Title: NERC Blackout Recommendations - A Focus on Transmission Planning -
1NERC Blackout Recommendations- A Focus on
Transmission Planning -
- Brian F. Thumm, P.E.
- Supervisor Transmission Planning
- Entergy Transmission Planning Summit
- July 8, 2004
2On August 14, 2003
- over 50 million people, in 8 states and two
Canadian provinces, were directly affected by a
cascading failure of the transmission grid - a blackout, in which nearly 65,000 MW of load
was interrupted. - On August 15, 2003, President George W. Bush and
Prime-Minister Jean Chrétien established a joint
U.S.-Canada Power System Outage Task Force. - Investigate the causes
- Reduce the possibility of future outages
- NERC commissioned an independent study of the
Blackout.
3NERC Investigation Conclusions
- Entities violated NERC operating policies and
planning standards - Existing process for monitoring and ensuring
compliance with NERC and regional reliability
standards inadequate - Reliability coordinators and control areas
adopted differing interpretations of functions,
responsibilities, authorities, and capabilities - Problems identified in studies of prior blackouts
repeated - Vegetation management
- Operator training
- Tools to help operators properly visualize system
conditions.
4NERC Investigation Conclusions
- Data used to model loads and generators
inaccurate - Lack of verification with actual system data and
field-testing - Planning studies, design assumptions, and
facilities ratings not consistently shared / not
subject to adequate peer review - Available system protection technologies not
consistently applied to optimize the ability to
slow or stop an uncontrolled cascading failure - Communications between system operators were not
effective
5NERC Resolutions
- Receive specific information on all violations of
NERC standards, including the identities of the
parties involved - Take firm actions to improve compliance with NERC
reliability standards - Provide greater transparency to violations of
standards, while respecting the confidential
nature of information and need for a fair and
deliberate due process - Inform and work closely with the Federal Energy
Regulatory Commission and other applicable
federal, state, and provincial regulatory
authorities in the United States, Canada, and
Mexico as needed to ensure public interests are
met with respect to compliance with reliability
standards.
6Blackout Recommendations
- NERC Board of Trustees approved 14
recommendations - near term actions actions that FirstEnergy,
PJM, and MISO must take to remedy deficiencies
before this summer (Recommendation 1) - strategic initiatives actions to strengthen
compliance with existing reliability standards
and to track the implementation of
recommendations from this and other outage
investigations (Recommendations 2-5) - technical initiatives actions to prevent or
mitigate the impact of future cascading
blackouts. (Recommendations 6-14)
NERC Board Recommendations issued prior to
release of NERC Blackout Report
7Recommendation 1 Correct the direct causes of
the August 14, 2003 Blackout
- 1a. The companies implicated in the blackout are
directed to complete specified remedial actions
and certify that these actions have been
completed. - 1b. NERC will assign experts to help these
companies develop plans that adequately address
the issues identified in this report, and for any
other remedial actions for which they require
technical assistance.
Near-Term Action
8Recommendation 2Strengthen NERCs Compliance
Enforcement Program
Entergy Status NERC formed a Compliance Template
Task Force, and revised several compliance
templates. Many of these revision were a
crisping of the existing standards, to make the
wording less ambiguous. The new compliance
templates were disseminated to the industry. The
SERC Region adopted the new templates, and
incorporated them into the current years
Compliance and Enforcement Plan.
- 2a. Each Region will report all violations of
NERC operating policies, planning standards and
regional standards, whether verified or pending
investigation. - 2b. If presented with evidence of a significant
violation, the offending organization must
correct the violation within a specified time. If
an organization is determined to be
non-responsive and presents a reliability risk,
NERC will request assistance of the appropriate
regulatory authorities. - 2c. NERC will review and update all compliance
templates applicable to current NERC reliability
standards. - 2d. NERC and ECAR will evaluate violations of
NERC and regional standards and develop
recommendations to improve compliance with
reliability standards.
Strategic Initiative
9Recommendation 3 Initiate Control Area and
Reliability CoordinatorReliability Readiness
Audits
Entergy Status Entergy made its personnel and
facilities available for a NERC Control Area
Readiness Audit from May 12 - 13, 2004 at the
System Operations Center. A draft report with
recommendations has been issued, and Entergy is
incorporating suggestions made by the Audit Team.
Entergy personnel have also been participating
on the readiness audits of other Control Areas.
- 3a. NERC and the Regions will establish a program
to audit all reliability coordinators and control
areas, with immediate attention given to
addressing the deficiencies identified in the
blackout investigation. These audits shall be
completed within three years, with the 20 highest
priority audits to be completed by June 30, 2004. - 3b. NERC will establish a set of baseline audit
criteria that will include evaluation of
reliability plans, procedures, processes, tools,
personnel qualifications, and training. - 3c. The Regions, with input from NERC, will audit
each control areas and reliability coordinators
readiness to meet these audit criteria.
Strategic Initiative
10Recommendation 4Evaluate Vegetation Management
Procedures and Results
Entergy Status September, 2003 Entergy staff
drafted a Transmission Vegetation Work Management
Process. The new process is in the review
stage. June, 2004 Entergy submitted a
Transmission Vegetation Management Report to
FERC, NERC, SERC, States. Another report is being
prepared in response to an APSC order for all
Transmission and Distribution lines and Rights of
Way in Arkansas (due July 16, 2004). July,
2004 Entergy will begin monthly reporting of
vegetation-related outages to SERC. Entergy has
actively participated in the development of a new
NERC vegetation standard through comments on the
SAR individually and through EEI and has
nominated a volunteer to serve on the NERC
standard drafting team.
- 4a. NERC and the Regions will initiate a program
to report all transmission line trips resulting
from vegetation contact. - 4b. Each transmission operator will submit an
annual report of all vegetation-related high
voltage line trips to its Region. - 4c. Each transmission owner shall make its
vegetation management procedures and
documentation of work completed available for
review and verification.
Strategic Initiative
11Recommendation 5Establish a Program to
TrackImplementation of Recommendations
Entergy Status Entergy participates in SERC at
the Regional level on committees and
subcommittees which are developing the types of
programmatic controls required by Recommendations
5a and 5b. Compliance Oversight
Group Compliance Review Steering Committee
(EC) Compliance Subcommittee (OC)
- 5a. NERC and the Regions will establish a program
to document the completion of recommendations
resulting from the August 14 blackout
investigation and investigations of other
historical outages, reports of violations of
reliability standards, results of compliance
audits, and lessons learned from system
disturbances. - 5b. NERC will establish a program to evaluate and
report on bulk electric system reliability
performance.
Strategic Initiative
12Recommendation 6 Improve Operator and
Reliability Coordinator Training
- 6. All reliability coordinators, control areas,
and transmission operators shall provide at least
five days per year of training and drills in
system emergencies for each staff person with
responsibility for the real-time operation or
reliability monitoring of the bulk electric
system.
Technical Initiative
13Recommendation 7 Evaluate Reactive Power and
Voltage Control Practices
Entergy Status The Entergy Transmission
Planning Technical Studies group is scoping
studies on reactive power planning and voltage
stability.
- 7a. NERC will reevaluate the effectiveness of the
existing reactive power and voltage control
standards and how they are being implemented in
practice, and develop recommendations to ensure
voltage control and stability issues are
adequately addressed. - 7b. ECAR will review its reactive power and
voltage criteria and procedures and verify that
its criteria and procedures are being fully
implemented in regional and member studies and
operations.
Technical Initiative
14Recommendation 8 Improve System Protection to
Slow or Limitthe Spread of Future Cascading
Outages
Entergy Status As of the week ending June 25,
over one-third of the Zone 3 settings have been
reviewed and tested. This review is expected to
be completed by the second week of
August. Entergy identified two areas in its
system that have the potential for developing
voltage stability problems and has implemented
undervoltage load shed programs to address these
extreme contingencies.
- 8a. All transmission owners will evaluate the
zone 3 relay settings on all transmission lines
operating at 230 kV and above for the purpose of
verifying that each zone 3 relay is not set to
trip on load under extreme emergency conditions.
NERC will review any proposed exceptions to
ensure they do not increase the risk of widening
a cascading failure of the power system. - 8b. Each Region will evaluate the feasibility and
benefits of installing under-voltage load
shedding capability in load centers that could
become unstable as a result of being deficient in
reactive power following multiple-contingency
events. The Regions are to promote the
installation of under-voltage load shedding
capabilities within critical areas that would
help to prevent an uncontrolled cascade of the
power system. - 8c. Evaluate Planning Standard III System
Protection and Control and propose revisions to
adequately address the issue of slowing or
limiting the propagation of a cascading failure.
Evaluate the lessons from August 14 regarding
relay protection design and application and offer
additional recommendations for improvement.
Technical Initiative
15Recommendation 9 Clarify Reliability Coordinator
and Control Area Functions, Responsibilities,
Capabilities
- 9. The NERC Operating Committee shall perform the
following - More clearly define the characteristics and
capabilities necessary to enable prompt
recognition and effective response to system
emergencies. - Ensure the accurate and timely sharing of outage
data necessary to support real-time operating
tools such as state estimators, real-time
contingency analysis, and other system monitoring
tools. - Establish the consistent application of effective
communications protocols, particularly during
emergencies. - The operating policies must be clarified to
remove ambiguities concerning the
responsibilities and actions appropriate to
reliability coordinators and control areas.
Technical Initiative
16Recommendation 10 Establish Guidelines for
Real-Time Operating Tools
- 10. Evaluate the real-time operating tools
necessary for reliable operation and reliability
coordination, including backup capabilities and
report both minimum acceptable capabilities for
critical reliability functions and a guide of
best practices.
Technical Initiative
17Recommendation 11 Evaluate Lessons Learned
During System Restoration
- 11a. Evaluate the black start and system
restoration performance following the outage of
August 14 and develop recommendations for
improvement. - 11b. All Regions will reevaluate their procedures
and plans to assure an effective blackstart and
restoration capability within their region.
Entergy Status Entergy is represented on the
SERC Operations Planning Subcommittee and
participated in the April 13, SERC OPS annual
review of blackstart plans. An effort is underway
to determine the status of synchronization
capability between the companies in SERC. The OC
OPS committee expects to present a new SERC
Blackstart Plan Appendix for approval at an OC
meeting listing availability of control area to
control area synchronization points in the near
future. Internally, Entergy's blackstart team
performs a thorough annual review of all aspects
of the plans for each Transmission Operation
Center, and, on a seasonal basis updates and
refreshes information such as emergency and
operations contacts, document owners, team
members, feeder priority lists, testing schedules
and synchronization.
Technical Initiative
18Recommendation 12 Install Additional
Time-SynchronizedRecording Devices as Needed
Entergy Status Entergy is in its third year of
a six-year program of modernizing and replacing
DFRs with new technology units that will
synchronize using satellite clocks. Presently, 43
of Entergys 70 DFRs are synchronized. Of the
twenty-seven DFRs that are not time synchronized,
ten are installed at nine substations that tie to
other companies. Entergy is implementing new
technologies to facilitate a good understanding
of the dynamic behavior of eastern
interconnection, such as the EIPP and the the
WAMS programs. The expected completion date is
Fall 2004 eleven total installations are planned
by October 2004.
- 12a. Define regional criteria for the application
of synchronized recording devices in power plants
and substations and facilitate the installation
of the devices to allow accurate recording of
system disturbances and to facilitate
benchmarking of simulation studies. - 12b. Facility owners will upgrade existing
dynamic recorders to include GPS time
synchronization and, as necessary, install
additional dynamic recorders.
Technical Initiative
19Recommendation 13 Reevaluate System Design,
Planning and Operating Criteria
Entergy Status Entergy participates at in SERC
at the Regional level on committees and
subcommittees which are developing the follow-up
reports on blackout lessons learned. Entergy
will continue to participate at the Regional
level to have input into the process. Reliability
Review Subcommittee Operations Plannng
Subcommittee Security Coordinators Subcommittee
- 13a. Evaluate operations planning and operating
criteria and recommend revisions. - 13b. ECAR will reevaluate its planning and study
procedures and practices to ensure they are in
compliance with NERC standards, ECAR Document
No.1, and other relevant criteria and that ECAR
and its members studies are being implemented as
required. - 13c.Reevaluate the criteria, methods and
practices used for system design, planning and
analysis. This review shall include an evaluation
of transmission facility ratings methods and
practices, and the sharing of consistent ratings
information.
Technical Initiative
20Recommendation 14 Improve System Modeling Data
and Data Exchange Practices
Entergy Status The SERC Region has commissioned
a Model Validation Task Force to implement
Recommendation 14. Entergy will be represented
on the task force by members of the VAST and VST
study groups. Entergy also participates in the
SERC Regional modeling efforts by remaining
active in the VST, which is responsible for the
development of the base case models that will
ultimately be validated.
- 14. Establish and implement criteria and
procedures for validating data used in power flow
models and dynamic simulations by benchmarking
model data with actual system performance.
Validated modeling data shall be exchanged on an
inter-regional basis to support reliable system
planning and operation.
Technical Initiative
21Questions