Title: Improve Facility Operation through Commissioning-A Case Study
1Improve Facility Operation through
Commissioning-A Case Study
- Mingsheng Liu, Ph.D., P. E.
- University of Nebraska
2Outline
- Facility information
- Commissioning measures
- Measured results and conclusions
31. 1 Building and AHUs Information
41.2 Control Systems Information
- A modern DDC system was installed in 1995 as part
of energy retrofit project - Provide remote control on each AHUs, pump, and
terminal box - Provide remote monitoring on critical parameters
51.3 AHUs Information
- All single duct systems are converted into VAV
system with modern DDC control - All systems have economizers
- All AHUs reset supply air temperature according
to the outside air temperature - New control valves and dampers were installed as
part of the energy retrofit project in 1995.
61.4 Boiler Plant Information
- New boilers were installed in 1995
- Boiler 1-250 HP (8 MMBtu/hr)
- Boiler 2-500 HP (17 MMBtu/hr)
- Boiler 3-700 HP (23 MMBtu/hr)
71.5 Thermal Storage System
81.6 Measured Hourly Electricity Consumption
Before Commissioning
91.7 Measured Hourly Gas Consumption Before
Commissioning
101.8 Operation Problems and Concern
- Thermal Storage System 1,760 kW peak demand in
1997 (expected to be 1,400 kW) - Overall retrofit savings significantly smaller
than the projected value - EMCS systems lack of confidence of smooth
operation
112.1 Commissioning Measures
- Energy Management and Control Systems
- Buildings
- Thermal storage systems
- Boiler systems
122.2 Measures for EMCS Systems
- Point by point check software
- Verify hardware in the field
- Optimize/modify control algorithms
- Terminal box
- AHUs
- Chilled water loop
- Hot water loop
132.2.1 Example VAV Fan Speed Control
Existing schedule Modulate the fan speed to keep
at least one of the five terminal box damper at
90.
142.2.2 Real Operation
- One of the room temperature set point was 72F.
The occupant wanted to be 76F. She could not
change the set point since it was programmed by
the EMCS system. - A foot heater is used to make 76F
- The box is open to fight the heater
- The fan is speed up to satisfy the box
152.2.3 Solutions
162.3 Measures for Buildings
- Chilled water loop balance
- Hot water loop balance
- Air flow balance
- Thermostats and terminal box check up
- Dampers and linkage check up/repair/replace
172.4 Measures for Thermal Storage System
- Loop differential pressure set point optimization
- Chiller on/off schedule
- Tank charge rate optimization
- Off-peak demand reduction
182.5 Measures for Boilers
- Decrease steam pressure from 60 psig to 40 psig
at night and weekends - Use smaller boiler/boilers
193.1 Comparison of Whole Campus Electricity
Consumption
203.2 Comparison of Campus Hourly Gas Consumption
(ft3/hr)
213.3 Comparison of Measured Peak Demand
- 1785 kW in 1997 (Before commissioning)
- 1483 kW in 1998 (During commissioning)
- ???? In 1999 (After commissioning)
223.4 Comparison of Costs and Savings
- The measured annual energy savings based on paid
utility bills 146,581 - 69,669 for electrical energy
- 24,462 for peak demand
- 52,670 for gas
- The total contract amount 143,000
- The project duration 10 months (3-98 to 12-98)
233.5 Conclusions
- Look for significant amount of energy savings
from commissioning - Look for significant operating improvement from
commissioning