Title: Facilities Update Site Improvements


1
Facilities UpdateSite Improvements
  • Encinitas Union School District
  • September 5, 2006

2
Capri
  • New HVAC system
  • New campus entrance w/ student drop-off / pick-up
  • Playground asphalt replacement and regrade.
  • Moved in one relocatable to house Media Center
    during construction
  • Next steps
  • Landscaping and irrigation at front of site
  • New marquee
  • Parking area
  • Media Center
  • Outdoor patio
  • Elevator
  • New stucco and painting

3
El Camino Creek
  • Completed three cottage-style classrooms
  • Next steps
  • Sandblast and repaint stairways
  • Replant slopes

4
Flora Vista
  • Preschool addition
  • Added two offices and one classroom
  • Replaced carpet with VCT
  • Replaced existing toilets
  • Remodeled main office
  • Remodeled principals office
  • Replaced school roof
  • Replaced lunch shade shelter
  • Sandblast and repaint windows
  • Next steps
  • Remodel existing storage
  • Add tack board to interior hallways
  • Replace asphalt (06-07)
  • Paint exterior of school (06-07)

5
La Costa Heights
  • Completing two new bathrooms
  • Added relocatable classroom
  • Next steps
  • Replace old playground equipment
  • Replace safety surfacing on playgrounds
  • Convert relocatables at back of site to
    cottage-style classrooms
  • Add modular cottage at front of site

6
Mission Estancia
  • Remodeled new computer room
  • Next steps
  • Replace tiles on outside walls
  • Move relocatables to south side of site and
    convert to cottage-style classrooms
  • Replace school roof (solar?) (06-07)

7
Ocean Knoll
  • Remodel auditorium
  • Remodel office entry
  • Conversion of HVAC plant to storage room
  • New ball wall
  • Playground asphalt recycled and replaced
  • Next steps
  • Add school sign
  • Asphalt striping

8
Ocean Knoll
9
Olivenhain Pioneer
  • Added nine cottage-style classrooms on east side
    of site
  • Added three bathrooms
  • Replaced carpet, tile, and painted throughout
    site
  • Next steps
  • Complete sink in existing art room
  • Replace school roof (solar?) (06-07)
  • Replace HVAC (07-08)

10
Olivenhain Pioneer
11
Park Dale Lane
  • Office renovation
  • Next steps
  • Add modular cottage at east side of site

12
Paul Ecke Central
  • Renovate teachers lounge into kitchen and
    workroom
  • New computer lab
  • Replaced old portable classroom w/ cottage-style
    classroom
  • Next steps
  • Remodel auditorium
  • Add three classrooms adjacent to auditorium
  • Improve perimeter along Vulcan
  • Add student drop-off/pick-up on Vulcan
  • Renovate parking on west side of site

13
Next Steps
  • Adoption of standardized classroom
  • Renovate playgrounds at all sites
  • Review facility priorities from 2004
  • Site visits to determine current and future
    facility needs and priorities