Title: What is Design Build?
1What is Design Build?
- Design-Build is a method of project delivery in
which one entity (the design-builder) forges a
single contract with the project owner to provide
both architectural, engineering design services
and construction services. - Source Design-Build Institute of America
2WELCOME TO DESIGN BUILD
3Design Build Panel
- Wayne Larsen Parsons Brinkerhoff
- Tom Loo Alberta Transportation
- Karen Stein Utah Department of Trans.
- ROUND TABLE DISCUSSION
4U.S. R/W Perspective
-
- Ms. Karen Stein, SR/WA, R/W-RAC
- Deputy Director for the Utah Department of
Transportation
5Traditional Design Bid Build
Plan UDOT Staff or Consultant
Clear ROW UDOT Staff or Consultant
Design UDOT Staff or Consultant
Build UDOT Staff or Consultant
6Design Build
Plan 30 Design UDOT Staff or Consultant
Design Design Build Consultant Team
Clear ROW Design Build Consultant Team
Build Design Build Consultant Team
7When is Design Build a good idea?
- Projects where in-house resources are not
sufficient - Projects that can benefit from fast-tracking
- Projects with a high need for innovation
- Projects on an Interstate
- Risks known and transferable
8With Design Bid Build(the traditional model)
- In DBB projects there is a balance between
- Scope
- Schedule
- Budget
9With Design Build
- It is all about the Schedule!
10Design Build from the U.S. Agencys perspective
- Benefits
- Identify and manage risk
- Reduce acquisition time line
- Encourage negotiated settlements
- Encourage design to mitigate damages
- Encourages use of effective scheduling methods
and software - Expands DOT resources for Acquisition/Relocation
Process - DB incentives help promote implementation of an
effective Public involvement plan -
11Design Build from the ROW perspective
- Risks
- Increased overhead and direct acquisition and
relocation costs - Potential for coercive acquisition methods
- Increased number of condemnation cases admin
settlements - Potential for precedent setting practices which
are out of compliance with URA and or UDOT ROW
Policies and Procedures. - Increased time for each ROW task due to increased
hand offs between DB and Central DOT ROW - Delay Claims if DOT fails to meet schedule
requirements
12Issues for ROW with Design Build
- The Selection Process
- Right of Way section of RFP must be sufficiently
and accurately detailed - Selection Team must include a ROW Staff person
- ROW component of the DB Proposals may not be
sufficient to affect the overall selection of the
DB team.
13Design Build from the Engineering point of view
- Benefits
- Early known cost
- Reduce delivery time
- Reduce design errors
- Improve Constructability
- Identify and manage risk
- Encourage innovation
- Less detail required in design
- Expands UDOT resources
- Risks
- Proposal costs
- Innovation limited to contractor experience
- Third Party Delay
14Canadian Perspective
- Mr. Tom Loo, P. E.
- Executive Director of Major Capital Projects for
Alberta Transportation
15Ring Roads
- The Premier and the Government of Alberta have
made a commitment to complete the ring roads in
a free flow condition around the cities of
Edmonton and Calgary - The majority of the land required for these major
freeways were purchased by the province in the
1970s
16Current Status of Ring Roads
- Segments of Anthony Henday Drive in Edmonton and
Stoney Trail in Calgary are currently open to
traffic - Planning, design, and construction is continuing
on all remaining segments of the ring roads
17Edmonton Ring Road
18Calgary Ring Road
19Project Delivery Mechanisms
- Traditional Design-Bid-Build
- Projects up to approximately 100 million
- Majority of projects delivered using this method
- Design/Build
- Projects approximately 100 to 300 million
- One project being delivered using this method
- Public Private Partnerships (P3) under a
Design/Build/Finance/Operate (DBFO) agreement - Projects approximately over 300 million
- Two projects designed, constructed and currently
in operations - Two other projects being delivered using this
method
20Anthony Henday Drive Stony Plain Road
Interchange
- Being delivered through Alberta Transportations
first design/build contract - Includes 50 lane km of new and rehabilitated
roadway and seven bridge structures which will
provide for a free flow systems interchange
21Anthony Henday Drive Stony Plain Road
Interchange
22Anthony Henday Drive Stony Plain Road
Interchange
- Design/Build Procurement commenced in summer 2008
- Issued RFQ in August 2008
- Short-listed to three proponents
- Issued RFP September 2008
- Executed agreement with preferred proponent
February 2009 - Contract price of 168.6 million
- Construction commenced April 2009
- Traffic availability scheduled for October 15,
2011
23Design/Build Advantages
- Cost certainty
- Schedule certainty
- Compressed schedule (fast-track design and
construction) - Clearly defined project scope
- Risk transfer
- Opportunity for innovation
24Design/Build Disadvantages
- Clearly defined project scope
- Design must be further advanced for accurate
pricing - Unknowns removed (geotechnical, etc.)
- Regulatory issues resolved in advance (risk not
transferred) - Less control by owner during
- design and construction
25Design/Build Disadvantages
- Clearly defined project scope
- Design must be further advanced for accurate
pricing - Unknowns removed (geotechnical, etc.)
- Regulatory issues resolved in advance (risk not
transferred) - Less control by owner during design
- and construction
26Design/Build Disadvantages
- Potential for quality issues
- Costly procurement process
- Not ideal for projects with
- Geotechnical unknowns
- Environmental issues
- Utility issues
- Any 3rd party which may add risk to contractor
27Design/Build Procurement Process
- Detailed Technical Requirements
- Pass/Fail criteria for technical submissions by
proponents - Allow multiple runs at the gate to achieve pass
within a set time period - Must be compliant technical proposal (pass) to
proceed to price submission - Lowest price wins
28Quality Management
- Quality is very important to the owner
- Quality Manager required and evaluated as part of
RFQ - Quality Management System must be ISO compliant
- Contractor responsible for overall Quality
Control and Quality Assurance - Owner has maintained rigorous quality management
oversight
29Elements of Design/Build
- Utility cost sharing threshold
- Progress payments during construction
- 10 holdback
- Late completion penalty of 10,000 per day
- 2-year warranty
30Land Acquisition
- Owner best party to manage the risk of property
acquisition - In general, risks not properly allocated or
mitigated will ultimately be transferred back to
the owner through the bid price - Ideally, all required land should be acquired
prior to the start of the procurement process - Majority of required land purchased by the
provincein the 1970s
31Land Acquisition
- Some slivers or small parcels required for design
and construction - Private contractors do not have the ability to
expropriate property if required - Property acquisition can be a lengthy process and
negate the advanced schedule benefits of
Design/Build
32Land Acquisition
- Where the required sliver or parcel of land was
not obtained prior to procurement, Design/Build
agreement specifies when the required land will
be available - Provincial staff continued to work during
procurement period and early construction period
to secure required land - Contractor required to mitigate impacts of not
having required land at start of construction - Process has worked reasonably well
33Current Status of Design/Build Project
- Ahead of schedule
- On budget
- Good quality
- Good working relationship with contractor
34DB Consultant Perspective
-
- C. Wayne Larsen, SR/WA, R/W-AC
35FORBES RatesBest Worst Cities for Commuters
- Forbes ranked Salt Lake City the best city in the
country for commuters (FEB 16, 2010) - "One of the reasons we are ranked so high by
Forbes is because we have such a comprehensive
transportation system." - "One of the biggest, most aggressive, and most
successful rail expansion program in the country
right now,"
36UTA FRONTLINES 2015 PROGRAM
- FRONTRUNNER CRS
- MID-JORDAN LRT
- DRAPER LRT
- WEST VALLEY LRT
- AIRPORT LRT
37UTA FRONTLINES 2015 PROGRAM
- 70 Miles in 7 Years (2015)
- Using a Design Build team approach
- 70 Miles in 5 Years (2013)
38The Most Important Lessons Learned by UDOT ROW
- The RFP is your controlling document
- Write and re-write the RFP to make sure all
expectations are clearly written - A commitment to oversight is required by the DOT
- Dont underestimate the amount of time and
number of resources this will require - Hold the DB accountable, be assured that the DB
will hold the DOT accountable - Manage Risk wisely and make the DB retain the
responsibility of clearing ROW after the NTP date
as stipulated in the RFP
39Additional Lessons Learned
- Monitor the QC/QA process to make sure it is
adequate and effective - Have a strong Public Information component of the
DB team - Make sure the DB carefully plans and conducts
effective Community and Neighborhood focus
meetings - Identify and work with 3rd party stakeholders
early in the process - Include utility, outdoor advertizing signs, rail
roads, local agency and or 3rd party agreements
in the environmental document if possible. - If, not in the environmental agreement, develop
utility, local agency and or 3rd party agreements
as early as possible
40DESIGN BUILD
41Thank you
- kstein_at_utah.gov (801) 965-4057
- Tom.Loo_at_gov.ab.ca (780) 913-0330
- Larsen_at_pbworld.com (801) 550-9259
42History of DB with ROW in Utah
- I-15 (prior to 2002 Olympics) Reconstruction
- UDOT cleared ROW for Residential properties, DB
team cleared ROW for Non-Residential properties - Under traditional DBB- 8 years estimated
- time to complete the construction
- Actual under DB completed in 4 years
43Current DB ROW Projects
- Pioneer Crossing (I-15 Interchange) (Region 3)
- I-15 Core (Region 3)
- SR-68 Bangerter to Saratoga Springs (Region 3)
- 114th South (I-15 Interchange) (Region 2)
- Fort Lane Interchange (I-15 in Region 1)
- 6200 South CFI (SR-68) (Region 2)
-
- See UDOTs website for interactive video of these
highly innovative projects www.udot.utah.gov
(Under public/innovations)
44Projects with specific innovative components
- Pioneer Crossing -- Diverging Diamond Interchange
(DDI) and Accelerated Bridge Construction (ABC) - S.R. 92 -- Commuter Lanes
- Express Lanes--I-15 Core
- Continuous Flow Interchange (CFI) SR-68
- Details about each project can be found on the
Udot website under public info/innovations and or
under Projects. - Home page is www.udot.utah.gov
- Video overview of UDOTs program with emphasis on
innovations is available on this website
45RFP must describe the specific Scope of Work
- Prepare list of parcels with high priority
- Determine clear scope of work for the ROW Design
- Prioritize 3rd party entities and all utilities
- Provide the DB with a list of properties already
acquired or which will be acquired by the DOT - Determine whether the DB will be responsible for
the Closings and if so, will they provide Title
Insurance - Detail who will have signature authority for
every step of the process - Just Compensation
- Pre-Approval of Admin. Settlement amounts
- Contracts and or Settlement Authority for
Mediations, Arbitrations and Condemnations. - Relocation Claims
- Develop a negotiated Flow Chart with the DB
- Meet and discuss status on a weekly basis
- Track all hand offs to and from the agency (using
a shared system if available) IE using our in
house EPM system, or the DBs tracking system.
Agree on the method to be used to track the
process, status and deliverable
46Best Practice RE Scope of Work
- Based on UDOT DB Projects
- DOT should begin early acquisition process (total
acquisitions complex acquisitions or 3rd party
involvement)) as soon as possible once the
project has Environmental Clearance - Purchase based on 30 design for the widest
estimated footprint to include all potential
easements - Transfer the responsibility of clearing ROW and
the Risk as of the Notice to Proceed (NTP) Date. -
47Appraisal/Valuation Issues
- Consistency in methodology and use of comparable
sales data - Out of state appraisers and review appraisers are
not recommended, out of necessity out of state
reviewer may be ok but not ideal. - Single review appraiser or at least one reviewer
per identified segment of the project for
consistency purposes
48Acquisition Issues
- Monitor to ensure that policies and RFP are
followed - Require good faith negotiations
- Do not allow DB to use Right of Entry (ROE)
unless other means to acquire have been exhausted - Use Right of Occupancy Agreement (ROO)
responsibly and only if owner is willing to
negotiate and or mediate differences of value - If ROO is obtained DB must follow up to acquire
or condemn based on negotiated time line
(negotiated with property owner) with
authorization of the DOT - Condemnation Resolutions prepared timely
- Condemnations may only be withdrawn by the
Director of ROW
49Relocation Issues
- Ensure that proper notices are prepared and
issued - Ensure that advisory assistance is appropriate
and timely given - Make sure that DOT pre-authorizes studies and
notices of eligibility before DB issues them - DB to keep log current and available to the DOT
after each contact with property owner or
displaced person - Sky is not the limit for relocations!
- Rush to clear should not result in super adequate
and or inappropriate relocation benefits offered - DB must insure that agents employed on the DB
project meet or exceed minimum qualifications as
if they were working directly for the DOT - Agents employed by the DB must be familiar with
the subject area to ensure that what is thought
to be comparable for replacement property is in
fact comparable - Agents employed by the DB must remember that they
are the face of the DOT and must conduct
themselves accordingly
50Property Management Issues
- Salvage rights
- Lease agreements
- Terms of assumed leases
- Walk through and release of security or key
deposits - Security issues
- Demolitions
- Surplus Property
- Staging Areas
5112300 South
- 360 ownerships (over 1000 parcels)
- DB project completed in 3 years vs. 9 years
projected under DBB. - Higher administrative settlement frequency due to
aggressive schedule cost pass through
52114th South
- Special complexities
- New Bridge over Jordan River
- Relocation of a power substation
- New I-15 Interchange
- 270 ownerships plus Utility easements
- Current status Construction is 61 complete
- Acquisitions and Relocations in progress
approximately 67 of needed ROW is cleared
53Access Utah Projects and I-15 Core (Innovation)
- Pioneer Crossing, a new, five-lane urban arterial
from Redwood Road in Saratoga Springs to 300 East
in Lehi. - Innovative Components
- A new diverging diamond interchange (DDI) at I-15
and American Fork Main Street, which will replace
the existing diamond interchange. - Includes an Express Lane in each direction
through the interchange (to tie in to the
upcoming I-15 widening project). - ABC Bridge Construction (American Fork Bridge)
- Estimated completion in 2 years
- Construction is Currently 62 Complete
- Managed as part of the Access Utah group of 5
separate projects. - Central ROW provides oversight and helps to
direct, train and oversee the ROW firms hired to
clear the right of way. -
-