IENG 471 - Lecture 04 - 3 - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

IENG 471 - Lecture 04 - 3

Description:

Title: IENG 471 Lecture 04 - Schedule Design Subject: Part 3 - Ideal Machine Assignment to end Author: D.H. Jensen Last modified by: Jensen, Dean H. – PowerPoint PPT presentation

Number of Views:148
Avg rating:3.0/5.0
Slides: 21
Provided by: DH5
Category:
Tags: ieng | lecture | machine | time

less

Transcript and Presenter's Notes

Title: IENG 471 - Lecture 04 - 3


1
IENG 471 - Lecture 04 - 3
  • Schedule Design
  • The Sequels Sequel

2
Agenda
  • Assignments
  • Schedule Design Part 3
  • Operator/Machine Assignments
  • Ideal Assignment
  • Total Cycle Time
  • Operation Times
  • Operator Idle Time
  • Machine Idle Time
  • Estimating Cost per Unit
  • Questions Issues

3
Assignments
  • Current Assignment
  • HW (HW 3) See Assignment Link
  • required input for each of the workstations
  • equipment necessary for each machine
  • steady state cycle time for each machine
  • ideal machine assignment for each machine
  • compute the idle time
  • unit cost at each workstation
  • total cost per good unit
  • square footage for each workstation and the total
    space required
  • We will use class time next period to work this
    problem
  • So sit with the people that you want to work with
    on this assignment!

4
Ex Injection Mold Rubber Feet
  • We obtain one set of feet per cycle
  • Machine time is 35 s (steady state) after the
    operator starts the process
  • At the start of each cycle, the operator will
    spend 5 s unloading moldings from the machine
    and spraying release agent on the mold halves
    before starting a machine cycle
  • During automatic injection cycle, operator trims
    feet (15 s) and feeds re-grind virgin material
    into machine hopper (10 s)

5
Ideal Machine Assignment
  • Neglects idle time
  • Where
  • a concurrent activity time (both op mach tied
    up)
  • b independent operator activity time
  • t independent machine activity time

6
Cycle Time
  • Cycle time (Tc)
  • Where
  • a concurrent activity time (both op mach tied
    up)
  • b independent operator activity time
  • t independent machine activity time
  • m number of identical machines assigned to op.
  • n ideal number of identical machines assigned
    to op.

7
Idle Machine Time
  • Idle time for machine (Im)
  • Where
  • a concurrent activity time (both op mach tied
    up)
  • b independent operator activity time
  • t independent machine activity time
  • m number of identical machines assigned to op.
  • n ideal number of identical machines assigned
    to op.

8
Idle Operator Time
  • Idle time for operator (Io)
  • Where
  • a concurrent activity time (both op mach tied
    up)
  • b independent operator activity time
  • t independent machine activity time
  • m number of identical machines assigned to op.
  • n ideal number of identical machines assigned
    to op.

9
Total Cost per Unit
  • Based on assigning m machines per operator, total
    cost (TC(m)) is
  • Where
  • Co cost per operator-hour
  • Cm cost per machine-hour
  • a concurrent activity time (both operator
    machine tied up)
  • b independent operator activity time
  • t independent machine activity time
  • m number of identical machines assigned to
    operator
  • n ideal number of identical machines
    assigned to operator

Add this to the material cost total from the BOM!
10
Idle Costing Example (cont.)
  • Assume t 35s
  • Case A Operator is assigned 1 machine
  • Case B Operator is assigned 2 machines
  • Case C Operator is assigned 1.3 machines

11
Example Ideal Machine Assign.
  • Neglecting idle time
  • Where
  • a 5s (load/unload)
  • b 15s (trimming) 10s (feeding) 25s
  • t 40s (cycle time) 5s (load/unload) 35s

12
Cycle Time 1 Machine/Operator
  • Cycle time (Tc)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 1
  • n 1.3

13
Cycle Time 2 Machines/Operator
  • Cycle time (Tc)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 2
  • n 1.3

14
Cycle Time 1.3 Machines/Operator
  • Cycle time (Tc)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 1.3
  • n 1.3

15
Idle Machine Time 1 Mach/Op
  • Idle time for machine (Im)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 1
  • n 1.3

Im faster than one machine, so the machine is
always busy!
M1
16
Idle Machine Time 2 Mach/Op
  • Idle time for machine (Im)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 2
  • n 1.3

Im slower than two machines, so now Im always
busy!
17
Idle Machine Time 1.3 Mach/Op
  • Idle time for machine (Im)
  • Where
  • a 5s
  • b 25s
  • t 35s
  • m 1
  • n 1.3

4 machines 3 operators
1.3
M1
M2
M4
M3
3 of us are just as fast as 4 machines, so
everything is always busy!
18
Idle Costing Example (cont.)
  • Assume the Following Costs
  • Operator Wage 15/hr
  • Operator Overhead 40
  • Electricity Cost/Machine 6/hr
  • Maintenance Cost/Machine 1/hr
  • Computing the Cost per Unit Components
  • Co Cost per Operator-Hour
  • 15/hr (.40)(15/hr) 21/hr
  • Cm Cost per Machine-Hour
  • 6/hr 1/hr 7/hr

19
Total Cost per Unit
  • Based on assigning 1 machine per operator
  • Where
  • Co cost per operator-hour
  • Cm cost per machine-hour

20
Total Cost per Unit
  • Based on assigning 2 machines per operator
  • Where
  • Co cost per operator-hour
  • Cm cost per machine-hour

21
Total Cost per Unit
  • Based on assigning 1.3 machines per operator
  • Where
  • Co cost per operator-hour
  • Cm cost per machine-hour
Write a Comment
User Comments (0)
About PowerShow.com