PPA BETWEEN BSES ANDHRA POWER Ltd. and APTRANSCO - PowerPoint PPT Presentation

About This Presentation
Title:

PPA BETWEEN BSES ANDHRA POWER Ltd. and APTRANSCO

Description:

dollar rupee exchange rate = 4.86%. depreciation = 90%. debt = 490 crore. equity = 210 crore. dollar component = 280 crore. rupee component = 210 crore-----years. – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 49
Provided by: Inte251
Learn more at: http://www.pmger.org
Category:

less

Transcript and Presenter's Notes

Title: PPA BETWEEN BSES ANDHRA POWER Ltd. and APTRANSCO


1
PPA BETWEEN BSES ANDHRA POWER Ltd. andAPTRANSCO
  • Presentation by
  • K. Raghu
  • Associate President
  • APSEB Engineers Association
  • Dt 16/01/2002

2
This presentation consists of
  1. Load forecast-Need for additional power.
  2. Availability of gas reserves in K-G basin.
  3. Trends in gas prices/implications.
  4. Alternatives.
  5. Issues involved in the present PPA.
  6. Prayer to the Commission.

3
Load forecast-Need for additional Power
  • Load forecast plans are not brought to public
    scrutiny.
  • State is landing in a surplus(?) situation.
  • For Year 2001-02
  • Available energy 45400MU
  • Energy purchased by APTRANSCO 41500MU.
  • Addition of NTPCs Simhadri power station (
    2x520MW) during 2002-03 would result in huge
    surplus situation.
  • Surplus is not a welcome sign in the absence of
    potential buyers, as it involves huge fixed cost
    commitments for APTRANSCO

4
Load forecast-Need for additional Power
  • Growth in consumption is not in keeping with the
    capacity additions.
  • it is almost stagnant for the past three
    years.(between 40000MU and 42000 MU).
  • With the reduction of TD losses there may be no
    need for any capacity addition for five more
    years.
  • Fall in subsidising sections(HT) and increase of
    agriculture consumption.
  • Capacity additions must be carefully planned.
  • Load forecast plans must be brought to public
    scrutiny.

5
Load forecast-Need for additional Power
  • While maintaining our reservation on addition of
    any new power projects without these Plans being
    brought under public scrutiny, in the present
    case, I.e the PPA between APTRANSCO and M/S BSES
    Andhra power Limited, we submit our
    objections/suggestions presuming that the
    APTRANSCO needs the power sought to be generated
    by M/S BSES Andhra Power Limited.

6
Availability of gas reserves in K-G basin
  • For the BAPL project gas is supplied from
    Krishna-Godavari Basin- from the oil fields
    located at Tativaka, Parsarlapudi, Kesnapalli,
    Mori and other nearby fields and in and around
    fields and Ravva offshore as fuel for the plant.
  • It is important to examine whether the gas
    reserves in K-G basin are sufficient to meet the
    requirement of existing and future projects,
    including the BAPL project.

7
Availability of gas reserves in K-G basin
  • Gas reserves in the K-G basin -various estimates
    (In Billion Cubic Meters)
  • As per CEA in the Fourth National Power Plan
    1997-2012...16.36BCM.
  • FICCI Task Force Report 2000..37.35BCM.
  • Hand book on Indian petroleum
    and Natural gas Industry and
    Investment scenario40.00BCM.

8
Requirement of gas
  • A) Existing Plants
  • APGPCL 12 (272MW)
  • GVK (216MW)
  • SPECTRUM (208MW)
  • KONDAPALLY(355MW)
  • TOTAL 1051 MW.
  • Therefore, gas required for the existing plants _at_
    0.005 MCMD per MW
  • 1051X 0.005 5.255.
  • Gas required per year 5.255X3651918MCM.
  • I.e 1.918 BCM.
  • _at_ 85plf gas requirement will be
    0.85X1.9181630.36MCM 1.63BCM.

9
Requirement of gas
  • B) Future Plants for which gas has already been
    allocated on firm basis
  • GVK(220MW), KONASEEMA (445 MW), VEMAGIRI (520
    MW), GOUTAMI NCC (598MW), SPECTRUM (220
    MW)8.53MCMD
  • Annual requirement 8.53X3653113MCMD 3.113BCM
  • _at_ 85plf gas requirement will be 0.85X3.1132.64
    BCM.
  • C)For BAPL project
  • Daily requirement 1MCMD
  • Annual requirement 365 MCM. 0.365 BCM.
  • D) Other users of ONGC/GAIL per year 2.58 BCM

10
Life of gas reserves in K-G basin
11
Life of gas reserves in K-G basin
  • Thus, it is very clear that
  • Even if no future additions are made, life of gas
    reserves (for the existing and other obligations
    of GAIL) is 3.63years (as per fourth national
    power plan) and 8.30 years ( as per FICCI
    estimates).
  • Where as the plant life for these projects varies
    from 15 to 18 years.
  • In the absence of gas reserves these plants will
    depend on costly alternate fuels like Naphtha,
    whose variable cost is very high.
  • It is not wise to go in for gas based projects,
    when such heavy risk is associated with these
    projects.

12
Trends in natural gas prices-implications
  • The pricing of indigenous natural gas is under an
    administered price regime wherein the price is
    decided by the GOI from time to time.
  • The pricing today is done with considerable
    amount of subsidy.
  • It is govt. policy to avoid and eliminate
    subsidies in the pricing of natural gas and bring
    it on par with international LS/HS fuel oil
    price.
  • Recently, the Petroleum ministry has proposed to
    the cabinet a hefty 81 increase at the floor
    level and 107 increase at the ceiling level
    prices of natural gas.

13
Trends in natural gas prices-implications
  • Implications of proposed changes on the power
    projects
  • The variable cost of generation may increase
    steeply. Considering Fuel Oil price prevalent
    during Sept. 2001 the price of gas is likely to
    become double from its existing level.
  • Increase in cost of fuel per unit generation will
    reduce in scheduling given for generation under
    merit order operation. This inter-alia will cause
    reduction in PLF and consumer will land up paying
    higher costs without drawing the power.
  • Since PLF shall go down, Power Sector will have
    to pay for the gas as committed even without
    consumption thereby incurring huge losses.

14
Trends in natural gas prices-implications
  • Even fixed charges per kwh will also increase due
    to lower off-take of power thus increasing the
    power cost both on account of fuel price as well
    as fixed charges per kwh.
  • Operating the gas based plants as peaking load
    stations has its own problems
  • Since the pipeline network for supply of gas can
    not take wide fluctuations in its rate of gas
    delivery, therefore, such a situation will affect
    the overall gas availability to the Power sector
    at a pointed time.
  • For the all above reasons, even if sufficient gas
    reserves are available, addition of gas- based
    stations is not in the interest of consumers.

15
Alternatives
  • SNC Lavalin commented in its document of Long
    term indicative Generation Plan for Andhra
    Pradesh, availability of gas will be a major
    concern.
  • The T.L. Shanker Committee observed that
    indigenous coal would be natural choice for power
    projects in India on both economic and other
    grounds.

16
Alternatives
  • NTPC, in a detailed paper on the choice of fuels
    for future projects in India, had concluded that
    preference should be given to coal based
    generation capacity as the cost of generation
    with domestic coal is cheaper than power
    generation with other fuels and the country has
    good reserves of coal.
  • We request the commission to encourage only coal
    based plants for any future capacity additions.

17
Issues involved in the present PPA
  • What is the subject matter before the Commission?
  • Is it giving consent to the
  • Amendment Agreement to the modified PPA
  • or simply
  • PPA between BAPL and APTRANSCO?
  • Since various covenants, such as achieving
    financial closure within 12 months from the date
    of signing of modified agreement(Art.7.1.(e)),sche
    duled date of completion - have not been
    achieved, there is no obligation on the part of
    APTRANSCO to adhere to the provisions of PPA .

18
Issues involved in the present PPA
  • Thus, there is no binding agreement between
    APTRANSCO and BAPL.
  • Any proposal for power purchase shall be treated
    as a new PPA between APTRANSCO and BAPL.
  • Hence, the proposal of APTRANSCO can not be
    treated as amendment agreement to the modified
    PPA, but only as a new PPA.
  • It is also not clear from the documents as to how
    both original and modified PPAs were signed on
    the same date, I.e on 31.03.1997, when proposal
    for merger came at a much later date.

19
Issues involved in the present PPA
  • Who should bear the risk?
  • It is also not clear how the BAPL went ahead with
    the project, without having a legally binding
    agreement with APTRANSCO.
  • By proceeding with the Project, without having
    the consent of the Commission, the developer has
    taken the riskand the Commission should ensure
    that any consent to the PPA will not put
    APTRANSCO and the consumers of the State in Risk.
  • As already stated there are so many risks
    associated with the gas-based plants viz,
  • .availability of gas, deregulation of gas prices
    etc,.
  • Also need for capacity additions at this point of
    time should be looked in to.

20
Issues involved in the present PPA
  • Need for fresh bidding
  • These projects are planned by the GOAP as short
    gestation projects(SGPs).
  • However they could not come up in time and lost
    their relevance now.
  • Originally these projects were awarded to various
    developers through ICB route.
  • Since these projects could not be completed in
    time , there is need for calling fresh bids and
    awarding the contracts to the lowest bidders.

21
Issues involved in the present PPA
  • Reasons stated for giving extensions to the same
    developers
  • It is claimed that going for fresh bids will
    cause enormous delay.
  • It is also claimed that the fixed charges per
    unit of all these projects have been brought on
    par with the lowest bidder of all the Short
    Gestation Projects, I.e.Goutami Power project,
    and thus there is no need for going for fresh
    bids.

22
Issues involved in the present PPA
  • The above reasons are not justified for the
    following reasons
  • there is no need for any urgency for setting
    upshort gestation projects at this point of
    time, since we are already having surplus power.
  • Important parameter for evaluating these projects
    at the time of awarding contracts was short
    gestation I.e. some weightage was given for
    completing the project in short duration,(
    including Goutami Power Project) at the expense
    of unit cost.
  • Now that these projects could not come up in
    time, calling for fresh bids may result in
    lowering of unit cost.

23
Issues involved in the present PPA
  • The claim that unit cost has been brought down to
    the level of Goutami Project, is also not totally
    true.
  • In the original PPA with Goutami the PLF for
    fixed cost recovery was pegged at 80.
  • In the revised PPA with Goutami(Now placed before
    the Commission for consent), PLF for fixed cost
    recovery has been raised to 85.
  • I.e. net increase of Fixed Cost payment by
    (85/80)x1006.25.
  • In real terms the increase in fixed cost
    597x0.876x6.25x0.99/100Rs 32.35 Crore/year.

24
Issues involved in the present PPA
  • For other projects also the claim of substantial
    reduction of fixed cost is not true.
  • For Ex it is claimed that for BAPL, the fixed
    cost has been brought down from Rs 1.30/Unit to
    Rs 0.99/ Unit(at present dollar exchange rate).

25
Issues involved in the present PPA
  • However, it can be seen that following factors
    have the effect of increasing the fixed cost.
  • 1. Effect of increasing PLF for fixed cost
    recovery
  • 99x 85/80-996.187 paise.
  • 2. Effect of increasing the debt repayment period
    from
  • 9 to 11 years 0.006x48x100x2/96.40
    Paise.
  • 3. Effect of increasing the capacity from 200MW
    to
  • 220MW(220/200)x99-99108.9-999.9 paise.
  • 4. Effect of provision for increase in capacity
    by 51.05x108.9-108.95.44 paise.
  • Total increase 6.1876.409.95.4427.92 paise.

26
Issues involved in the present PPA
  • Hence the fixed cost recovery per unit in real
    terms is not 99 paise but 99 27.92 126.92
    Paise.
  • I.e. 220x0.876x0.85x0.2792x1.05 Rs 48.01 crore
    more than what is stated.
  • The total additional burden on APTRANSCO and
    consumers of the state during the life of project
    is Rs 720 crore.
  • Thus it is not true that substantial savings have
    been achieved through negotiations with the
    reduction of fixed cost per unit.
  • Hence, there is a need for calling fresh bids,
    keeping revised capacity additions in view, which
    may result in substantial savings to the
    APTRANSCO.

27
Fixed cost for similar project-Is 0.6990.006
cheaper?
28
Fixed cost for similar project-Is 0.6990.006
cheaper?
29
Fixed cost for similar project-Is 0.6990.006
cheaper?
  • Average fixed cost for the identical project
  • 1662.66/15 Rs 110.844 Crore
  • Fixed cost per unit _at_ 85 PLF
  • 110.844/(2200.8760.85)Rs 0.676 per unit
  • i.e. 67.6 paise/ unit
  • Therefore, for similar capital cost the fixed
    cost obligation for APTRANSCO is 31.71 less than
    the BAPL project.

30
What should be the Fixed cost for BAPL?
  • Average fixed cost to be
  • allowed Rs 110.844Crore.
  • _at_ 85 plf fixed cost per unit
  • 110.844/(2200.8760.85) 67.66 Paise.
  • Since the OM contract provides for 92 PLF, the
    fixed cost per unit shall be
  • 67.6685/92 62.51paise.
  • If 5 increase in installed capacity is allowed,
    fixed cost recovery per unit shall be
    62.51/1.0559.53 Paise
  • However, the old practice for payment of fixed
    charges may be followed, for more clarity and to
    avoid complications.

31
Issues involved in the present PPA
  • Other important issues
  • It is not clear from the Agreement whether there
    is any provision for disincentive when the PLF
    falls below 85 and is above 68.5.
  • Clause 3.6 deals with the disincentives for PLFs
    below 68.5 only.
  • Section 5.2.(c) which deals with the Monthly
    tariff bills, only specifies the recovery to be
    made if PLF falls below 80, and not for PLFs
    below 85.

32
Issues involved in the present PPA
  • It is also not clear from 5.2.(c), whether the
    recovery proposed is for all the PLFs below 80
    or Only upto 68.5.
  • Also it is to be made clear whether the recovery
    is in addition to the penalties that are proposed
    to be levied.
  • Section 5.2.(c) states that in case PLF is less
    than 80 for any tariff year, the company shall
    refund to the Board as a credit against the
    amounts due in the next monthly tariff bills.

33
Issues involved in the present PPA
  • this is totally unjust, as APTRANSCO will lose
    the interest during this period for the payments
    already made.
  • Even for the adjustments of disincentives, there
    is no mention of any interest being added to the
    disincentive paid by the Company to APTRANSCO,
    before it is adjusted in the next tariff bills.
  • Also, there is no additional disincentive if the
    project achieves the PLF below 50.5

34
Issues involved in the present PPA
  • it means that, even if the plant does not operate
    APTRANSCO is bound to pay an amount equal
    to220x0.876x0.85x(0.99-.46x0.699)x1.05
  • Rs 114.97 Crore.
  • This is equal to 115/700x10016.42 Return on
    investments made.

35
Issues of concern in Gas Supply Agreement(GSA)
  • Allocation of gas is on fall back basis. As per
    the definition in Section 1.16 of GSAFALL BACK
    BASIS shall mean Second alternative I.e. supply
    of GAS on As And When Available Basis without
    any commitment on the part of the SELLER and
    depending upon surplus GAS available after
    meeting the demand of other firm consumers and
    fall back consumer use alternate fuel when GAS is
    not available for supply.
  • Also, according to Article 5, SELLER agrees to
    sell and deliver GAS, on as and when available
    basis,for supply to the BUYER, subject to the
    maximum of 1.0 MSCMD.

36
Issues of concern in Gas Supply Agreement(GSA)
  • Period of contranct Article 2.01 states that
    this CONTRACT shall come in to force from the
    date it is signed and shall remain valid for a
    period upto 31.12.2010. Subject to Article 5.01
    hereinafter the supply of GAS under this CONTRACT
    would commence from 1.10.2001 or from any earlier
    date that may be mutually accepted by the SELLER
    and the BUYER and shall continue for a period
    ending 31.12.2010.
  • Whereas the plant life is 15 years, the GSA is
    valid only for only 8 1/2 years from now, subject
    to the conditions of fall back basis and maximum
    availability of 1.0MCMD.

37
Issues of concern in Gas Supply Agreement(GSA)
  • It is important to note that existing plants
    viz,.GVK, SPECTRUM and APGPCL, which have gas
    allocation on Fall back firm Basis, are being
    supplied gas only to the extent of Firm allotment
    made to these projects.
  • Even if there is slight short fall in supply of
    GAS, it should be mixed with certain minimum
    quantity of NAPHTHA on technical considerations.
  • At present for APGPCL a ratio of 8020 between
    gas and naphtha is used for power generation.
    This is increasing the variable cost by 5
    paise/unit.

38
Issues of concern in Gas Supply Agreement(GSA)
  • Quality of GAS
  • Even though certain specifications are laid down
    in Annexure-I of GSA, there is no mention of
    Gross Calorific Value of gas that is supplied by
    the GAIL.
  • Without Gross Calorific Value specifically
    mentioned in the GSA, it is difficult to estimate
    the actual gas that is consumed and variable
    cost per unit of energy generated.
  • If there is any savings in GAS consumption it
    must be passed on to the consumer.

39
Issues of concern in Gas Supply Agreement(GSA)
  • Delivery of GAS
  • According to Article 4.03, in addition to the
    price of GAS, the BUYER shall pay to the SELLER
    monthly transmission charges of Rs
    1,93,15,175 per month for facilities provided by
    the SELLER for supply of GAS. (I.e. total fixed
    cost commitment to APTRANSCO is (16323.16)Rs
    186.16 crore.)
  • Also, during the currency of the CONTRACT
    irrespective of total/partial/non-supply of
    quantity of gas as per Article 5.01, the buyer
    shall pay the above monthly fixed transmission
    charges
  • the above monthly Transmission charges shall be
    increased by 3 on yearly basis with effect from
    1.4.2001.

40
Issues of concern in Gas Supply Agreement(GSA)
  • Thus the entire Gas Supply Agreement is heavily
    biased in favour of supplier, full of
    uncertainties and does not meet the requirement
    of APTRANSCO.

41
Equipment Supply OM contracts.
  • Various technical parameters specified in the
    Equipment Supply and OM contracts viz,.
  • Guaranteed output
  • gross heat rate
  • auxiliary consumption
  • sheduled date of completion
  • liquidated damages for delays, short fall, heat
    rate,shortfall in auxiliary consumption,
    guaranteed availability etc,.
  • PLF below which penalties are levied
  • are found to be far superior than those provided
    in the PPA.

42
Equipment Supply OM contracts.
  • This will unduly benefit the IPP, as all the
    benefits from EPC and OM contract are to be
    passed on to the consumer.
  • For ex it is stated in the Equipment Supply
    contract that minimum availability shall be 93
    and in OM contract minimum PLF to be maintained
    as 92. IPP will levy penalties for any shortfall
    from the stated PLF during the operation.
  • However, in the PPA it is stated that IPP will
    get incentive for generation above 85 and
    disincentive for PLFs below 68.5.
  • If the plant is operated at 90PLF, the IPP will
    not only collect incentive from APTRANSCO but
    also gets benefited from the penalty levied on
    OM contractor.

43
Issues involved in the present PPA
  • Plant Life Plant life is stated as only 15
    years. Where as for other IPP projects like GVK
    and SPECTRUM the plant life is 18 years.
  • Escrow facility in addition to the irrevocable
    revolving letter of credit in favour of the
    company, as an additional security to the
    company, APTRANSCO has to open escrow account
    with any of the Boards scheduled Bank. This is
    totally unjustified and not in the interest of
    APTRANSCO.
  • Buy out procedure The buy out procedure adopted
    in the PPA will result in the higher buy out
    price for the project at the end of 15 years.
    Since most of the capital cost (more than 90) is
    recovered by the IPP by way of fixed charges, the
    actual cost of plant shall only be 10 of the
    total capital cost

44
Prayer to the Commission
  • Not to give consent to the PPA in view of the
    following
  • Inadequate demand for power and consequent burden
    of huge fixed costs.
  • Inadequate gas reserves available in
    Krishna-Godavari Basin.
  • Lack of firm allocation of gas from GAIL.
  • Uncertainties associated with the Gas prices, in
    view of GOI policy to bring prices of natural gas
    on par with the international LS/HS fuel oil
    prices.

45
Prayer to the Commission
  1. To recommend to the GOAP to call for fresh bids
    for gas based projects, in case capacity
    additions are necessary.
  2. To give serious consideration to the
    ramifications of planning for gas based power
    projects in view of scarce natural gas resources,
    high cost of alternate fuels, high forex
    outflows, etc,.

46
Prayer to the Commission
  • 4. In case Commission decides to give Consent to
    the proposed PPA, to consider the following
    issues
  • To reduce the fixed cost burden as per the
    calculations suggested in this petition.
  • Plant life shall be increased to 18 years from
    existing 15 years on par with other Gas based
    IPPs.
  • Recovery for full fixed costs shall be at 92PLF
    as per OM contract, and in case unit cost method
    for fixed charge recovery is used, the total
    fixed cost shall be limited to the levels
    suggested in this petition.

47
Prayer to the Commission
  • Disincentives shall be applied for PLFs below
    50.5.
  • Gas supply shall be on firm basis, for full life
    of the plant.Also Gross calorific value of Gas
    shall be clearly stated.
  • Provisions relating to technical parameters of
    Equipment Supply Contract and OM contract shall
    be incorporated in the PPA.
  • Escrow facility shall not be given.
  • Buy out procedure shall be modified to reflect
    the actual cost at the end of plant life.

48
  • THANK YOU
  • APSEB ENGINEERS ASSOCIATION
Write a Comment
User Comments (0)
About PowerShow.com