Title: Production Planning and Control
1Production Planning and Control
Chapter 9 Advancement in Production Planning
and Control
Professor JIANG Zhibin Department of Industrial
Engineering Management Shanghai Jiao Tong
University
2Chapter 9 Advancement in PPC
- Contents
- Optimized Production Planning
- Theory of Constraint Based Production Planning
- Advanced Planning and Scheduling
- Mass Customization and its Production Planning
3 Optimized Production Planning-Introduction (1)
- The most prevalent approach in the production
planning is based on the concept of material
requirement planning (MRP). - The release time is obtained by shifting the
expected output time back along the time scale
by a period of the estimated average lead time - The release quantity is derived by dividing the
expected output by the estimated average product
yield.
- However, MRP-based methods have three major
drawbacks - The lead time not only needs to be pre-specified
but also is assumed to be static over the entire
planning horizon - The capacity is assumed to be infinite, which
means the derived production planning may not be
realized - The production system is made nervous. Little
adjustment in MPS changes the due date, requiring
the recalculation of MRP.
4Optimized Production Planning -Introduction (2)
- New methods need to be developed for production
planning based on mathematical programming - Time Dimension
- Space Dimension
- Corporate level planning production planning
- Shop floor level planning production lot planning
- Mathematical programming based optimized
Production Planning Commonly used in production
planning - Linear Programming (LP)- the most widely used
methods - Dynamic Programming (DP)- for multi-periods
planning - Stochastic Programming (SP)-coping with the
uncertainty.
5Optimized Production Planning -L P (3)
Common LP model
x Decision variables f(x) Objective function
gi(x) constraints.
- Commonly used terms
- Objective function, constraints, right-hand side,
feasible region, feasible solution, optimal
solution. - Features of LP
- Linearity the objective and all constraints can
be expressed as a linear function of the
decisions variables - Continuity the decision variables should be
continuous
6 Optimized Production Planning -L P (4)
Example Make the production planning of milk
product One barrel of milk can be made into 3kg
A1 by 12 hours or 4kg A2 by 8 hours. The profit
of A1 and A2 are 24/kg and 16/kg, respectively.
The supply of raw material, milk, is 50 barrels
per day. Capacity is 480 hours per day and the
production limit of A1 is 100kg at most.
50 barrels of milk/ day, 480 hours available/day,
and 100kg A1 at most
7Optimized Production Planning -L P (5)
Raw material
Work hours
Constraints
Requirement constraints
8 Optimized Production Planning -L P (6)
Xi is continuous The barrels of milk is real
number
- Model Analysis
- Features of LP Linearity and Continuity
Proportion The contributions of xi to objective
function and constraints are separately
proportional to xi. Addition The contributions
of xi to objective function and constraints are
separately independent of xj.
The profit/ kg of A1,A2 is constant, and the
production quantity and time of A1,A2 from one
barrel of milk are constant.
The profit/ kg of A1,A2 is constant, and the
production quantity and time of A1,A2 from one
barrel of milk are constant.
9Optimized Production Planning An Example in
Semiconductor Manufacturing
- The following are the assumption underlying this
model - The activity of the model are the production
activity on each of wafer fab routes. Activity
are measured in terms of the quantity of wafer
released the quantity of output is measured in
terms of good die. - Each wafer type are assumed to provide a single
type of die, thus wafer types and die types are
synonymous. There can be alternative wafer fab
routes for producing the same wafer type.
10Optimized Production Planning An Example in
Semiconductor Manufacturing
- The following are the assumption underlying this
model (Cont.) - The overall planning horizon is divided into
planning periods in which demands, capacities and
productions rates are assumed to be held
constant. The length of each planning period for
each wafer fab facility may vary and is measured
in terms of working days. The length of each
period is measured in calendar days for the
purpose of discounting cash flows in the
objective functions. - A production variable is defined as a quantity of
a particular wafer type to be released following
a particular route during a planning. An
inventory variable is defined as the inventory
level of a particular die type at the end of a
planning period. A backorder variable represents
the quantity of die demand that can not be
satisfied on time at the end of a planning
period.
11Optimized Production Planning An Example in
Semiconductor Manufacturing
- The following are the assumption underlying this
model (Cont.) - The demands are expressed in terms of time-phased
die output requirements and are assumed to be net
of initial die inventory and net of equivalent
die output of the initial work-in-process (WIP).
These demands are divided into prioritized
classes that are loaded onto front end facilities
by incremental LP calculation. Demands in class 1
are loaded first, then demands in classes 1 and 2
loaded subject to not exceeding backorder levels
associated with class 1, etc. The formulation for
all classes is the same, except for the values of
the demands and the lower bounds on back order
variables. - Production is rate-based, i.e., the release
quantity in a particular period is to be
distributed uniformly over the period.
12Optimized Production Planning An Example in
Semiconductor Manufacturing
- The following are the assumption underlying this
model (Cont.) - As a horizon condition, the wafer fab are
required to enter steady-state, whereby
production releases on each route are required to
follow some constant rate in all periods falling
within one total flow time of the planning
horizon. The planning periods that overlap the
interval beginning one total flow time for a
route before the planning horizon until the
horizon are termed frozen periods with respect to
that route. Demands from each class in the last
planning period are assumed to continue at the
same rate forever.
13Optimized Production Planning An Example in
Semiconductor Manufacturing
- Parameters
- g die type.
- i wafer fab route.
- l processing step (i. e., operation) on a wafer
fab route. - li the last step on wafer fab route i.
- k resource type (i. e., machine type).
- p, q planning period, p 1,2,,P. P is the
planning horizon. An extra period P1 is appended
to the planning horizon whose length is equal to
the flow time of the longest fab route. - r demand class, r 1,2,,R.
- Gr set of all die types appearing in r-th demand
class. - I r set of all wafer routes producing die types
appearing in Gr. - Kr set of all resource types loaded by routes in
I r.
14Optimized Production Planning An Example in
Semiconductor Manufacturing
The following values are assumed to be known and
constant
15Optimized Production Planning An Example in
Semiconductor Manufacturing
Continued
16Optimized Production Planning An Example in
Semiconductor Manufacturing
Variables
Short notation
17Optimized Production Planning An Example in
Semiconductor Manufacturing
Maximize the discounted sum of (die output
revenue)-(raw material cost)-(die inventory
holding cost)-(cost of backordered die demands)
Objective function (For r-th demand class)
- Constraints
- Conservation of Die Demand
- Constraints relating Resource Capacity
- Variables ranges.
18Optimized Production Planning An Example in
Semiconductor Manufacturing
(die output during the period) (inventory at
the end of period) (backorders at the end of
period) (demands at the end of period)
(die output during the period) (inventory at
the start of period) (backorders at the end of
period) (inventory at the end of period)
(backorders at the end of period) (demands at
the end of period)
(die output during the period) (backorders at
the end of period) (backorders at the end of
period) (demands at the end of period)
Constraints Conservation of Die
Demand Constraints relating Resource
Capacity Variables ranges.
19Optimized Production Planning An Example in
Semiconductor Manufacturing
(machine hours required to process new releases)
(available machine hours for processing activity)
(machine hours required to flush initial WIP)
Constraints Conservation of Die
Demand Constraints relating Resource
Capacity Variables ranges.
0 (backorder variables) ( upper bound on
backorder quantity), and all other variables0.
20Optimized Production Planning -Dynamic
Programming (DP)
- DP is an approach developed to solve sequential,
or multi-stage, decision problems by solving a
series of single stage problems - DP tends to break the original problem to
sub-problems and chooses the best solution in the
sub-problems, beginning from the smaller in size - DP follows the principle of best, that is the
best solution of the problem will come by the
combination of the best solutions of
sub-problems, if the possible solutions of a
problem are a combination of possible solutions
of sub-problems - DP can solve the multi-periods production
planning problems.
21Optimized Production Planning -Dynamic
Programming (DP)
The decision makers take some actions at the
first stage A recourse decision can then be made
in the second stage that compensates for any bad
effects that might have been experienced as a
result of the first-stage decision.
- SP is a framework for modeling optimization
problems that involve uncertainty - The most widely applied and studied stochastic
programming models are two-stage linear programs - Multi-stage linear programs have been extended,
- SP can tackle the uncertainty of future demand.
Each stage consists of a decision followed by a
set of observations of the uncertain parameters
which are gradually revealed over time.
22 APS-Overview of Planning and Scheduling
- Generally speaking, planning and scheduling
jointly determine how, when, and in what quantity
products will be manufactured or purchased. In
essence, planning establishes what should be done
and scheduling determines how to do it - There is no agreed definition of planning versus
scheduling. Many believe that the right and only
way to achieve accurate due dates is to perform
very detailed scheduling. Others believe that it
is much more important to put more effort in the
planning process. But most agree that the
distinction between planning and scheduling is
the trade-off of time horizon versus the level of
detail.
23APS- Definition
Advanced Planning and Scheduling (APS) is a
software system that uses intelligent analytical
tools to perform finite scheduling and produce
realistic plans.
24 APS-Overview (1)
- Its most important advantage over traditional
planning approaches is that material and capacity
are simultaneously considered as elements that
may constrain production. This stands in marked
contrast to the conventional MRP approach of
independently planning material and then
subsequently checking this plan against capacity
to identify violations - APS systems are able to generate plans and
schedules very quickly. An APS engine can be
designed to either look over a long time horizon
(a few months) with less details or more details
over a shorter period (a few weeks). - APS covers various capabilities such as finite
capacity scheduling or constraint-based
scheduling at shop floor level - Quite intuitive to say that the APS systems
resolve (or attempt to resolve) the shortfall of
the ERP system as a planning tool
25APS-Overview (2)
- APS does Advanced Planning
- Consider business objectives
- Consider the organization of machines and work
cells - APS does Advanced Scheduling
- Consider plant capacity
- Consider business limitations
26APS-the Scope (1)
- The scope of APS is not limited to factory
planning and scheduling, but has grown rapidly to
include the full spectrum of enterprise and
inter-enterprise planning and scheduling
functions - Strategic and long-term planning
- Demand planning and forecasting
- Sales and operations planning (SOP)
- Inventory planning
- Supply chain planning (SCP)
- Available-to-promise (ATP)
27APS-the Scope (2)
- Manufacturing planning
- Distribution planning
- Transportation planning
- Production scheduling
- Shipment scheduling
- Inter-company collaboration
- Source Bermudez, John. Advance Planning and
Scheduling Is It as Good as It Sounds? The
Report on Supply Chain Management. Advanced
Manufacturing Research, Inc., March, 1998.)
28APS- the Four-Part Model
AMRs APS Model
Source Advanced Manufacturing Research, Inc.
29APS- Mathematical Technologies
- Linear Programming
- Genetic Algorithms
- Heuristics
- Constraint Based Programming (CBP)
- Source Shires, Nigel, (2005). Optimization
Techniques and Their Application to Production
Scheduling , White Paper, Preactor
International, published on website
http//www.preactor.com/whitepapers.asp.
30APS-APS/ERP Integration
The comprehensive nature of todays APS
algorithms drives the need for copious amounts of
data--data that typically reside in an ERP
system. This means that attaining the full
benefits of APS is largely predicted on how well
it is integrated with ERP. When done well, both
systems benefit. Source Musselman, K., and
Uzsoy, R. (2001), Advanced Planning and
Scheduling for Manufacturing, in Handbook of
Industrial Engineering, 3rd Ed., G. Salvendy,
Eds., John Wiley Sons, New York.
31APS/ERP Integration
APS/ERP Integration
Source Musselman, K., and Uzsoy, R. (2001),
Advanced Planning and Scheduling for
Manufacturing, in Handbook of Industrial
Engineering, 3rd Ed., G. Salvendy, Eds., John
Wiley Sons, New York.
32APS- Software Providers
- Preactor
- SAP - Advanced Planner and Optimizer (APO)
- Oracle - APS
- Manugistics
- i2
-
33APS-Preactor APS Screenshot
34APS-SAP-APO Screenshot
35Theory of Constraints (TOC)-Introduction
- The theory was first described by Israels
physicist Dr. Eliyahu M. Goldratt in his book The
Goal as a way of managing the business to
increase profits in 1980s .
TOC is a proven method that can be used by
existing personnel to increase throughput
(sales), reliability, and quality while
decreasing inventory, WIP, late deliveries, and
overtime. Successful organizations also adopt
TOC to help make tactical strategic decisions
for continuous improvement.
36TOC-Introduction
- The Theory of Constraints is based on the
premise that - Every real system, such as a business, must have
within it at least one constraint. If this were
not the case then the system could produce
unlimited amounts of whatever it was striving
for, profit in the case of a business..
-
Dr Eli Goldratt
37TOC-Drum Buffer Rope
buffer
rope
drum
- Drum Buffer Rope (DBR) is a planning and
scheduling solution derived from the Theory of
Constraints (TOC). - The fundamental assumption of DBR is that within
any plant there is one or a limited number of
scarce resources which control the overall output
of that plant. This is the drum, which sets
the pace for all other resources. - In order to maximize the output of the system,
planning and execution behaviors are focused on
exploiting the drum, protecting it against
disruption through the use of time buffers, and
synchronizing or subordinating all other
resources and decisions to the activity of the
drum through a mechanism that is akin to a
rope.
38TOC-the Steps for Implementation
- Step 1 Identify the system's constraint(s)
- Step 2 Decide how to exploit the systems
constraint(s) - Step 3 Subordinate everything else to the above
decision - Step 4 Elevate the systems constraint(s)
- Step 5 If in the previous step, a constraint has
been broken go back to step 1, but
do not allow inertia to become the systems
constraint
39TOC- Types of Constraint
- A constraint is anything in an organization that
limits it from moving toward or achieving its
goal. - There are two basic types of constraints
physical constraints and non-physical
constraints. - A physical constraint is something like the
physical capacity of a machine. - A non-physical constraint might be something
like demand for a product, a corporate procedure,
or an individual's paradigm for looking at the
world. - THE MARKET
- CAPACITY
- RESOURCES
- SUPPLIERS
- FINANCE
- KNOWLEDGE OR COMPETENCE
- POLICY
40TOC- Applications
- 1. Production Planning and Scheduling
- 2. Distribution and Supply Chain
- 3. Financial Management
- 4. Marketing
- 5. Strategic Planning
- 6. Project Management
41TOC-the Principles of Applying TOC in Production
Scheduling
- Factory production rate is production rate of
bottleneck work center - Most of the buffer WIP should be waiting at
bottleneck - Bottleneck implies certain amount of idle time at
other work stations - Important to regulate bottleneck workload other
work centers should serve the bottleneck, not
optimize themselves.
42TOC-Capacity and Bottlenecks in Production
- Capacity is defined as the available time for
production (excluding maintenance and other
downtime) - A bottleneck (constraint) is defined as any
resource whose capacity is less than the demand
placed upon it - A non-bottleneck is a resource whose capacity is
greater than the demand placed on it - A capacity-constrained resource (CCR) is one
whose utilization is close to capacity and could
be bottleneck if it is not scheduled carefully
43TOC- An Example in Semiconductor Manufacturing
- SLIM (Short Cycle Time and Low Inventory in
Manufacturing) is a project carried by Prof.
Leachman at University of California at Berkeley.
- SLIM is a set of methodologies and scheduling
applications for managing cycle time in
semiconductor and its main method is TOC. - Between 1996 and 1999, Samsung Electronics Corp.,
Ltd., implemented SLIM in all its semiconductor
manufacturing facilities and achieve great
success - During the presentation at the 2001 Franz
Edelman Award Competition, Yoon-Woo Lee,
president of Samsungs semiconductor business,
stated The financial impact of SLIM was
significant. We increased revenue - almost 1 billion dollars through five years
without any additional capital investment, and
our global DRAM market share increased from 18
percent to 22 percent.
44TOC- An Example in Semiconductor Manufacturing
WIP between photo steps at normal time
Fab Process
The pipe represents the production line, and its
width represents the maximum flow rate or
capacity at various process steps. SEC fabs were
designed so that the photo machines are the
bottlenecks, and other machines have surplus
capacity. Thus the pipe in the figure narrows at
each photo step. When all the machines are up
and the process is in control, the photo
machines are the bottlenecks, and the largest
concentrations of WIP is at those points.
45TOC- An Example in Semiconductor Manufacturing
WIP between photo steps at disturbance
The case of process or equipment trouble at a
non-photo manufacturing area of the fab is
depicted by a constriction of the pipe at a
non-photo step. If this condition persists, the
WIP at a photo machine can become exhausted. A
buffer is needed, proportional to the risk of
trouble in that layer. For example, if Layer j of
the process experiences more trouble than Layer
j1 the bottleneck step immediately following
Layer j should be awarded a larger buffer than
the bottleneck step following Layer j1.
46TOC- An Example in Semiconductor Manufacturing
The way to solve the problem
- The philosophy underlying SLIM is to distribute
WIP to put the fab in the best position to cope
with the next disruption. That is, while the
equipment and process are working well, the fab
should strive to move as much WIP as possible to
the photo bottleneck, to be prepared for the next
disruption.
47CS-Introduction
- With the increasing competition in the global
market, the manufacturing industry has been
facing the challenge of increasing customer
value - More importantly, quality means ensuring customer
satisfaction and enhancing customer value to the
extent that customers are willing to pay for the
goods and services - A well-accepted practice in both academia and
industry is the exploration of flexibility in
modern manufacturing systems to provide quick
response to customers with new products catering
to a particular spectrum of customer needs - The key to success in the highly competitive
manufacturing enterprise often is the companys
ability to design, produce, and market
high-quality products within a short time frame
and at a price that customers are willing to pay - In order to meet these pragmatic and highly
competitive needs of todays industries, it is
imperative to promote high-value-added products
and services - Mass customization enhances profitability through
a synergy of increasing customer-perceived values
and reducing the costs of production and
logistics.
48CS-Introduction
- Mass customization is producing goods and
services to meet individual customers needs with
near mass production efficiency - Mass customization is a new paradigm for
industries to provide products and services that
best serve customer needs while maintaining
near-mass production efficiency. Contradicted two
sides
- Mass production demonstrates an advantage in
high-volume production - Satisfying each individual customers needs can
often be translated into higher value, however,
economically not viable
49CS-Introduction
Economic Implication of Mass Customization
- Mass customization is capable of reducing costs
and lead time by accommodating companies to
garner economy of scale by repetitions. - With flexibility and programmability, companies
with low to medium production volume can gain an
edge over competitors by implementing MC - Mass customization can potentially develop
customer loyalty, propel company growth, and
increase market share by widening the product
range.
50CS-Introduction
Technical challenges
- The essence of mass customization lies in the
product and service providers ability to
perceive and capture latent market niches and
subsequently develop technical capabilities to
meet the diverse needs of target customers - To encapsulate the needs of target customer
groups means to emulate existing or potential
competitors in quality, cost, quick response - Therefore, the requirements of mass customization
depend on three aspects time-to-market (quick
responsiveness), variety (customization), and
economy of scale (volume production efficiency) - Successful mass customization depends on a
balance of three elements features, cost, and
schedule.
51CS-Introduction
Maximizing reusability
- Maximal amounts of repetition are essential to
achieve the efficiency of mass production, as
well as efficiencies in sales, marketing, and
logistics, which attained through maximizing
commonality in design, which leads to reusable
tools, equipment, and expertise in subsequent
manufacturing - Customization emphasizes the differentiation
among products. - An important step toward to this goal is the
development and proliferation of design
repositories that are capable of creating various
customized products - Dynamic stability a firm can serve the widest
range of customers and changing product demands. - To achieve mass customization, the synergy of
commonality and modularity needs to be tackled
and needs to encompass both the physical and
process domains of design.
52CS- Introduction
Product platform
- The effectiveness of a firms new product
generation lies in - Its ability to create a continuous stream of
successful new products over an extended period
of time - The attractiveness of these products to the
target market niches - The essence of mass customization is to maximize
such a match of internal capabilities with
external market needs - A product platform is impelled to provide the
necessary taxonomy for positioning different
products and the underpinning structure
describing the interrelationships between various
products with respect to customer requirements,
competition information, and fulfillment
processes - This implicates two aspects
- to represent the entire product portfolio,
including both existing products and proactively
anticipated ones, by characterizing various
perceived customer needs, and - to incorporated proven designs, materials, and
process technologies
53CS- Introduction
Integrated product life cycle
- Mass customization starts from understanding
customers individual requirements and ends with
a fulfillment process targeting each particular
customer, - The time-to-market can be achieved by telescoping
lead time - Product realization should simultaneously satisfy
various product life cycle concerns, including
functionality, cost, schedule, reliability,
manufacturability, marketability, and
serviceability, to name but a few - The realization of mass customization requires
not only integration across the product
development horizon, but also the provision of a
context-coherent integration of various
viewpoints of product life cycle.
54CS-Design for mass customization
- Design for mass customization (DFMC) aims at
considering economies of scope and scale at the
early design stage of the product-realization
process - The main emphasis of DFMC is on elevating the
current practice of designing individual products
to designing product families - There two basic concepts underpinning DFMC
- Product family architecture
- Product family design.
55CS-Understanding DFMC
56CS-Product family
- A product family is a set of products that are
derived from a common platform - A product family targets a certain market
segment, whereas each product variant is
developed to address a specific set of customer
needs of the market segment - The interpretation of product families depends on
different perspectives.
57CS-Modularity and commonality
- There two basic issues associated with product
families modularity and commonality - Modularity tries to separate a system into
independent parts or modules that can be treated
as logical units - Decomposition is a major concern in modularity
analysis - Modularity is achieved from multiple viewpoints,
including functionality, solution technologies,
and physical structures - There are three types of modularity involved in
product realization functional modularity,
technical modularity, and physical modularity - The interaction between modules is important in
characterizing modularity. - As for functional modularity, the interaction is
exhibited by the relevance of functional features
(FFs) across different customer groups
58CS-Modularity and commonality (Continued)
- The commonality reveals the difference of the
architecture of product families from the
architecture of a single product - Corresponding to the three types of modularity,
there are three types of commonality in
accordance with functional, design, and process
views - Functional commonality manifests itself through
functional classification, that is, grouping
similar customer requirements into one class,
where similarity is measured by the Euclidean
distance among FF instances - A class of products is described by modularity
and product variants differentiate according to
the commonality among module instances.
59CS-A comparison of modularity and commonality
Issues Modularity Commonality
Focused objects Type (class) Instances (members)
Characteristic of measure Interaction Similarity
Analysis method Decomposition Clustering
Product differentiation Product structure Product variants
Integration/relation Class-member relationship Class-member relationship
60CS-Product variety
- Product variety is defined as the diversity of
products that a manufacturing enterprise provides
to the marketplace - Two types of variety can be observed functional
variety and technical variety - Functional variety is used broadly to mean any
differentiation in the attributes related to a
products functionality from which the customer
could derive certain benefits - Technical variety refers to diverse technologies,
design methods, manufacturing processes,
components and/or assemblies, and so on that are
necessary to achieve specific functionality of a
product required by the customer. It may be
invisible to customers - While functional variety is mostly related to
customer satisfaction from the marketing/sales
perspective, technical variety usually involves
manufacturability and costs from the engineering
perspective.
61CS-Product variety (Continued)
- These two types of variety result in two
different variety design strategies functional
variety strategy and design for functional
variety strategy - Since functional variety directly affects
customer satisfaction, this type of variety
should be encouraged in product development - A design for functional variety strategy aims
at increasing functional variety and manifests
itself through vast research in the business
community, such as product line structuring,
equilibrium pricing, and product positioning - A design for technical variety tries to reduce
technical variety so as to gain cost advantages.
62CS-Variety Leverage Handling Variety for Mass
Customization
63CS-Product family architecture
- A well-planned product family architecture (PFA)
provides a generic umbrella for capturing and
utilizing commonality, within each new product
instantiated and extends so as to anchor future
designs to a common product line structure.
64CS-PFA and Its Relationships with Market Segments
65CS-Composition of PFA
- The PFA consists of three elements the common
base, the differentiation enabler, and the
configuration mechanism - Common bases (CBs) are the shared elements among
different products in a product family - Differentiation enablers (DEs) are basic elements
making products different from one another. They
are the source of variety within a product
family - Configuration mechanisms (CMs) define the rules
and means of deriving product variants. Three
types of configuration mechanisms can be
identified selection constraints, include
conditions, and variety generation.
66CS-Composition of PFA (Continued)
- Selection constraints specify restrictions on
optional features because certain combinations of
options are not allowed or feasible or, on the
contrary, are mandatory - Include conditions are concerned with the
determination of alternative variants for each
differentiation enabler. The include condition of
a variant defines the condition under which the
variant should be used or not used with respect
to achieving the required product
characteristics - Variety generation refers to the way in which the
distinctiveness of product features can be
created. It focuses on the engineering
realization of custom products in the form of
product structures.
67CS-Basic Methods of Variety Generation
68CS-Synchronization of multiple views
- The strategy is to employ a generic, unified
representation and to use its fragments for
different purposes, rather than to maintain
consistency among multiple representations
through transformation of different product data
models to standard ones.
69CS-Representing Multiple Views of Product Family
within a Single Context
70CS-Product family design
- Under the umbrella of PFA, product family design
manifests itself through the derivation processes
of product variants based on PFA constructs.
71PFA-Based Product Family Design Variant
Derivation through GPS Instantiation
72CS- PFA-Based Product Family Design Variant
Derivation through GPS Instantiation
73CS- Manufacturing and production planning
- Competition for mass customization manufacturing
is focused on the flexibility and responsiveness
in order to satisfy dynamic changes of global
markets. The future major trends are - A major part of manufacturing will gradually
shift from mass production to the manufacturing
of semi-customized or customized products to meet
increasingly diverse demands - The made-in-house mindset will gradually shift
to distributed locations, and various entities
will team up with others to utilize special
capabilities at different locations to speed up
product development, reduce risk, and penetrate
local markets - Centralized control of various entities with
different objectives, locations, and cultures is
almost out of the question now. control systems
to enable effective coordination among
distributed entities have become critical to
modern manufacturing systems.
74CS-Managing variety in production planning
- Major challenge of mass customization production
planning results from the increase of variety - Facing such a variety dilemma, many companies try
to satisfy demands from their customers through
engineer-to-order, make-to-order, or
assembly-to-order production systems - The traditional approach to variant handling is
to treat every variant as a separate product by
specifying a unique BOM for each variant. This
works with a low number of variants, but not when
customers are granted a high degree of freedom in
specifying products. The problem is that a large
number of BOM structures will occur in mass
customization production - To overcome these limitations, a generic BOM
(GBOM) concept has been developed. - The GBOM provides a means of describing, with a
limited amount of data, a large number of
variants within a product family,while leaving
the product structure unimpaired. The structure
has three aspects
75CS-A Generic Structure for Characterizing Variety
76CS-The generic variety structure for souvenir
clocks
Structure items Ii Variety parameter Pj Variety instance Vj
3/hands Setting type Two-hand setting, three-hand setting
3/hands Color White, Grey, etc.
3/hands Size Large, medium, small
3/dial pattern Logo, mosic, scenery, customized photo, etc.
3/dial Size Large, medium, small
4/transmission Alarm Yes, no
4/core Alarm Yes, no
3/base Shape Round, rectangular, hexagonal
3/base Material Acrylic, aluminum, etc.
3/base Color Transparent, red, etc.
3/front plate Shape Rectangular,round, rhombus
3/front plate Material Acrylic, aluminum, etc.
3/front plate Color Transparent, red, etc.
1/label sticker Pattern HKUST, signature, etc.
1/paper box Type Ordinary, deluxe, etc.
77CS-The generic variety structure for souvenir
clocks (continued)
- To understand the generic concept underlying
such a variety representation, two fundamental
issues need to be highlighted - Generic item
- Indirect identification.
78CS-Coordination in manufacturing resource
allocation
- Challenges of manufacturing resource allocation
for mass customization include - The number of product variety flowing through the
manufacturing system is approaching an
astronomical scale - Production forecasting for each line item and its
patterns is not often available - Systems must be capable of rapid response to
market fluctuation - The system should be easy for reconfiguration
---- ideally, one set of codes employed across
different agents - The addition and removal of resources or jobs can
be done with little change of scheduling systems.
79CS-Major considerations of scheduling for
resource allocation
- Decompose large, complex scheduling problem into
smaller, disjointed allocation problems - Decentralize resource access, allocation, and
control mechanisms - Design a reliable, fault-tolerant, and robust
allocation mechanism - Design scalable architectures for resource access
in a complex system and provide a plug-and-play
resource environment such that resource providers
and consumers can enter or depart from the market
freely - Provide guarantees to customers and applications
on performance criteria.
80CS-A Market Structure for Collaborative Scheduling
81CS-A Market Structure for Collaborative
Scheduling (Continued)
- The satisfaction of multiple criteria, such as
costs and responsiveness, cannot be achieved
using solely a set of dispatching rules - A price mechanism should be constructed to serve
as an invisible hand to guide the coordination in
balancing diverse requirements and maximizing
performance in a dynamic environment.
82CS-The Price Mechanism of a Market Model
83CS-Message-Based Bidding and Dynamic Control
84CS-High-variety shop-floor control
- The requirements of the new control systems
include re-configurability, decomposability, and
scalability to achieve make-to-order with very
short response time
85Chapter 9 Advancement in PPC