and orientation are usually
different from members in their final position
4Pre-Planning Piece Size
- The most economical piece size for a project is
usually the largest, considering the following
factors - Stability and stresses on the element during
handling - Transportation size and weight regulations and
equipment restrictions
5Pre-Planning Piece Size
- Available crane capacity at both the plant and
the project site. - Position of the crane must be considered, since
capacity is a function of reach - Storage space, truck turning radius, and other
site restrictions
6Planning and Setup
- Once a piece has been fabricated, it is necessary
to remove it from the mold without being damaged. - Positive drafts or breakaway forms should be used
to allow a member to lift away from the casting
bed without becoming wedged within the form - Adequate draft also serves to reduce trapped air
bubbles.
7Planning and Setup
- Lifting points must be located to keep member
stresses within limits and to ensure proper
alignment of the piece as it is being lifted - Members with unsymmetrical geometry or projecting
sections may require supplemental lifting points
and auxiliary lifting lines to achieve even
support during handling - Come-alongs or chain-falls are frequently
used for these auxiliary lines
8Planning and Setup
- When the member has areas of small cross section
or large cantilevers, it may be necessary to add
a structural steel strongback to the piece to
provide added strength
9Planning and Setup
- Members that require a secondary process prior to
shipment, such as sandblasting or attachment of
haunches, may need to be rotated at the
production facility. In these cases, it may be
necessary to cast in extra lifting devices to
facilitate these maneuvers
10Planning and Setup
- When developing member shapes, the designer
should consider the extra costs associated with
special rigging or forming, and pieces requiring
multiple handling
11Stripping General
- Orientation of members during storage, shipping
and final in-place position is critical in
determining stripping requirements - They can be horizontal, vertical or some angle in
between - The number and location of lifting devices are
chosen to keep stresses within the allowable
limits, which depends on whether the no
cracking or controlled cracking criteria is to
be used
12Stripping General
- It is desirable to use the same lifting devices
for both stripping and erection however,
additional devices may be required to rotate the
member to its final position
13Stripping General
- Panels that are stripped by rotating about one
edge with lifting devices at the opposite edge
will develop moments as shown
14Stripping General
- When panels are stripped this way, care should be
taken to prevent spalling of the edge along which
the rotation occurs - A compressible material or sand bed will help
protect this edge
15Stripping General
- Members that are stripped flat from the mold will
develop the moments shown
16Stripping General
- In some plants, tilt tables or turning rigs are
used to reduce stripping stresses
17Stripping General
- Since the section modulus with respect to the top
and bottom faces may not be the same, the
designer must select the controlling design
limitation - Tensile stresses on both faces to be less than
that which would cause cracking - Tensile stress on one face to be less than that
which would cause cracking, with controlled
cracking permitted on the unexposed face - Controlled cracking permitted on both faces
18Stripping General
- If only one of the faces is exposed to view, the
exposed face will generally control the stripping
method
19Rigging Configurations
- Stresses and forces occurring during handling are
also influenced by the type of rigging used to
hook up to the member
20Rigging Configurations
- Lift line forces for a two-point lift using
inclined lines are shown
21Rigging Configurations
- When the sling angle is small, the components of
force parallel to the longitudinal axis of the
member may generate a significant moment due to
secondary effects
22Rigging Configurations
- While this effect can and should be accounted
for, it is not recommended that it be allowed to
dominate design moments
23Rigging Configurations
- Consideration should be given to using spreader
beams, two cranes or other mechanisms to increase
the sling angle - Any such special handling required by the design
should be clearly shown on drawings
24Rigging Configurations
- Using a spreader beam can also eliminate the use
of rolling blocks - Note that the spreader beam must be sufficiently
stiffer than the concrete panel to limit panel
deflections and cracking - Lifting hook locations, hook heights, and sling
lengths are critical to ensure even lifting of
the member - For analysis, the panel acts as a continuous beam
over multiple supports
25Stripping Design
- To account for the forces on the member caused by
form suction and impact, it is common practice to
apply a multiplier to the member weight and treat
the resulting force as an equivalent static
service load. - The multipliers cannot be quantitatively derived,
so they are based on experience
26Stripping Design
- PCI provides a table of typical values
27Factor of Safety
- When designing for stripping and handling, the
following safety factors are recommended - Use embedded inserts and erection devices with a
pullout strength at least equal to four (4) times
the calculated load on the device. - For members designed without cracking, the
modulus of rupture (MOR) , is divided by a safety
factor of 1.5.
28Stress Limits Crack Control
- Stress limits for prestressed members during
production are discussed in Section 4.2.2.2 of
the the PCI Handbook - ACI 318-02 does not restrict stresses on
non-prestressed members, but does specify minimum
reinforcement spacing, as discussed in Section
4.2.2.1. (PCI chapter 4 member design)
29Stress Limits Crack Control
- Members which are exposed to view will generally
be designed for the no discernible cracking
criteria (see Eq. 4.2.2.2), which limits the
stress to . - In the case of stripping stresses, f'ci should be
substituted for f'c - Whether or not the members are exposed to view,
the strength design and crack control
requirements of ACI 318-02, as discussed in
Chapter 4 of this Handbook, must be followed.
30Benefits of Prestressing
- Panels can be prestressed, using either
pretensioning or post-tensioning. - Design is based on Chapter 18 of ACI 318-02, as
described in Chapter 4 of this Handbook. Further,
tensile stresses should be restricted to less
than , must be followed.
31Benefits of Prestressing
- It is recommended that the average stress due to
prestressing, after losses, be within a range of
125 to 800 psi - The prestressing force should be concentric with
the effective cross section in order to minimize
camber, although some manufacturers prefer to
have a slight inward bow in the in-place position
to counteract thermal bow - It should be noted that concentrically
prestressed members do not camber, hence the form
adhesion may be larger than with members that do
camber
32Strand Recomendation
- In order to minimize the possibility of splitting
cracks in thin pretensioned members, the strand
diameter should not exceed that shown in the
table below - Additional light transverse reinforcement may be
required to control longitudinal cracking
33Strand Recommendations
- When wall panels are post-tensioned, care must be
taken to ensure proper transfer of force at the
anchorage and protection of anchors and tendons
against corrosion - Straight strands or bars may be used, or, to
reduce the number of anchors, the method shown
may be used
34Strand Recommendation
- It should be noted that if an unbonded tendon is
cut, the prestress is lost. This can sometimes
happen if an unplanned opening is cut in at a
later date
35Handling Devices
- Since lifting devices are subject to dynamic
loads, ductility of the material is a requirement - Deformed reinforcing bars should not be used as
the deformations result in stress concentrations
from the shackle pin - Also, reinforcing bars may be hard grade or
re-rolled rail steel with little ductility and
low impact strength at cold temperatures
36Handling Devices
- Strain hardening from bending may cause
embrittlement - Smooth bars of a known steel grade may be used if
adequate embedment or mechanical anchorage is
provided - The diameter must be such that localized failure
will not occur by bearing on the shackle pin
37Aircraft Cable Loops
- For smaller precast members, aircraft cable can
be used for stripping and erection purposes - Aircraft cable comes in several sizes with
different capacities - The flexible cable is easier to handle and will
not leave rust stains on precast concrete
38Aircraft Cable Loops
- For some small precast members such as coping,
the flexible loops can be cast in ends of members
and tucked back in the joints after erection - Aircraft cable loops should not be used as
multiple loops in a single location, as even pull
on multiple cables in a single hook is extremely
difficult to achieve - User should ensure that the cable is clean and
that each leg of the loop is embedded a minimum
of 48 in.
39Prestressing Strand Loops
- Prestressing strand, both new and used, may be
used for lifting loops - The capacity of a lifting loop embedded in
concrete is dependent upon the strength of the
strand, length of embedment, the condition of the
strand, the diameter of the loop, and the
strength of the concrete
40Prestressing Strand Loops
- As a result of observations of lift loop behavior
during the past few years, it is important that
certain procedures be followed to prevent both
strand slippage and strand failure - Precast producers tests and/or experience offer
the best guidelines for the load capacity to use - A safety factor of 4 against slippage or breakage
should be used
41Strand Loops Recommendations
- In lieu of test data, the recommendations listed
below should be considered when using strand as
lifting loops. - Minimum embedment for each leg of the loop should
be 24 in. - The strand surface must be free of contaminants,
such as form oil, grease, mud, or loose rust,
which could reduce the bond of the strand to the
concrete
42Strand Loops Recommendations
- Continued
- The diameter of the hook or fitting around which
the strand lifting eye will be placed should be
at least four times the diameter of the strand
being used - Do not use heavily corroded strand or strand of
unknown size and strength.
43Strand Loops Recommendations
- In the absence of test or experience, it is
recommended that the safe load on a single 1/2
in. diameter 270 ksi strand loop satisfying the
above recommendations not exceed 8 kips - The safe working load of multiple loops may be
conservatively obtained by multiplying the safe
load for one loop by 1.7 for double loops and 2.2
for triple loops
44Strand Loops Recommendations
- To avoid overstress in one loop when using
multiple loops, care should be taken in the
fabrication to ensure that all strands are bent
the same - Thin wall conduit over the strands in the region
of the bend has been used to reduce the potential
for overstress
45Strand Loops Recommendations
- When using double or triple loops, the embedded
ends may need to be spread apart for concrete
consolidation around embedded ends without voids
being formed by bundled strand
46Threaded Inserts
- Threaded inserts can have NC (National Course) or
coil threads - Anchorage is provided by loop, strut or
reinforcing bar - Inserts must be placed accurately because their
safe working load decreases sharply if they are
not perpendicular to the bearing surface, or if
they are not in a straight line with the applied
force
47Threaded Inserts
- Embedment of inserts close to an edge will
greatly reduce the effective area of the
resisting concrete shear cone and thus reduce the
tension safe working load of the embedded insert - When properly designed for both insert and
concrete capacities, threaded inserts have many
advantages - However, correct usage is sometimes difficult to
inspect during handling operations
48Threaded Inserts
- In order to ensure that an embedded insert acts
primarily in tension, a swivel plate as indicated
in should be used
- It is extremely important that sufficient threads
be engaged to develop the strength of the bolt
49Threaded Inserts
- For straight tension loads only, eye bolts or
wire rope loops provide a fast method for
handling precast members. - Do not use either device if shear loading
conditions exist.
50Proprietary Devices
- A variety of castings or stock steel devices,
machined to accept specialized lifting assemblies
are used in the precast industry
51Proprietary Devices
- These proprietary devices are usually recessed
(using a pocket former) to provide access to
the lifting unit. The recess allows one panel to
be placed against another without cutting off the
lifting device, and also helps prevent spalling
around the device - Longer devices are used for edge lifting or deep
precast concrete members - Shallow devices are available for thin precast
concrete members.
52Proprietary Devices
- The longer devices usually engage a reinforcing
bar to provide greater pullout capacity, and
often have holes for the bar to pass through as
shown to the left
53Proprietary Devices
- These units have a rated capacity as high as 22
tons, with reductions for thin panels or close
edge distances - Supplemental reinforcement may be required to
achieve these values - Shallow units usually have a spread foot or base
to increase pullout capacity
54Proprietary Devices
- Reinforcing bars are required in two directions
over the base to fully develop the lifting unit,
as shown in Figure below - These inserts are
- rated up to 8 tons
55Proprietary Devices
- Some lifting eyes do not swivel, so rotation may
be a concern - In all cases manufacturer recommendations should
be rigorously followed when using any of these
devices
56Wall Panel Example
- This example and others in Chapter 5 illustrate
the use of many of the recommendations in this
chapter - They are intended to be illustrative and general
only - Each manufacturer will have its own preferred
methods of handling
57Wall Panel Example
- Given
- A flat panel used as a loadbearing wall on a
two-story structure, as shown on next slide - Section properties (nominal dimensions are used
for design) - Solid panel Panel with
openings - A 960 in2 A 480 in2
- Sb St 1280 in3 Sb St 640 in3
- Ix 5120 in4 Ix 2560 4 in4
- Unit weight _at_ 150 pcf 100 psf 0.100 ksf
- Total weight 35.2 kips (solid panel)
- 29.2 kips (panel w/
openings)
58Wall Panel Example
59Wall Panel Example
- Stripping method
- Inside crane height prevents panel from being
turned on edge directly in mold, therefore, strip
flat - Handling multipliers
- Exposed flat surface has a smooth form finish
with false joints. Side rails are removable. Use
multiplier of 1.4
60Wall Panel Example
- f'ci at stripping 3000 psi
- Allowable tensile stresses at stripping and
lifting - Problem
- Check critical stresses involved with stripping.
Limit stresses to 0.274 ksi. - Compare Simple Solution to Mechanics Solution
61Solution Steps
- Step 1 Determine section properties
- Step 2 Select number of pick points and
determine maximum stress - Step 3 Determine stress from mechanic
approach - Step 4 Check panel with opening
- Step 5 Check rolling block solution
- Step 6 Check transverse bending
- Step 7 Check secondary effects
62Step 1 Determine Section Properties
- Solid panel dimensions
- a 10 ft, b 35.2 ft, a/2 5 ft 60 in.
-
- S for resisting section (half of panel width)
63Step 2 4-point pick
- Figure 5.36.1.1(a) (page 5-5)
64Step 2 Check Stresses
- 4 Point Stresses
- Not Good try 8 point pick
65Step 2 8 Point Pick
- Figure 5.3.1.1(b) (Page 5-5)
66Step 2 Check Stresses
67Step 3 Mechanics of Materials
68Step 4 Panel With Openings
69Step 5 Rolling Blocks
- If using a rolling block for handling as shown
below, the panel cannot be analyzed with the
previous method - Each leg of continuous cable over a rolling block
must carries equal load
70Step 5 Rolling Block
71Step 6 Transverse Bending
- Consider lower portion of panel with openings
- Note that Figure Without the concrete in the area
of the opening, the weight is reduced and
unevenly distributed. Also, the resisting section
is limited to a width of 4.7 ft.
72Step 6 Transverse Bending
- Section through lifters
- From continuous beam analysis, load carried by
bottom two anchors is 7.2 kips, therefore
73Step 7 Secondary Effects
- Check added moment due to sling angle
- Using recessed proprietary lifting anchor
- e 3.5 in
74Step 7 Secondary Effects
- Resisting Section
- Therefore Section is OK
75Prestressed Wall Example
- Given
- Same wallpanel as previousexample
76Prestressed Wall Example
- Problem
- Determine required number of 1/2 in diameter,
270 ksi strands pulled to 28.9 kips to prevent
cracking in window panel. Assume 10 loss of
prestress. - From previous example, tensile stress is 0.431
ksi. The desired level of tensile stress is
or 0.274 ksi
77Solution Steps
- Step 1 Determine additional compressive
Required - Step 2 Determine the number of strands
required based on stress - Step 3 Calculate the number of strands
78Step 1 Additional Compressive
- Compressive stress required
- 0.431 0.274 0.157 ksi
79Step 2 Of Strands Based On Stress
- From previous the max moment/stress occurs at
lifting points (-M). This results in tensile
stresses on the top face.
80Step 3 Number of Strands
- 0.060(no. of strands) 0.019(no. of strands)
0.157 ksi - No. of strands 3.8
- Add four strands to panel (two on each side of
opening)
81Storage
- Wherever possible, a member should be stored on
points of support located at or near those used
for stripping and handling - Where points other than those used for stripping
or handling are used for storage, the storage
condition must be checked
82Storage
- If support is provided at more than two points,
and the design is based on more than two
supports, precautions must be taken so that the
element does not bridge over one of the supports
due to differential support settlement
83Storage
- Warpage in storage may be caused by
- temperature or shrinkage differential between
surfaces - creep
- storage conditions
- Warpage can only be minimized by providing
- Where feasible, the member should be oriented in
the yard so that the sun does not overheat one
side
84Storage
- By superposition, the total instantaneous
deflection, ymax , at the maximum point can be
estimated by
Ic , Ib moment of inertia of uncracked section
in the respective directions for 1 in. width of
panel
85Storage
- This instantaneous deflection should be modified
by a factor to account for the time dependent
effects of creep and shrinkage - ACI 318-02 suggests the total deformation yt, at
any time can be estimated as
86Storage
- ? amplification due to creep and shrinkage as a
function of '? (reinforcement ratio for
non-prestressed compressionreinforcement,As/b?t)
87Transportation
- The method used for transport can affect the
structural design because of size and weight
limitations and the dynamic - Except for long prestressed deck members, most
products are transported on either flatbed or
low-boy trailers - Trailers deform during hauling
- Size and weight limitations vary from one state
to state - Loads are further restricted on secondary roads
- The common payload for standard trailers without
special permits is 20 tons.
88Transportation
- Low-boy trailers permit the height to be
increased to about 10 to 12 ft. - However they have a have a shorter bed length.
- This height may require special routing to avoid
low overpasses and overhead wires
89Transportation
- Erection is simplified when members are
transported in the same orientation they will
have in the structure - For example, single-story wall panels can be
transported on A-frames with the panels upright - A-frames also provide good lateral support and
the desired two points of vertical support
90Transportation
- Longer units can be transported on their sides to
take advantage of the increased stiffness
compared with flat shipment
91Transportation
- In all cases, the panel support locations should
be consistent with the panel design - Panels with large openings sometimes require
strongbacks, braces or ties to keep stresses
within the design values
92Transportation
- For members not symmetrical with respect to the
bending axis, the following expressions can be
used for determining the location of supports to
give equal tensile stresses for positive and
negative bending moments
93Transportation
- For one end cantilevered
- Where
- yb distance from the bending axis to the
bottom fiber - yt distance from the bending axis to the top
fiber
94Transportation
- For two ends cantilevered
-
- Where
- yb distance from the bending axis to the
bottom fiber - yt distance from the bending axis to the top
fiber
95Erection
- Precast concrete members frequently must be
reoriented from the position used to transport to
its final construction position - The analysis for this tripping (rotating)
operation is similar to that used during other
handling stages - In chapter 5 in the PCI handbook, maximum moments
for several commonly used tripping techniques are
illustrated
96Tripping Design Guide
97Erection
- When using two crane lines, the center of gravity
must be between them in order to prevent a sudden
shifting of the load while it is being rotated - To ensure that this is avoided, the stability
condition shown must be met
98Erection
- The capacities of lifting devices must be checked
for the forces imposed during the tripping
operation, since the directions vary - When rotating a panel with two crane lines, the
pick points should be located to prevent the
panel from an uncontrolled roll on the roller
blocks can be done by slightly offsetting the
pick point locations to shift the weight toward
the upper crane line lift points, or by using
chain drags on the rolling block
99Erecting Wall Panels Example
- Given
- The wall panels with openings used on previous
examples - Problem
- Determine appropriate procedures for erecting
the wall panels with openings, panel will be
shipped flat
100Erecting Wall Panels Example
- Assumptions
- Limit stresses to (0.354 ksi).
- Crane has main and auxiliary lines.
- A telescoping man lift is available on site.
- Solution
- Try three-point rotation up using stripping
inserts and rolling block To simplify,
conservatively use solid panel (no openings) to
determine moments.
101Erecting Wall Panels Example
102Erecting Wall Panels Example
- In Horizontal Position
- Therefore, 3 point pick not adequate
103Erecting Wall Panels Example
- Knowing from the stripping analysis that a
four-point pick can be used, the configurations
shown here may be used - However, this rigging may become unstable at some
point during tripping, i.e., continued rotation
without tension in Line A - Therefore, the lower end of the panel must stay
within inches of the ground to maintain control.
104Erecting Wall Panels Example
- Because the previous configuration requires six
rolling blocks and can be cumbersome, the method
shown on the following slide may be an
alternative
105Erecting Wall Panels Example
106Erection Bracing Introduction
- This section deals with the temporary bracing
which may be necessary to maintain structural
stability of a precast structure during
construction - When possible, the final connections should be
used to provide at least part of the erection
bracing, but additional bracing apparatus is
sometimes required to resist all of the temporary
loads
107Erection Bracing Introduction
- These temporary loads may include wind, seismic,
eccentric dead loads including construction
loads, unbalanced conditions due to erection
sequence and incomplete connections Due to the
low probability of design loads occurring during
erection, engineering judgment should be used to
establish a reasonable design load
108Erection Bracing Responsibilities
- Proper planning of the construction process is
essential for efficient and safe erection - Sequence of erection must be established early,
and the effects accounted for in the bracing
analysis and the preparation of shop drawings - The responsibility for the erection of precast
concrete may vary as follows - (see also ACI 318-02 Section 10.3)
109Erection Bracing Responsibilities
- The precast concrete manufacturer supplies the
product erected, either with his own forces, or
by an independent erector - The manufacturer is responsible only for
supplying the product, F.O.B. plant or jobsite - Erection is done either by the general contractor
or by an independent erector under a separate
agreement
110Erection Bracing Responsibilities
- The products are purchased by an independent
erector who has a contract to furnish the
complete precast concrete package. - Responsibility for stability during erection must
be clearly understood. - Design for erection conditions must be in
accordance with all local, state and federal
regulations. It is desirable that this design be
directed or approved by a Professional Engineer
111Erection Bracing Responsibilities
- It is desirable that this design be directed or
approved by a Professional Engineer - Erection drawings define the procedure
- on how to assemble the components into the final
structure - The erection drawings should also address the
stability of the structure during construction
and include temporary connections
112Erection Bracing Responsibilities
- When necessary, special drawings may be required
to include shoring, guying, bracing and specific
erection sequences - It is desirable that this design be directed or
approved by a Professional Engineer - Erection drawings define the procedure
- on how to assemble the components into the final
structure
113Erection Bracing Responsibilities
- The erection drawings should also address the
stability of the structure during construction
and include temporary connections - When necessary, special drawings may be required
to include shoring, guying, bracing and specific
erection sequences
114Erection Bracing Responsibilities
- For large and/or complex projects, a pre-job
conference prior to the preparation of erection
drawings may be warranted, in order to discuss
erection methods and to coordinate with other
trades
115Handling Equipment
- The type of jobsite handling equipment selected
may influence the erection sequence, and hence
affect the temporary bracing requirements - Several types of erection equipment are
available, including truck-mounted and crawler
mobile cranes, hydraulic cranes, tower cranes,
monorail systems, derricks and others - The PCI Recommended Practice for Erection of
Precast Concrete provides more information on the
uses of each.
116Surveying and Layout
- Before products are shipped to the jobsite, a
field check of the project is recommended to
ensure that prior construction is suitable to
accept the precast units - This check should include location, line and
grade of bearing surfaces, notches, blockouts,
anchor bolts, cast-in hardware, and dimensional
deviations - Site conditions such as access ramps, overhead
electrical lines, truck access, etc., should also
be checked
117Surveying and Layout
- Any discrepancies between actual conditions and
those shown on drawings should be addressed
before erection is started - Surveys should be required before, during and
after erection - Before, so that the starting point is clearly
established and any potential difficulties with
the support structure are determined early. - During, to maintain alignment.
- After, to ensure that the products have been
erected within tolerances.
118Loads on Structure
- The publication Design Loads on Structures During
Construction (SEI/ASCE 37-02) provides minimum
design loads, including wind, earthquake and
construction loads and load combinations for
partially completed structures and structures
used during construction - In addition to working stress or strength design
using loads from the above publication, the
designer must consider the effect of temporary
loading on stability and bracing design
119Temporary Loading Examples
- Columns with eccentric loads from other framing
members produce sidesway which means the columns
lean out of plumb - A similar condition can exist whencladding
panels are erected on oneside of a multistory
structure
120Temporary Loading Examples
- Unbalanced loads due to partially complete
erection may result in beam rotation - The erection drawings should address these
Conditions
121Temporary Loading Examples
- Some solutions are
- Install wood wedges between flange of tee and top
of beam - Use connection to columns that prevent rotation
- Erect tees on both sides of beam
- Prop tees to level below
122Temporary Loading Examples
- Rotations and deflections of framing members may
be caused by cladding panels. This may result in
alignment problems and require connections that
allow for alignment adjustment after all panels
are erected
123Temporary Loading Examples
- If construction equipment such as concrete
buggies, man-lifts, etc., are to be used,
information such as wheel loads and spacing
should be conveyed to the designer of the precast
members and the designer of the erection bracing
124Factors of Safety
- Suggested safety factors are shown
Bracing inserts cast into precast members 3
Reusable hardware 5
Lifting inserts 4
125Bracing Equipment and Materials
- For most one-story and two-story high components
that require bracing, steel pipe braces similar
to those shown are used
126Bracing Equipment and Materials
- Proper anchoring of the braces to the precast
members and deadmen must be considered - When the pipe braces are in tension, there may be
significant shear and tension loads applied to
the deadmen - Properly designed deadmen are a requirement for
safe bracing - Cable guys with turnbuckles are normally used for
taller structures
127Bracing Equipment and Materials
- Since wire rope used in cable guys can resist
only tension, they are usually used in
combination with other cable guys in an opposite
direction - Compression struts, which may be the precast
concrete components, are needed to complete truss
action of the bracing system - A number of wire rope types are available
- Note that capacity of these systems is often
governed by the turnbuckle capacity
128General Considerations
- Careful planning of the erection sequence is
important - This plan is usually developed by a coordinated
effort involving the general contractor, precast
erector, precaster production and shipping
departments and a structural engineer - A properly planned erection sequence can reduce
bracing requirements - For example, with wall panel systems a corner can
first be erected so that immediate stability can
be achieved
129General Considerations
- Similar considerations for shear wall structures
can also reduce bracing requirements - All parties should be made aware of the necessity
of closely following erection with the welded
diaphragm connections - This includes the diaphragm to shear wall
connections
130General Considerations
- In order for precast erection to flow smoothly
- The site access and preparation must be ready
- The to-be-erected products must be ready
- Precast shipping must be planned
- The erection equipment must be ready
- Bracing equipment and deadmen must be ready
131Questions?