Title: IENG 471 - Lecture 04 - 3
1IENG 471 - Lecture 04 - 3
- Schedule Design
- The Sequels Sequel
2Agenda
- Assignments
- Schedule Design Part 3
- Operator/Machine Assignments
- Ideal Assignment
- Total Cycle Time
- Operation Times
- Operator Idle Time
- Machine Idle Time
- Estimating Cost per Unit
- Questions Issues
3Assignments
- Current Assignment
- HW (HW 3) See Assignment Link
- required input for each of the workstations
- equipment necessary for each machine
- steady state cycle time for each machine
- ideal machine assignment for each machine
- compute the idle time
- unit cost at each workstation
- total cost per good unit
- square footage for each workstation and the total
space required - We will use class time next period to work this
problem - So sit with the people that you want to work with
on this assignment!
4Ex Injection Mold Rubber Feet
- We obtain one set of feet per cycle
- Machine time is 35 s (steady state) after the
operator starts the process - At the start of each cycle, the operator will
spend 5 s unloading moldings from the machine
and spraying release agent on the mold halves
before starting a machine cycle - During automatic injection cycle, operator trims
feet (15 s) and feeds re-grind virgin material
into machine hopper (10 s)
5Ideal Machine Assignment
- Neglects idle time
- Where
- a concurrent activity time (both op mach tied
up) - b independent operator activity time
- t independent machine activity time
6Cycle Time
- Cycle time (Tc)
- Where
- a concurrent activity time (both op mach tied
up) - b independent operator activity time
- t independent machine activity time
- m number of identical machines assigned to op.
- n ideal number of identical machines assigned
to op.
7Idle Machine Time
- Idle time for machine (Im)
- Where
- a concurrent activity time (both op mach tied
up) - b independent operator activity time
- t independent machine activity time
- m number of identical machines assigned to op.
- n ideal number of identical machines assigned
to op.
8Idle Operator Time
- Idle time for operator (Io)
- Where
- a concurrent activity time (both op mach tied
up) - b independent operator activity time
- t independent machine activity time
- m number of identical machines assigned to op.
- n ideal number of identical machines assigned
to op.
9Total Cost per Unit
- Based on assigning m machines per operator, total
cost (TC(m)) is - Where
- Co cost per operator-hour
- Cm cost per machine-hour
- a concurrent activity time (both operator
machine tied up) - b independent operator activity time
- t independent machine activity time
- m number of identical machines assigned to
operator - n ideal number of identical machines
assigned to operator
Add this to the material cost total from the BOM!
10Idle Costing Example (cont.)
- Assume t 35s
- Case A Operator is assigned 1 machine
- Case B Operator is assigned 2 machines
- Case C Operator is assigned 1.3 machines
11Example Ideal Machine Assign.
- Neglecting idle time
- Where
- a 5s (load/unload)
- b 15s (trimming) 10s (feeding) 25s
- t 40s (cycle time) 5s (load/unload) 35s
12Cycle Time 1 Machine/Operator
- Cycle time (Tc)
- Where
- a 5s
- b 25s
- t 35s
- m 1
- n 1.3
13Cycle Time 2 Machines/Operator
- Cycle time (Tc)
- Where
- a 5s
- b 25s
- t 35s
- m 2
- n 1.3
14Cycle Time 1.3 Machines/Operator
- Cycle time (Tc)
- Where
- a 5s
- b 25s
- t 35s
- m 1.3
- n 1.3
15Idle Machine Time 1 Mach/Op
- Idle time for machine (Im)
- Where
- a 5s
- b 25s
- t 35s
- m 1
- n 1.3
Im faster than one machine, so the machine is
always busy!
M1
16Idle Machine Time 2 Mach/Op
- Idle time for machine (Im)
- Where
- a 5s
- b 25s
- t 35s
- m 2
- n 1.3
Im slower than two machines, so now Im always
busy!
17Idle Machine Time 1.3 Mach/Op
- Idle time for machine (Im)
- Where
- a 5s
- b 25s
- t 35s
- m 1
- n 1.3
4 machines 3 operators
1.3
M1
M2
M4
M3
3 of us are just as fast as 4 machines, so
everything is always busy!
18Idle Costing Example (cont.)
- Assume the Following Costs
- Operator Wage 15/hr
- Operator Overhead 40
- Electricity Cost/Machine 6/hr
- Maintenance Cost/Machine 1/hr
- Computing the Cost per Unit Components
- Co Cost per Operator-Hour
- 15/hr (.40)(15/hr) 21/hr
- Cm Cost per Machine-Hour
- 6/hr 1/hr 7/hr
19Total Cost per Unit
- Based on assigning 1 machine per operator
- Where
- Co cost per operator-hour
- Cm cost per machine-hour
20Total Cost per Unit
- Based on assigning 2 machines per operator
- Where
- Co cost per operator-hour
- Cm cost per machine-hour
21Total Cost per Unit
- Based on assigning 1.3 machines per operator
- Where
- Co cost per operator-hour
- Cm cost per machine-hour