NERC Blackout Recommendations - A Focus on Transmission Planning -

presentation player overlay
About This Presentation
Transcript and Presenter's Notes

Title: NERC Blackout Recommendations - A Focus on Transmission Planning -


1
NERC Blackout Recommendations- A Focus on
Transmission Planning -
  • Brian F. Thumm, P.E.
  • Supervisor Transmission Planning
  • Entergy Transmission Planning Summit
  • July 8, 2004

2
On August 14, 2003
  • over 50 million people, in 8 states and two
    Canadian provinces, were directly affected by a
    cascading failure of the transmission grid
  • a blackout, in which nearly 65,000 MW of load
    was interrupted.
  • On August 15, 2003, President George W. Bush and
    Prime-Minister Jean Chrétien established a joint
    U.S.-Canada Power System Outage Task Force.
  • Investigate the causes
  • Reduce the possibility of future outages
  • NERC commissioned an independent study of the
    Blackout.

3
NERC Investigation Conclusions
  • Entities violated NERC operating policies and
    planning standards
  • Existing process for monitoring and ensuring
    compliance with NERC and regional reliability
    standards inadequate
  • Reliability coordinators and control areas
    adopted differing interpretations of functions,
    responsibilities, authorities, and capabilities
  • Problems identified in studies of prior blackouts
    repeated
  • Vegetation management
  • Operator training
  • Tools to help operators properly visualize system
    conditions.

4
NERC Investigation Conclusions
  • Data used to model loads and generators
    inaccurate
  • Lack of verification with actual system data and
    field-testing
  • Planning studies, design assumptions, and
    facilities ratings not consistently shared / not
    subject to adequate peer review
  • Available system protection technologies not
    consistently applied to optimize the ability to
    slow or stop an uncontrolled cascading failure
  • Communications between system operators were not
    effective

5
NERC Resolutions
  • Receive specific information on all violations of
    NERC standards, including the identities of the
    parties involved
  • Take firm actions to improve compliance with NERC
    reliability standards
  • Provide greater transparency to violations of
    standards, while respecting the confidential
    nature of information and need for a fair and
    deliberate due process
  • Inform and work closely with the Federal Energy
    Regulatory Commission and other applicable
    federal, state, and provincial regulatory
    authorities in the United States, Canada, and
    Mexico as needed to ensure public interests are
    met with respect to compliance with reliability
    standards.

6
Blackout Recommendations
  • NERC Board of Trustees approved 14
    recommendations
  • near term actions actions that FirstEnergy,
    PJM, and MISO must take to remedy deficiencies
    before this summer (Recommendation 1)
  • strategic initiatives actions to strengthen
    compliance with existing reliability standards
    and to track the implementation of
    recommendations from this and other outage
    investigations (Recommendations 2-5)
  • technical initiatives actions to prevent or
    mitigate the impact of future cascading
    blackouts. (Recommendations 6-14)

NERC Board Recommendations issued prior to
release of NERC Blackout Report
7
Recommendation 1 Correct the direct causes of
the August 14, 2003 Blackout
  • 1a. The companies implicated in the blackout are
    directed to complete specified remedial actions
    and certify that these actions have been
    completed.
  • 1b. NERC will assign experts to help these
    companies develop plans that adequately address
    the issues identified in this report, and for any
    other remedial actions for which they require
    technical assistance.

Near-Term Action
8
Recommendation 2Strengthen NERCs Compliance
Enforcement Program
Entergy Status NERC formed a Compliance Template
Task Force, and revised several compliance
templates. Many of these revision were a
crisping of the existing standards, to make the
wording less ambiguous. The new compliance
templates were disseminated to the industry. The
SERC Region adopted the new templates, and
incorporated them into the current years
Compliance and Enforcement Plan.
  • 2a. Each Region will report all violations of
    NERC operating policies, planning standards and
    regional standards, whether verified or pending
    investigation.
  • 2b. If presented with evidence of a significant
    violation, the offending organization must
    correct the violation within a specified time. If
    an organization is determined to be
    non-responsive and presents a reliability risk,
    NERC will request assistance of the appropriate
    regulatory authorities.
  • 2c. NERC will review and update all compliance
    templates applicable to current NERC reliability
    standards.
  • 2d. NERC and ECAR will evaluate violations of
    NERC and regional standards and develop
    recommendations to improve compliance with
    reliability standards.

Strategic Initiative
9
Recommendation 3 Initiate Control Area and
Reliability CoordinatorReliability Readiness
Audits
Entergy Status Entergy made its personnel and
facilities available for a NERC Control Area
Readiness Audit from May 12 - 13, 2004 at the
System Operations Center. A draft report with
recommendations has been issued, and Entergy is
incorporating suggestions made by the Audit Team.
Entergy personnel have also been participating
on the readiness audits of other Control Areas.
  • 3a. NERC and the Regions will establish a program
    to audit all reliability coordinators and control
    areas, with immediate attention given to
    addressing the deficiencies identified in the
    blackout investigation. These audits shall be
    completed within three years, with the 20 highest
    priority audits to be completed by June 30, 2004.
  • 3b. NERC will establish a set of baseline audit
    criteria that will include evaluation of
    reliability plans, procedures, processes, tools,
    personnel qualifications, and training.
  • 3c. The Regions, with input from NERC, will audit
    each control areas and reliability coordinators
    readiness to meet these audit criteria.

Strategic Initiative
10
Recommendation 4Evaluate Vegetation Management
Procedures and Results
Entergy Status September, 2003 Entergy staff
drafted a Transmission Vegetation Work Management
Process. The new process is in the review
stage. June, 2004 Entergy submitted a
Transmission Vegetation Management Report to
FERC, NERC, SERC, States. Another report is being
prepared in response to an APSC order for all
Transmission and Distribution lines and Rights of
Way in Arkansas (due July 16, 2004). July,
2004 Entergy will begin monthly reporting of
vegetation-related outages to SERC. Entergy has
actively participated in the development of a new
NERC vegetation standard through comments on the
SAR individually and through EEI and has
nominated a volunteer to serve on the NERC
standard drafting team.
  • 4a. NERC and the Regions will initiate a program
    to report all transmission line trips resulting
    from vegetation contact.
  • 4b. Each transmission operator will submit an
    annual report of all vegetation-related high
    voltage line trips to its Region.
  • 4c. Each transmission owner shall make its
    vegetation management procedures and
    documentation of work completed available for
    review and verification.

Strategic Initiative
11
Recommendation 5Establish a Program to
TrackImplementation of Recommendations
Entergy Status Entergy participates in SERC at
the Regional level on committees and
subcommittees which are developing the types of
programmatic controls required by Recommendations
5a and 5b. Compliance Oversight
Group Compliance Review Steering Committee
(EC) Compliance Subcommittee (OC)
  • 5a. NERC and the Regions will establish a program
    to document the completion of recommendations
    resulting from the August 14 blackout
    investigation and investigations of other
    historical outages, reports of violations of
    reliability standards, results of compliance
    audits, and lessons learned from system
    disturbances.
  • 5b. NERC will establish a program to evaluate and
    report on bulk electric system reliability
    performance.

Strategic Initiative
12
Recommendation 6 Improve Operator and
Reliability Coordinator Training
  • 6. All reliability coordinators, control areas,
    and transmission operators shall provide at least
    five days per year of training and drills in
    system emergencies for each staff person with
    responsibility for the real-time operation or
    reliability monitoring of the bulk electric
    system.

Technical Initiative
13
Recommendation 7 Evaluate Reactive Power and
Voltage Control Practices
Entergy Status The Entergy Transmission
Planning Technical Studies group is scoping
studies on reactive power planning and voltage
stability.
  • 7a. NERC will reevaluate the effectiveness of the
    existing reactive power and voltage control
    standards and how they are being implemented in
    practice, and develop recommendations to ensure
    voltage control and stability issues are
    adequately addressed.
  • 7b. ECAR will review its reactive power and
    voltage criteria and procedures and verify that
    its criteria and procedures are being fully
    implemented in regional and member studies and
    operations.

Technical Initiative
14
Recommendation 8 Improve System Protection to
Slow or Limitthe Spread of Future Cascading
Outages
Entergy Status As of the week ending June 25,
over one-third of the Zone 3 settings have been
reviewed and tested. This review is expected to
be completed by the second week of
August. Entergy identified two areas in its
system that have the potential for developing
voltage stability problems and has implemented
undervoltage load shed programs to address these
extreme contingencies.
  • 8a. All transmission owners will evaluate the
    zone 3 relay settings on all transmission lines
    operating at 230 kV and above for the purpose of
    verifying that each zone 3 relay is not set to
    trip on load under extreme emergency conditions.
    NERC will review any proposed exceptions to
    ensure they do not increase the risk of widening
    a cascading failure of the power system.
  • 8b. Each Region will evaluate the feasibility and
    benefits of installing under-voltage load
    shedding capability in load centers that could
    become unstable as a result of being deficient in
    reactive power following multiple-contingency
    events. The Regions are to promote the
    installation of under-voltage load shedding
    capabilities within critical areas that would
    help to prevent an uncontrolled cascade of the
    power system.
  • 8c. Evaluate Planning Standard III System
    Protection and Control and propose revisions to
    adequately address the issue of slowing or
    limiting the propagation of a cascading failure.
    Evaluate the lessons from August 14 regarding
    relay protection design and application and offer
    additional recommendations for improvement.

Technical Initiative
15
Recommendation 9 Clarify Reliability Coordinator
and Control Area Functions, Responsibilities,
Capabilities
  • 9. The NERC Operating Committee shall perform the
    following
  • More clearly define the characteristics and
    capabilities necessary to enable prompt
    recognition and effective response to system
    emergencies.
  • Ensure the accurate and timely sharing of outage
    data necessary to support real-time operating
    tools such as state estimators, real-time
    contingency analysis, and other system monitoring
    tools.
  • Establish the consistent application of effective
    communications protocols, particularly during
    emergencies.
  • The operating policies must be clarified to
    remove ambiguities concerning the
    responsibilities and actions appropriate to
    reliability coordinators and control areas.

Technical Initiative
16
Recommendation 10 Establish Guidelines for
Real-Time Operating Tools
  • 10. Evaluate the real-time operating tools
    necessary for reliable operation and reliability
    coordination, including backup capabilities and
    report both minimum acceptable capabilities for
    critical reliability functions and a guide of
    best practices.

Technical Initiative
17
Recommendation 11 Evaluate Lessons Learned
During System Restoration
  • 11a. Evaluate the black start and system
    restoration performance following the outage of
    August 14 and develop recommendations for
    improvement.
  • 11b. All Regions will reevaluate their procedures
    and plans to assure an effective blackstart and
    restoration capability within their region.

Entergy Status Entergy is represented on the
SERC Operations Planning Subcommittee and
participated in the April 13, SERC OPS annual
review of blackstart plans. An effort is underway
to determine the status of synchronization
capability between the companies in SERC. The OC
OPS committee expects to present a new SERC
Blackstart Plan Appendix for approval at an OC
meeting listing availability of control area to
control area synchronization points in the near
future. Internally, Entergy's blackstart team
performs a thorough annual review of all aspects
of the plans for each Transmission Operation
Center, and, on a seasonal basis updates and
refreshes information such as emergency and
operations contacts, document owners, team
members, feeder priority lists, testing schedules
and synchronization.
Technical Initiative
18
Recommendation 12 Install Additional
Time-SynchronizedRecording Devices as Needed
Entergy Status Entergy is in its third year of
a six-year program of modernizing and replacing
DFRs with new technology units that will
synchronize using satellite clocks. Presently, 43
of Entergys 70 DFRs are synchronized. Of the
twenty-seven DFRs that are not time synchronized,
ten are installed at nine substations that tie to
other companies. Entergy is implementing new
technologies to facilitate a good understanding
of the dynamic behavior of eastern
interconnection, such as the EIPP and the the
WAMS programs. The expected completion date is
Fall 2004 eleven total installations are planned
by October 2004.
  • 12a. Define regional criteria for the application
    of synchronized recording devices in power plants
    and substations and facilitate the installation
    of the devices to allow accurate recording of
    system disturbances and to facilitate
    benchmarking of simulation studies.
  • 12b. Facility owners will upgrade existing
    dynamic recorders to include GPS time
    synchronization and, as necessary, install
    additional dynamic recorders.

Technical Initiative
19
Recommendation 13 Reevaluate System Design,
Planning and Operating Criteria
Entergy Status Entergy participates at in SERC
at the Regional level on committees and
subcommittees which are developing the follow-up
reports on blackout lessons learned. Entergy
will continue to participate at the Regional
level to have input into the process. Reliability
Review Subcommittee Operations Plannng
Subcommittee Security Coordinators Subcommittee
  • 13a. Evaluate operations planning and operating
    criteria and recommend revisions.
  • 13b. ECAR will reevaluate its planning and study
    procedures and practices to ensure they are in
    compliance with NERC standards, ECAR Document
    No.1, and other relevant criteria and that ECAR
    and its members studies are being implemented as
    required.
  • 13c.Reevaluate the criteria, methods and
    practices used for system design, planning and
    analysis. This review shall include an evaluation
    of transmission facility ratings methods and
    practices, and the sharing of consistent ratings
    information.

Technical Initiative
20
Recommendation 14 Improve System Modeling Data
and Data Exchange Practices
Entergy Status The SERC Region has commissioned
a Model Validation Task Force to implement
Recommendation 14. Entergy will be represented
on the task force by members of the VAST and VST
study groups. Entergy also participates in the
SERC Regional modeling efforts by remaining
active in the VST, which is responsible for the
development of the base case models that will
ultimately be validated.
  • 14. Establish and implement criteria and
    procedures for validating data used in power flow
    models and dynamic simulations by benchmarking
    model data with actual system performance.
    Validated modeling data shall be exchanged on an
    inter-regional basis to support reliable system
    planning and operation.

Technical Initiative
21
Questions
Write a Comment
User Comments (0)
About PowerShow.com