Title: EP-3 Recovery
1EP-3 Recovery
- Mr. Ross Higa
- HQ PACAF/CECI
2Background
- CE Mission Document pavement degradation from
AN-124 traffic - US responsible for pavement damage
- Chinese tried, but could not run up the bill
- Airfield designed for fighter aircraft
- Narrow taxiways, small aprons
- Limited pavement bearing strength
- AN-124 has higher damage potential than C-5
- Five AN-124 flights (first and last were
heaviest) - Cargo weight and fuel strictly controlled to
avoid damage - First AN-124 arrived 16 Jun 01 to start recovery
operations - completed 3 Jul 01
3Logistics and Security
- Lodged at Gloria Resort Hotel in Sanya
- U.S. manager assisted in logistical support
- One hour bus ride to/from Lingshui Air Base
- Left hotel 0630, returned 1830
- Operations kept low key
- Minimal news coverage
- Photographers and reporters kept away from hotel
and base - Police stationed along route to Lingshui
- Exception Numerous guests/photographers on base
during fuselage loading
4Lingshui (Naval) Air Base, Hainan Island,
People's Republic of China
5EP-3 and AN-124
6Crew members guided the AN-124 on narrow taxiways
and through tight turns
7Kneeling AN -124 - Load bearing points on the
pavement were closely monitored
8The airfield already had existing defects
9Working Conditions
- Lockheed Martin was well prepared
- Chartered Gulfstream IV on standby at Sanya
Airport for evacuation - Physician on team - local hospitals inadequate
- Temperatures reached 107 deg F with high humidity
- Heat stress encountered early on
- Administered medication as needed
- Daily safety meetings - no injuries incurred
- Local contracts for work trailers, water,
transportation, meals, toilets, generator, etc. - Cell phones with international capability
10People's Liberation Army
- PLA Navy monitored operations closely
- Continuous photography and video taping of work
and people - U.S. workers restricted from crossing rope
barriers - Routine review of photos and video taken by U.S.
- End of day meetings held to recap day's events
and resolve issues - Key project officers from Beijing not Lingshui
- Non-threatening, but many "home turf" rules
11(No Transcript)
12(No Transcript)
13Three jack stands supported the aircraft during
underside disassembly work
14Blowers vented residual fuel before cutting
operations could begin
15A safety line was installed for topside work
16Flaps, ailerons and leading edges were salvaged
17Tail section was cut off the fuselage
18Key components were salvaged
19Four engines were removed in one day
20(No Transcript)
21Gas powered saws were used to cut and remove the
wings in sections
22Scrapped parts were also taken to Kadena on the
AN-124
23Main and nose gears were removed when rain halted
wing cutting operations
24A specially made trailer was jacked up to support
the aircraft
25EP-3 rested solely on the raised trailer after
the jack stands were removed
26Interior pipes and cables were pre-cut to
facilitate removal of wing sections
27Nacelles were salvaged
28The AN-124 was "cubed out" on almost every return
flight
29Lockheed and Russian crews "busted butts" to load
same-day turnaround flights
30Bridge cranes were used to load from the rear
31A centerline marker was laid out to help align
the AN-124 to the EP-3
32The AN-124 hit the mark perfectly
33The AN-124 used portable extension ramps to
reduce the incline
34Steel cables from the cargo bay were attached to
the trailer
35Winches pulled the fuselage into the cargo bay
36The wide wheels and narrow ramps left no room for
error
37The fuselage and trailer cleared by a few inches
38(No Transcript)
39(No Transcript)
40The portable ramps were disassembled and loaded
onto the AN-124
41The Russian crew
42After a refueling stop in the Philippines and
crew rest in Hawaii, the fuselage was welcomed
home at Dobbins ARB, GA (home of Lockheed Martin
Aeronautical Systems Co.)
43Additional Information
- Additional Information and photos can be found on
the PACOM website at - http//www.pacom.mil/ep3photos.htm
- http//www.pacom.mil/ep3.htm