Production Planning and Control - PowerPoint PPT Presentation

1 / 85
About This Presentation
Title:

Production Planning and Control

Description:

Title: No Slide Title Author: McGraw-Hill Higher Education Last modified by: Administrator Created Date: 10/24/2000 4:00:39 PM Document presentation format – PowerPoint PPT presentation

Number of Views:344
Avg rating:3.0/5.0
Slides: 86
Provided by: McGrawHill228
Category:

less

Transcript and Presenter's Notes

Title: Production Planning and Control


1
Production Planning and Control
Chapter 9 Advancement in Production Planning
and Control
Professor JIANG Zhibin Department of Industrial
Engineering Management Shanghai Jiao Tong
University
2
Chapter 9 Advancement in PPC
  • Contents
  • Optimized Production Planning
  • Theory of Constraint Based Production Planning
  • Advanced Planning and Scheduling
  • Mass Customization and its Production Planning

3
Optimized Production Planning-Introduction (1)
  • The most prevalent approach in the production
    planning is based on the concept of material
    requirement planning (MRP).
  • The release time is obtained by shifting the
    expected output time back along the time scale
    by a period of the estimated average lead time
  • The release quantity is derived by dividing the
    expected output by the estimated average product
    yield.
  • However, MRP-based methods have three major
    drawbacks
  • The lead time not only needs to be pre-specified
    but also is assumed to be static over the entire
    planning horizon
  • The capacity is assumed to be infinite, which
    means the derived production planning may not be
    realized
  • The production system is made nervous. Little
    adjustment in MPS changes the due date, requiring
    the recalculation of MRP.

4
Optimized Production Planning -Introduction (2)
  • New methods need to be developed for production
    planning based on mathematical programming
  • Time Dimension
  • Space Dimension
  • Corporate level planning production planning
  • Shop floor level planning production lot planning
  • Mathematical programming based optimized
    Production Planning Commonly used in production
    planning
  • Linear Programming (LP)- the most widely used
    methods
  • Dynamic Programming (DP)- for multi-periods
    planning
  • Stochastic Programming (SP)-coping with the
    uncertainty.

5
Optimized Production Planning -L P (3)
Common LP model
x Decision variables f(x) Objective function
gi(x) constraints.
  • Commonly used terms
  • Objective function, constraints, right-hand side,
    feasible region, feasible solution, optimal
    solution.
  • Features of LP
  • Linearity the objective and all constraints can
    be expressed as a linear function of the
    decisions variables
  • Continuity the decision variables should be
    continuous

6
Optimized Production Planning -L P (4)
Example Make the production planning of milk
product One barrel of milk can be made into 3kg
A1 by 12 hours or 4kg A2 by 8 hours. The profit
of A1 and A2 are 24/kg and 16/kg, respectively.
The supply of raw material, milk, is 50 barrels
per day. Capacity is 480 hours per day and the
production limit of A1 is 100kg at most.
50 barrels of milk/ day, 480 hours available/day,
and 100kg A1 at most
7
Optimized Production Planning -L P (5)
Raw material
Work hours
Constraints
Requirement constraints
8
Optimized Production Planning -L P (6)
Xi is continuous The barrels of milk is real
number
  • Model Analysis
  • Features of LP Linearity and Continuity

Proportion The contributions of xi to objective
function and constraints are separately
proportional to xi. Addition The contributions
of xi to objective function and constraints are
separately independent of xj.
The profit/ kg of A1,A2 is constant, and the
production quantity and time of A1,A2 from one
barrel of milk are constant.
The profit/ kg of A1,A2 is constant, and the
production quantity and time of A1,A2 from one
barrel of milk are constant.
9
Optimized Production Planning An Example in
Semiconductor Manufacturing
  • The following are the assumption underlying this
    model
  • The activity of the model are the production
    activity on each of wafer fab routes. Activity
    are measured in terms of the quantity of wafer
    released the quantity of output is measured in
    terms of good die.
  • Each wafer type are assumed to provide a single
    type of die, thus wafer types and die types are
    synonymous. There can be alternative wafer fab
    routes for producing the same wafer type.

10
Optimized Production Planning An Example in
Semiconductor Manufacturing
  • The following are the assumption underlying this
    model (Cont.)
  • The overall planning horizon is divided into
    planning periods in which demands, capacities and
    productions rates are assumed to be held
    constant. The length of each planning period for
    each wafer fab facility may vary and is measured
    in terms of working days. The length of each
    period is measured in calendar days for the
    purpose of discounting cash flows in the
    objective functions.
  • A production variable is defined as a quantity of
    a particular wafer type to be released following
    a particular route during a planning. An
    inventory variable is defined as the inventory
    level of a particular die type at the end of a
    planning period. A backorder variable represents
    the quantity of die demand that can not be
    satisfied on time at the end of a planning
    period.

11
Optimized Production Planning An Example in
Semiconductor Manufacturing
  • The following are the assumption underlying this
    model (Cont.)
  • The demands are expressed in terms of time-phased
    die output requirements and are assumed to be net
    of initial die inventory and net of equivalent
    die output of the initial work-in-process (WIP).
    These demands are divided into prioritized
    classes that are loaded onto front end facilities
    by incremental LP calculation. Demands in class 1
    are loaded first, then demands in classes 1 and 2
    loaded subject to not exceeding backorder levels
    associated with class 1, etc. The formulation for
    all classes is the same, except for the values of
    the demands and the lower bounds on back order
    variables.
  • Production is rate-based, i.e., the release
    quantity in a particular period is to be
    distributed uniformly over the period.

12
Optimized Production Planning An Example in
Semiconductor Manufacturing
  • The following are the assumption underlying this
    model (Cont.)
  • As a horizon condition, the wafer fab are
    required to enter steady-state, whereby
    production releases on each route are required to
    follow some constant rate in all periods falling
    within one total flow time of the planning
    horizon. The planning periods that overlap the
    interval beginning one total flow time for a
    route before the planning horizon until the
    horizon are termed frozen periods with respect to
    that route. Demands from each class in the last
    planning period are assumed to continue at the
    same rate forever.

13
Optimized Production Planning An Example in
Semiconductor Manufacturing
  • Parameters
  • g die type.
  • i wafer fab route.
  • l processing step (i. e., operation) on a wafer
    fab route.
  • li the last step on wafer fab route i.
  • k resource type (i. e., machine type).
  • p, q planning period, p 1,2,,P. P is the
    planning horizon. An extra period P1 is appended
    to the planning horizon whose length is equal to
    the flow time of the longest fab route.
  • r demand class, r 1,2,,R.
  • Gr set of all die types appearing in r-th demand
    class.
  • I r set of all wafer routes producing die types
    appearing in Gr.
  • Kr set of all resource types loaded by routes in
    I r.

14
Optimized Production Planning An Example in
Semiconductor Manufacturing
The following values are assumed to be known and
constant
15
Optimized Production Planning An Example in
Semiconductor Manufacturing
Continued
16
Optimized Production Planning An Example in
Semiconductor Manufacturing
Variables
Short notation
17
Optimized Production Planning An Example in
Semiconductor Manufacturing
Maximize the discounted sum of (die output
revenue)-(raw material cost)-(die inventory
holding cost)-(cost of backordered die demands)
Objective function (For r-th demand class)
  • Constraints
  • Conservation of Die Demand
  • Constraints relating Resource Capacity
  • Variables ranges.

18
Optimized Production Planning An Example in
Semiconductor Manufacturing
(die output during the period) (inventory at
the end of period) (backorders at the end of
period) (demands at the end of period)
(die output during the period) (inventory at
the start of period) (backorders at the end of
period) (inventory at the end of period)
(backorders at the end of period) (demands at
the end of period)
(die output during the period) (backorders at
the end of period) (backorders at the end of
period) (demands at the end of period)
Constraints Conservation of Die
Demand Constraints relating Resource
Capacity Variables ranges.
19
Optimized Production Planning An Example in
Semiconductor Manufacturing
(machine hours required to process new releases)
(available machine hours for processing activity)
(machine hours required to flush initial WIP)
Constraints Conservation of Die
Demand Constraints relating Resource
Capacity Variables ranges.
0 (backorder variables) ( upper bound on
backorder quantity), and all other variables0.
20
Optimized Production Planning -Dynamic
Programming (DP)
  • DP is an approach developed to solve sequential,
    or multi-stage, decision problems by solving a
    series of single stage problems
  • DP tends to break the original problem to
    sub-problems and chooses the best solution in the
    sub-problems, beginning from the smaller in size
  • DP follows the principle of best, that is the
    best solution of the problem will come by the
    combination of the best solutions of
    sub-problems, if the possible solutions of a
    problem are a combination of possible solutions
    of sub-problems
  • DP can solve the multi-periods production
    planning problems.

21
Optimized Production Planning -Dynamic
Programming (DP)
The decision makers take some actions at the
first stage A recourse decision can then be made
in the second stage that compensates for any bad
effects that might have been experienced as a
result of the first-stage decision.
  • SP is a framework for modeling optimization
    problems that involve uncertainty
  • The most widely applied and studied stochastic
    programming models are two-stage linear programs
  • Multi-stage linear programs have been extended,
  • SP can tackle the uncertainty of future demand.

Each stage consists of a decision followed by a
set of observations of the uncertain parameters
which are gradually revealed over time.
22
APS-Overview of Planning and Scheduling
  • Generally speaking, planning and scheduling
    jointly determine how, when, and in what quantity
    products will be manufactured or purchased. In
    essence, planning establishes what should be done
    and scheduling determines how to do it
  • There is no agreed definition of planning versus
    scheduling. Many believe that the right and only
    way to achieve accurate due dates is to perform
    very detailed scheduling. Others believe that it
    is much more important to put more effort in the
    planning process. But most agree that the
    distinction between planning and scheduling is
    the trade-off of time horizon versus the level of
    detail.

23
APS- Definition
Advanced Planning and Scheduling (APS) is a
software system that uses intelligent analytical
tools to perform finite scheduling and produce
realistic plans.
24
APS-Overview (1)
  • Its most important advantage over traditional
    planning approaches is that material and capacity
    are simultaneously considered as elements that
    may constrain production. This stands in marked
    contrast to the conventional MRP approach of
    independently planning material and then
    subsequently checking this plan against capacity
    to identify violations
  • APS systems are able to generate plans and
    schedules very quickly. An APS engine can be
    designed to either look over a long time horizon
    (a few months) with less details or more details
    over a shorter period (a few weeks).
  • APS covers various capabilities such as finite
    capacity scheduling or constraint-based
    scheduling at shop floor level
  • Quite intuitive to say that the APS systems
    resolve (or attempt to resolve) the shortfall of
    the ERP system as a planning tool

25
APS-Overview (2)
  • APS does Advanced Planning
  • Consider business objectives
  • Consider the organization of machines and work
    cells
  • APS does Advanced Scheduling
  • Consider plant capacity
  • Consider business limitations

26
APS-the Scope (1)
  • The scope of APS is not limited to factory
    planning and scheduling, but has grown rapidly to
    include the full spectrum of enterprise and
    inter-enterprise planning and scheduling
    functions
  • Strategic and long-term planning
  • Demand planning and forecasting
  • Sales and operations planning (SOP)
  • Inventory planning
  • Supply chain planning (SCP)
  • Available-to-promise (ATP)

27
APS-the Scope (2)
  • Manufacturing planning
  • Distribution planning
  • Transportation planning
  • Production scheduling
  • Shipment scheduling
  • Inter-company collaboration
  • Source Bermudez, John. Advance Planning and
    Scheduling Is It as Good as It Sounds? The
    Report on Supply Chain Management. Advanced
    Manufacturing Research, Inc., March, 1998.)

28
APS- the Four-Part Model
AMRs APS Model
Source Advanced Manufacturing Research, Inc.
29
APS- Mathematical Technologies
  • Linear Programming
  • Genetic Algorithms
  • Heuristics
  • Constraint Based Programming (CBP)
  • Source Shires, Nigel, (2005). Optimization
    Techniques and Their Application to Production
    Scheduling , White Paper, Preactor
    International, published on website
    http//www.preactor.com/whitepapers.asp.

30
APS-APS/ERP Integration
The comprehensive nature of todays APS
algorithms drives the need for copious amounts of
data--data that typically reside in an ERP
system. This means that attaining the full
benefits of APS is largely predicted on how well
it is integrated with ERP. When done well, both
systems benefit. Source Musselman, K., and
Uzsoy, R. (2001), Advanced Planning and
Scheduling for Manufacturing, in Handbook of
Industrial Engineering, 3rd Ed., G. Salvendy,
Eds., John Wiley Sons, New York.
31
APS/ERP Integration
APS/ERP Integration
Source Musselman, K., and Uzsoy, R. (2001),
Advanced Planning and Scheduling for
Manufacturing, in Handbook of Industrial
Engineering, 3rd Ed., G. Salvendy, Eds., John
Wiley Sons, New York.
32
APS- Software Providers
  • Preactor
  • SAP - Advanced Planner and Optimizer (APO)
  • Oracle - APS
  • Manugistics
  • i2

33
APS-Preactor APS Screenshot
34
APS-SAP-APO Screenshot
35
Theory of Constraints (TOC)-Introduction
  • The theory was first described by Israels
    physicist Dr. Eliyahu M. Goldratt in his book The
    Goal as a way of managing the business to
    increase profits in 1980s .

TOC is a proven method that can be used by
existing personnel to increase throughput
(sales), reliability, and quality while
decreasing inventory, WIP, late deliveries, and
overtime. Successful organizations also adopt
TOC to help make tactical strategic decisions
for continuous improvement.
36
TOC-Introduction
  • The Theory of Constraints is based on the
    premise that
  • Every real system, such as a business, must have
    within it at least one constraint. If this were
    not the case then the system could produce
    unlimited amounts of whatever it was striving
    for, profit in the case of a business..

  • Dr Eli Goldratt

37
TOC-Drum Buffer Rope
buffer
rope
drum
  • Drum Buffer Rope (DBR) is a planning and
    scheduling solution derived from the Theory of
    Constraints (TOC).
  • The fundamental assumption of DBR is that within
    any plant there is one or a limited number of
    scarce resources which control the overall output
    of that plant. This is the drum, which sets
    the pace for all other resources.
  • In order to maximize the output of the system,
    planning and execution behaviors are focused on
    exploiting the drum, protecting it against
    disruption through the use of time buffers, and
    synchronizing or subordinating all other
    resources and decisions to the activity of the
    drum through a mechanism that is akin to a
    rope.

38
TOC-the Steps for Implementation
  • Step 1 Identify the system's constraint(s)
  • Step 2 Decide how to exploit the systems
    constraint(s)
  • Step 3 Subordinate everything else to the above
    decision
  • Step 4 Elevate the systems constraint(s)
  • Step 5 If in the previous step, a constraint has
    been broken go back to step 1, but
    do not allow inertia to become the systems
    constraint

39
TOC- Types of Constraint
  • A constraint is anything in an organization that
    limits it from moving toward or achieving its
    goal.
  • There are two basic types of constraints
    physical constraints and non-physical
    constraints.
  • A physical constraint is something like the
    physical capacity of a machine.
  • A non-physical constraint might be something
    like demand for a product, a corporate procedure,
    or an individual's paradigm for looking at the
    world.
  • THE MARKET
  • CAPACITY
  • RESOURCES
  • SUPPLIERS
  • FINANCE
  • KNOWLEDGE OR COMPETENCE
  • POLICY

40
TOC- Applications
  • 1. Production Planning and Scheduling
  • 2. Distribution and Supply Chain
  • 3. Financial Management
  • 4. Marketing
  • 5. Strategic Planning
  • 6. Project Management

41
TOC-the Principles of Applying TOC in Production
Scheduling
  • Factory production rate is production rate of
    bottleneck work center
  • Most of the buffer WIP should be waiting at
    bottleneck
  • Bottleneck implies certain amount of idle time at
    other work stations
  • Important to regulate bottleneck workload other
    work centers should serve the bottleneck, not
    optimize themselves.

42
TOC-Capacity and Bottlenecks in Production
  • Capacity is defined as the available time for
    production (excluding maintenance and other
    downtime)
  • A bottleneck (constraint) is defined as any
    resource whose capacity is less than the demand
    placed upon it
  • A non-bottleneck is a resource whose capacity is
    greater than the demand placed on it
  • A capacity-constrained resource (CCR) is one
    whose utilization is close to capacity and could
    be bottleneck if it is not scheduled carefully

43
TOC- An Example in Semiconductor Manufacturing
  • SLIM (Short Cycle Time and Low Inventory in
    Manufacturing) is a project carried by Prof.
    Leachman at University of California at Berkeley.
  • SLIM is a set of methodologies and scheduling
    applications for managing cycle time in
    semiconductor and its main method is TOC.
  • Between 1996 and 1999, Samsung Electronics Corp.,
    Ltd., implemented SLIM in all its semiconductor
    manufacturing facilities and achieve great
    success
  • During the presentation at the 2001 Franz
    Edelman Award Competition, Yoon-Woo Lee,
    president of Samsungs semiconductor business,
    stated The financial impact of SLIM was
    significant. We increased revenue
  • almost 1 billion dollars through five years
    without any additional capital investment, and
    our global DRAM market share increased from 18
    percent to 22 percent.

44
TOC- An Example in Semiconductor Manufacturing
WIP between photo steps at normal time
Fab Process
The pipe represents the production line, and its
width represents the maximum flow rate or
capacity at various process steps. SEC fabs were
designed so that the photo machines are the
bottlenecks, and other machines have surplus
capacity. Thus the pipe in the figure narrows at
each photo step. When all the machines are up
and the process is in control, the photo
machines are the bottlenecks, and the largest
concentrations of WIP is at those points.
45
TOC- An Example in Semiconductor Manufacturing
WIP between photo steps at disturbance
The case of process or equipment trouble at a
non-photo manufacturing area of the fab is
depicted by a constriction of the pipe at a
non-photo step. If this condition persists, the
WIP at a photo machine can become exhausted. A
buffer is needed, proportional to the risk of
trouble in that layer. For example, if Layer j of
the process experiences more trouble than Layer
j1 the bottleneck step immediately following
Layer j should be awarded a larger buffer than
the bottleneck step following Layer j1.
46
TOC- An Example in Semiconductor Manufacturing
The way to solve the problem
  • The philosophy underlying SLIM is to distribute
    WIP to put the fab in the best position to cope
    with the next disruption. That is, while the
    equipment and process are working well, the fab
    should strive to move as much WIP as possible to
    the photo bottleneck, to be prepared for the next
    disruption.

47
CS-Introduction
  • With the increasing competition in the global
    market, the manufacturing industry has been
    facing the challenge of increasing customer
    value
  • More importantly, quality means ensuring customer
    satisfaction and enhancing customer value to the
    extent that customers are willing to pay for the
    goods and services
  • A well-accepted practice in both academia and
    industry is the exploration of flexibility in
    modern manufacturing systems to provide quick
    response to customers with new products catering
    to a particular spectrum of customer needs
  • The key to success in the highly competitive
    manufacturing enterprise often is the companys
    ability to design, produce, and market
    high-quality products within a short time frame
    and at a price that customers are willing to pay
  • In order to meet these pragmatic and highly
    competitive needs of todays industries, it is
    imperative to promote high-value-added products
    and services
  • Mass customization enhances profitability through
    a synergy of increasing customer-perceived values
    and reducing the costs of production and
    logistics.

48
CS-Introduction
  • Mass customization is producing goods and
    services to meet individual customers needs with
    near mass production efficiency
  • Mass customization is a new paradigm for
    industries to provide products and services that
    best serve customer needs while maintaining
    near-mass production efficiency. Contradicted two
    sides
  • Mass production demonstrates an advantage in
    high-volume production
  • Satisfying each individual customers needs can
    often be translated into higher value, however,
    economically not viable

49
CS-Introduction
Economic Implication of Mass Customization
  • Mass customization is capable of reducing costs
    and lead time by accommodating companies to
    garner economy of scale by repetitions.
  • With flexibility and programmability, companies
    with low to medium production volume can gain an
    edge over competitors by implementing MC
  • Mass customization can potentially develop
    customer loyalty, propel company growth, and
    increase market share by widening the product
    range.

50
CS-Introduction
Technical challenges
  • The essence of mass customization lies in the
    product and service providers ability to
    perceive and capture latent market niches and
    subsequently develop technical capabilities to
    meet the diverse needs of target customers
  • To encapsulate the needs of target customer
    groups means to emulate existing or potential
    competitors in quality, cost, quick response
  • Therefore, the requirements of mass customization
    depend on three aspects time-to-market (quick
    responsiveness), variety (customization), and
    economy of scale (volume production efficiency)
  • Successful mass customization depends on a
    balance of three elements features, cost, and
    schedule.

51
CS-Introduction
Maximizing reusability
  • Maximal amounts of repetition are essential to
    achieve the efficiency of mass production, as
    well as efficiencies in sales, marketing, and
    logistics, which attained through maximizing
    commonality in design, which leads to reusable
    tools, equipment, and expertise in subsequent
    manufacturing
  • Customization emphasizes the differentiation
    among products.
  • An important step toward to this goal is the
    development and proliferation of design
    repositories that are capable of creating various
    customized products
  • Dynamic stability a firm can serve the widest
    range of customers and changing product demands.
  • To achieve mass customization, the synergy of
    commonality and modularity needs to be tackled
    and needs to encompass both the physical and
    process domains of design.

52
CS- Introduction
Product platform
  • The effectiveness of a firms new product
    generation lies in
  • Its ability to create a continuous stream of
    successful new products over an extended period
    of time
  • The attractiveness of these products to the
    target market niches
  • The essence of mass customization is to maximize
    such a match of internal capabilities with
    external market needs
  • A product platform is impelled to provide the
    necessary taxonomy for positioning different
    products and the underpinning structure
    describing the interrelationships between various
    products with respect to customer requirements,
    competition information, and fulfillment
    processes
  • This implicates two aspects
  • to represent the entire product portfolio,
    including both existing products and proactively
    anticipated ones, by characterizing various
    perceived customer needs, and
  • to incorporated proven designs, materials, and
    process technologies

53
CS- Introduction
Integrated product life cycle
  • Mass customization starts from understanding
    customers individual requirements and ends with
    a fulfillment process targeting each particular
    customer,
  • The time-to-market can be achieved by telescoping
    lead time
  • Product realization should simultaneously satisfy
    various product life cycle concerns, including
    functionality, cost, schedule, reliability,
    manufacturability, marketability, and
    serviceability, to name but a few
  • The realization of mass customization requires
    not only integration across the product
    development horizon, but also the provision of a
    context-coherent integration of various
    viewpoints of product life cycle.

54
CS-Design for mass customization
  • Design for mass customization (DFMC) aims at
    considering economies of scope and scale at the
    early design stage of the product-realization
    process
  • The main emphasis of DFMC is on elevating the
    current practice of designing individual products
    to designing product families
  • There two basic concepts underpinning DFMC
  • Product family architecture
  • Product family design.

55
CS-Understanding DFMC
56
CS-Product family
  • A product family is a set of products that are
    derived from a common platform
  • A product family targets a certain market
    segment, whereas each product variant is
    developed to address a specific set of customer
    needs of the market segment
  • The interpretation of product families depends on
    different perspectives.

57
CS-Modularity and commonality
  • There two basic issues associated with product
    families modularity and commonality
  • Modularity tries to separate a system into
    independent parts or modules that can be treated
    as logical units
  • Decomposition is a major concern in modularity
    analysis
  • Modularity is achieved from multiple viewpoints,
    including functionality, solution technologies,
    and physical structures
  • There are three types of modularity involved in
    product realization functional modularity,
    technical modularity, and physical modularity
  • The interaction between modules is important in
    characterizing modularity.
  • As for functional modularity, the interaction is
    exhibited by the relevance of functional features
    (FFs) across different customer groups

58
CS-Modularity and commonality (Continued)
  • The commonality reveals the difference of the
    architecture of product families from the
    architecture of a single product
  • Corresponding to the three types of modularity,
    there are three types of commonality in
    accordance with functional, design, and process
    views
  • Functional commonality manifests itself through
    functional classification, that is, grouping
    similar customer requirements into one class,
    where similarity is measured by the Euclidean
    distance among FF instances
  • A class of products is described by modularity
    and product variants differentiate according to
    the commonality among module instances.

59
CS-A comparison of modularity and commonality
Issues Modularity Commonality
Focused objects Type (class) Instances (members)
Characteristic of measure Interaction Similarity
Analysis method Decomposition Clustering
Product differentiation Product structure Product variants
Integration/relation Class-member relationship Class-member relationship
60
CS-Product variety
  • Product variety is defined as the diversity of
    products that a manufacturing enterprise provides
    to the marketplace
  • Two types of variety can be observed functional
    variety and technical variety
  • Functional variety is used broadly to mean any
    differentiation in the attributes related to a
    products functionality from which the customer
    could derive certain benefits
  • Technical variety refers to diverse technologies,
    design methods, manufacturing processes,
    components and/or assemblies, and so on that are
    necessary to achieve specific functionality of a
    product required by the customer. It may be
    invisible to customers
  • While functional variety is mostly related to
    customer satisfaction from the marketing/sales
    perspective, technical variety usually involves
    manufacturability and costs from the engineering
    perspective.

61
CS-Product variety (Continued)
  • These two types of variety result in two
    different variety design strategies functional
    variety strategy and design for functional
    variety strategy
  • Since functional variety directly affects
    customer satisfaction, this type of variety
    should be encouraged in product development
  • A design for functional variety strategy aims
    at increasing functional variety and manifests
    itself through vast research in the business
    community, such as product line structuring,
    equilibrium pricing, and product positioning
  • A design for technical variety tries to reduce
    technical variety so as to gain cost advantages.

62
CS-Variety Leverage Handling Variety for Mass
Customization
63
CS-Product family architecture
  • A well-planned product family architecture (PFA)
    provides a generic umbrella for capturing and
    utilizing commonality, within each new product
    instantiated and extends so as to anchor future
    designs to a common product line structure.

64
CS-PFA and Its Relationships with Market Segments
65
CS-Composition of PFA
  • The PFA consists of three elements the common
    base, the differentiation enabler, and the
    configuration mechanism
  • Common bases (CBs) are the shared elements among
    different products in a product family
  • Differentiation enablers (DEs) are basic elements
    making products different from one another. They
    are the source of variety within a product
    family
  • Configuration mechanisms (CMs) define the rules
    and means of deriving product variants. Three
    types of configuration mechanisms can be
    identified selection constraints, include
    conditions, and variety generation.

66
CS-Composition of PFA (Continued)
  • Selection constraints specify restrictions on
    optional features because certain combinations of
    options are not allowed or feasible or, on the
    contrary, are mandatory
  • Include conditions are concerned with the
    determination of alternative variants for each
    differentiation enabler. The include condition of
    a variant defines the condition under which the
    variant should be used or not used with respect
    to achieving the required product
    characteristics
  • Variety generation refers to the way in which the
    distinctiveness of product features can be
    created. It focuses on the engineering
    realization of custom products in the form of
    product structures.

67
CS-Basic Methods of Variety Generation
68
CS-Synchronization of multiple views
  • The strategy is to employ a generic, unified
    representation and to use its fragments for
    different purposes, rather than to maintain
    consistency among multiple representations
    through transformation of different product data
    models to standard ones.

69
CS-Representing Multiple Views of Product Family
within a Single Context
70
CS-Product family design
  • Under the umbrella of PFA, product family design
    manifests itself through the derivation processes
    of product variants based on PFA constructs.

71
PFA-Based Product Family Design Variant
Derivation through GPS Instantiation
72
CS- PFA-Based Product Family Design Variant
Derivation through GPS Instantiation
73
CS- Manufacturing and production planning
  • Competition for mass customization manufacturing
    is focused on the flexibility and responsiveness
    in order to satisfy dynamic changes of global
    markets. The future major trends are
  • A major part of manufacturing will gradually
    shift from mass production to the manufacturing
    of semi-customized or customized products to meet
    increasingly diverse demands
  • The made-in-house mindset will gradually shift
    to distributed locations, and various entities
    will team up with others to utilize special
    capabilities at different locations to speed up
    product development, reduce risk, and penetrate
    local markets
  • Centralized control of various entities with
    different objectives, locations, and cultures is
    almost out of the question now. control systems
    to enable effective coordination among
    distributed entities have become critical to
    modern manufacturing systems.

74
CS-Managing variety in production planning
  • Major challenge of mass customization production
    planning results from the increase of variety
  • Facing such a variety dilemma, many companies try
    to satisfy demands from their customers through
    engineer-to-order, make-to-order, or
    assembly-to-order production systems
  • The traditional approach to variant handling is
    to treat every variant as a separate product by
    specifying a unique BOM for each variant. This
    works with a low number of variants, but not when
    customers are granted a high degree of freedom in
    specifying products. The problem is that a large
    number of BOM structures will occur in mass
    customization production
  • To overcome these limitations, a generic BOM
    (GBOM) concept has been developed.
  • The GBOM provides a means of describing, with a
    limited amount of data, a large number of
    variants within a product family,while leaving
    the product structure unimpaired. The structure
    has three aspects

75
CS-A Generic Structure for Characterizing Variety
76
CS-The generic variety structure for souvenir
clocks
Structure items Ii Variety parameter Pj Variety instance Vj
3/hands Setting type Two-hand setting, three-hand setting
3/hands Color White, Grey, etc.
3/hands Size Large, medium, small
3/dial pattern Logo, mosic, scenery, customized photo, etc.
3/dial Size Large, medium, small
4/transmission Alarm Yes, no
4/core Alarm Yes, no
3/base Shape Round, rectangular, hexagonal
3/base Material Acrylic, aluminum, etc.
3/base Color Transparent, red, etc.
3/front plate Shape Rectangular,round, rhombus
3/front plate Material Acrylic, aluminum, etc.
3/front plate Color Transparent, red, etc.
1/label sticker Pattern HKUST, signature, etc.
1/paper box Type Ordinary, deluxe, etc.
77
CS-The generic variety structure for souvenir
clocks (continued)
  • To understand the generic concept underlying
    such a variety representation, two fundamental
    issues need to be highlighted
  • Generic item
  • Indirect identification.

78
CS-Coordination in manufacturing resource
allocation
  • Challenges of manufacturing resource allocation
    for mass customization include
  • The number of product variety flowing through the
    manufacturing system is approaching an
    astronomical scale
  • Production forecasting for each line item and its
    patterns is not often available
  • Systems must be capable of rapid response to
    market fluctuation
  • The system should be easy for reconfiguration
    ---- ideally, one set of codes employed across
    different agents
  • The addition and removal of resources or jobs can
    be done with little change of scheduling systems.

79
CS-Major considerations of scheduling for
resource allocation
  • Decompose large, complex scheduling problem into
    smaller, disjointed allocation problems
  • Decentralize resource access, allocation, and
    control mechanisms
  • Design a reliable, fault-tolerant, and robust
    allocation mechanism
  • Design scalable architectures for resource access
    in a complex system and provide a plug-and-play
    resource environment such that resource providers
    and consumers can enter or depart from the market
    freely
  • Provide guarantees to customers and applications
    on performance criteria.

80
CS-A Market Structure for Collaborative Scheduling
81
CS-A Market Structure for Collaborative
Scheduling (Continued)
  • The satisfaction of multiple criteria, such as
    costs and responsiveness, cannot be achieved
    using solely a set of dispatching rules
  • A price mechanism should be constructed to serve
    as an invisible hand to guide the coordination in
    balancing diverse requirements and maximizing
    performance in a dynamic environment.

82
CS-The Price Mechanism of a Market Model
83
CS-Message-Based Bidding and Dynamic Control
84
CS-High-variety shop-floor control
  • The requirements of the new control systems
    include re-configurability, decomposability, and
    scalability to achieve make-to-order with very
    short response time

85
Chapter 9 Advancement in PPC
  • End !
Write a Comment
User Comments (0)
About PowerShow.com