Title: NSF Division of Astronomical Sciences
1NSF Division of Astronomical Sciences
- AAAC
- October 15-16, 2009
- Craig Foltz
2Summary
- AST Budget Overview
- Retrospective look
- FY 2009 ARRA
- Looking forward
- Status of Senior Review implementation
- Changes in AST
- Recent Activities and Actions
3MPS Budget trends
4MPS budget trends (cont.)
5AST Budget trends
10 year doubling
6FY 2009 Budget Plan FY 2010 Budget Request
7FY2009 spending(including American Reinvestment
and Recovery Act, ARRA)
8ARRA Funding
- As shown, roughly 2/3 for grants and 1/3 for
overdue facility infrastructure improvements and
preconstruction activities. - Quite strong restrictions some suggested
spending not permitted funds bring additional
reporting requirements. - Success rate in research grants program (AAG)
rose from last years 21 to a healthy 36. - Risk exaggerated even if all awards were 3 years
(they werent) and all of them came back in
exactly 3 years (which they wont), only a 15
increase, which we have seen and handled before. - Yes, the funding rate will not be this high in
future. - Increases for CAREER (low success rate anyway)
and Graduate Research Fellowships. - Infrastructure improvements long overdue but the
problem persists.
9FY 2010 Budget Request
- AST Total 250.8 M (increase of 10 over FY
2009) - Facilities 141 M (56)
- Gemini - 19.1 M
- NAIC - 8.4 M
- NOAO - 27.5 M
- NSO - 9.1 M
- NRAO - 67.1 M
- UROs - 10 M
- Research and Education Grants 110 M total (44)
- Roughly 45M for AAG 37 M for instrumentation
- 25 M for special programs (AAPF, CAREER, REU,
Cyberinfrastructure, NSF-wide, etc)
10Budget Projections?
- Administration, congressional support for NSF
budget doubling over 10 years. - How will AST fare in this growth?
- Administration priorities not well aligned with
AST - Green energy
- Climate change
- Short term economic recovery
- But historically AST has tracked NSF RRA quite
well -
11AST Budget trends
NSF projection
12Status of Senior Review Recommendations
- VLBA - non-AST funding for 50 of VLBA operations
or closure. - NRAO pursuing partnerships, prospects look very
good - GONG - non-AST support of operations or
termination, one year after successful SDO
commissioning. - NSO pursuing partnership with US Air Force
Weather Agency - Carry out cost reviews of all facilities
- Completed by external firm, report in hand, will
be working with observatories to institute
(minor) cost savings over next years - NAIC (next slide)
13National Astronomy and Ionosphere Center (NAIC)
- Recommendation to ramp budget down to 8M by
2010, 4M in following years. Seek non-AST
support to maintain operations or closure - NSF Atmospheric Sciences increasing contribution
to operations - NSF (AST, ATM) will compete the next cooperative
agreement for the management and operation of
NAIC. - Recommendations of the 2006 AST Senior Review are
being factored into planning. - NSF expects to issue a detailed program
solicitation in fall 2009, with full proposals
due six months following publication. - Expected to lead to the award of a single,
five-year cooperative agreement for the
management and operation of NAIC for 2011-2015.
14Changes in AST
- FY2009 was a remarkably unusual year.
- The Division of Astronomical Sciences has been
without a full-time Division Director for 18
months. - We have been without an Deputy Division Director
for 4 months. - We have an open permanent PO position.
- We have a rotator leaving this month, a year
before anticipated. - Since there was no back-fill, we will soon be
short 3-4 Program Officers. The added strain of
ARRA was clearly felt. - Interviews for DD and DDD are later this month
but the most optimistic start is January 2010,
probably significantly later. - Permanent PO hiring has closed IPA is now open
(until November 20). - New management can change the divisions
direction. - Limited staff lack the leisure for planning.
15Recent Activities and Actions
- NRAO Cooperative Agreement with AUI extended for
five years. - NOAO Cooperative Agreement with AURA extended for
54 months. - NSO now has its own Cooperative Agreement, also
with AURA for 54 months. - Gemini partnership in flux. May have budgetary
consequences. - MRI R2 and ARI proposals (both ARRA) under
review. - ATST FDR and NSB action.
16(No Transcript)
17NSB Approval of ATST Construction
- On August 6, 2009, the National Science Board
approved an award to be derived from 146,000,000
of ARRA funds and 151,928,000 of appropriated
MREFC funds, in accordance with the following
resolution - RESOLVED, that the National Science Board
authorizes the Director at his discretion to
issue an eight-year award to the Association of
Universities for Research in Astronomy for a
not-to-exceed amount of 297,928,000 for the
construction of the Advanced Technology Solar
Telescope. This award will be contingent upon
the publication of a record of decision
authorizing the commencement of construction.
18Construction Cost Estimate
FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017
FY 2009 Appropriations 7,000 - - - - - - -
ARRA of 2009 146,000 - - - - - - -
Proposed Funding 10,000 20,000 20,000 20,000 20,000 20,000 20,000 14,928
Total 163,000 20,000 20,000 20,000 20,000 20,000 20,000 14,928
Cumulative 163,000 183,000 203,000 223,000 243,000 263,000 283,000 297,928
19Construction Cost Estimate (cont.)
- Costs are in spent-year dollars calculated with
current OMB escalators. - 32.9 contingency based on Monte Carlo
simulations for 95 confidence. - Includes effect of mitigation of impact on
Hawaiian Dark-Rumped Petrel, Buy American
costs, management of National Park Special Use
Permit, etc. - Does not include costs associated with cultural
mitigation.
20ATST Schedule Overview
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Technology Development
Concept Design
CDUP
Site EIS Process
FDR/Baseline Review
Site Construction
SDRs
NSF Panel Review
IT C
Initial Operations
December 4, 2008
AURA SOVC
Feb 27, 2007
AURA SOC
20
NSF PDR
20
21Environmental and Cultural Compliance
- Comprehensive site selection was based on site
characteristics derived from flow-down from
science drivers. 72 sites studied. Final site
selected at Haleakala High Altitude Observatory
(U. Hawaii), Maui. Haleakala is the only site
that meets the requirements. - Environmental Review and Permitting process for
site - Final EIS submitted to EPA on July 24, 2009
published on July 31. - EIS is 3116 pages long cost gt3M.
- Application for building permit (state of Hawaii
process) underway University of Hawaii leads. - More than thirty National Historic Preservation
Act Section 106 consultations resulted in draft
programmatic agreement currently under
negotiation. - Record of Decision in development. This will
complete compliance requirements.
22The Geographical Context
Puu Ulaula
ATST Alternate Site
Maui
Puu Kolekole
Haleakala
Mauna Kea
ATST Primary Site
Hawaii
ATST Site
23ATST atop Haleakala, Maui