Title: AASHTO Subcommittee on Construction Contract Administration Section Panel on Unbalanced Bidding Procedures
1AASHTO Subcommittee on ConstructionContract
Administration SectionPanel on Unbalanced
Bidding Procedures
- Jerry Yakowenko (FHWA Headquarters)Dean Word
(Dean Word Construction)Brenda OBrien (Michigan
DOT)Byron Coburn (A. Morton Thomas Associates,
Inc representing Virginia DOT)
2Background
- Bid tabulation and bid reviews are an important
part of ensuring a transparent, fair and
competitive procurement system. - While the frequency of unbalanced bids is
relatively rare, unbalanced bidding reviews are
an important step in the letting and award
process.
3FHWA Regulatory Policy
- Definitions (23 CFR 635.102)
- Mathematically unbalanced bid means a bid
containing lump sum or unit bid items which do
not reflect reasonable actual costs plus a
reasonable proportionate share of the bidder's
anticipated profit, overhead costs, and other
indirect costs. - Materially unbalanced bid means a bid which
generates a reasonable doubt that award to the
bidder submitting a mathematically unbalanced bid
will result in the lowest ultimate cost to the
Federal Government.
4FHWA Regulatory Policy (continued)
- 23 CFR 635.114 Award of contract and
concurrence in award. - (c) Following the opening of bids, the STD
shall examine the unit bid prices of the apparent
low bid for reasonable conformance with the
engineer's estimated prices. A bid with extreme
variations from the engineer's estimate, or where
obvious unbalancing of unit prices has occurred,
shall be thoroughly evaluated. - (d) Where obvious unbalanced bid items exist, the
STD's decision to award or reject a bid shall be
supported by written justification. A bid found
to be mathematically unbalanced, but not found to
be materially unbalanced, may be awarded. - (e) When a low bid is determined to be both
mathematically and materially unbalanced, the
Division Administrator will take appropriate
steps to protect the Federal interest. This
action may be concurrence in a STD decision not
to award the contract. If, however, the STD
decides to proceed with the award and requests
FHWA concurrence, the Division Administrator's
action may range from nonconcurrence to
concurrence with contingency conditions limiting
Federal participation.
52004 AASHTO SOC CA Section Survey
- 1) Does your state have written procedures for
determining when a bid is materially unbalanced? - 2) In the past three years, how many times has a
bid been declared to be materially unbalanced? - 3) What was the disposition of these
circumstances?
62004 Survey (continued)
- 27 State DOT responses were received by the FHWA
Office of Program Administration. - From 2001-2003
- twelve states did not declare a bid to be
materially unbalanced, - eleven states had between 1- 4 materially
unbalanced bids, - two states had 5 10 materially unbalanced bids,
and - two states provided a not applicable response.
- From 2001-2003 states responded to irregular bids
in the following manner - eleven states rejected all bids and readvertised,
- four states indicated that they declared the
irregular bid non-responsive and awarded to the
lowest responsive bidder, and - ten states responded with not applicable reply.
72004 Survey (continued)
- Seven State DOTs (CA, FL, NC, NV, TN, TX and WI)
provided their formal procedures for evaluating
unbalancing. - Florida DOTs procedure includes the use of an
Unbalanced Bid Item program that utilizes a
bell curve distribution to develop a statistical
average unit price for comparison purposes. - TxDOTs procedure analyzes
- unbalanced prices that vary from the estimate
outside a specific range. - utilizes a comparison of the balanced vs.
unbalanced monthly payout rates - calculates monthly payout during the life of the
contract based on an assumed schedule. - Wisconsin DOT Construction and Materials Manual,
Section 2.10.2.1 Unbalanced Bid Analysis, defines
significant item and provides a procedure for
reviewing unbalanced bids http//roadwaystandards
.dot.wi.gov/standards/cmm/210.pdf - Link to the 2004 Survey Summary
- http//construction.transportation.org/Documents/2
004surveyonmateriallyunbalancedbids.pdf
8Caltrans Low Bid vs. EE and Average Number of
Bidders
http//www.dot.ca.gov/hq/esc/oe/download.php?idcp
rchart
9The Contracting Industrys PerspectiveDean Word
(Dean Word Construction)
10A State DOTs Perspective (Michigan)Brenda
OBrien (Michigan DOT)
11Unbalanced Bids Michigan DOT Practices
- AASHTO Subcommittee on Construction
- August 17, 2010
- Brenda OBrien, Michigan Department of
Transportation
12Unbalanced Bids Michigan DOT
- Audit Finding Lacking a documented review of
bids for unbalanced unit prices - Unbalanced Low Bid Management Review Team
(ULBMRT) established April 2009 - Reviews every letting
- Identifies potential materially unbalanced bids
13Unbalanced Bids Michigan DOT
- Project Selection
- All projects over 5 Million
- AND
- Random selection of 1/3 of all projects let
- Screening Criteria
- Line item /- 15 from engineers estimate
- Engineers estimate line item amount of /- 1000
- Secondary screening
- Contractors historical bids for respective line
item
14(No Transcript)
15Bid Item Analysis Check
16Unbalanced Bids Michigan DOT
- First year results
- 21 lettings
- 353 contracts reviewed
- 65 contracts sent for further field review
- 7990 line items reviewed
- No individual bids rejected
- Two letters of clarification
- Two projects pulled, corrected, and re-let
17A State DOTs Perspective (Virginia)Byron
Coburn (A. Morton Thomas Associates, Inc
representing Virginia DOT)
18 Byron Coburn, PE AMT Associate Former
State Construction Engineer August 17, 2010
Unbalanced Bids
19(No Transcript)
20VDOT History
- VDOT has not rejected a bid for being unbalance
in over 10 years. VDOTs methods have to date
overcome the need to reject for unbalance. - VDOT awards between 400 to 600 road work
contracts per year. - Nearly all contracts are unit priced type
contracts. The actual number of units used during
construction multiplied by the unit price is what
the contractor is paid. - However, VDOT does use some lump sum pay items
but there use is limited.
21How VDOT Estimates
- Just prior to receipt of bids, VDOT performs a
rational (real world) estimate. The estimator
puts together a virtual crew, gets quotes on
materials, adds transportation cost, etc
mimicking what a contractor would do. This is
done on all but very simplest of projects. This
Engineers Estimate becomes in essence VDOTs
bid for the project. This is the estimate used
to determine good value. - The low bid should be within 7 of EE to be
considered acceptable. When it is not, VDOT seeks
to know why. Since VA Code allows for negotiation
to bring price within the budget, and is
otherwise silent to the analysis of bids, VDOT
can ask the contractor questions about how he
prepared his bid. - It should be noted that there is no actual
negotiations during this analysis merely
discovery. Therefore, federal regulations are
not violated. The bids are examined primarily for
ultimate value (or materially balance) and are
primarily focused on the bottom line.
22Memorandum of Understanding (MOU)
- If an unusual unit price is detected that
suggests a mathematically unbalanced bid, the
contractor is asked to explain why he priced the
item that way. After meeting with the bidder, the
VDOT estimator may consider the information
gleaned from the contractor to re-price the item,
and again makes a comparison. - If the price is still outside acceptable range,
VDOT usually uses a Memorandum of Understanding
(MOU) to limit exposure to overruns. - A MOU is a supplement to the contract signed by
the contractor and the Department, outlining the
terms of the agreement related to unbalanced
item. Usually the MOU will limit the payment of
the bid unit price to the quantity listed in the
schedule of items. Any additional units
(overruns) are agreed to be supplied at a new
established price that is priced at the current
market price. MOUs are used on about 25 times per
year. - A MOU can also limit the Contractors risk to
underruns if desired.
23Zero or Penny Bids
- VDOT will accept a zero or penny bid as a
legitimate bid if the contractor can explain and
demonstrate why he priced the item that way. The
reason could include that the cost was included
in other related items, the cost is being paid
for on another project, there is no intrinsic
value for that work, the contractors methods
eliminate the need for that work, etc. - Example On a recent Woodrow Wilson Bridge
project, the Contractor bid a penny on traffic
control barrels. He had figured his total traffic
control cost for the project, and it was his
companys practice to covered that cost in his
traffic barrels. He explained that he was
concerned that the quantity shown in the schedule
of items would not actually be used, so he would
not recoup his cost if indeed the barrels
underran. His strategy instead was to added his
traffic control cost to his mobilization and
place no cost on the barrels. VDOT noted this in
the MOU so the contractor could not later claim
that he made a mistake.
24Zero or Penny Bids
- Example The contract calls for allying dust thru
water truck hours. The contractor plans to
control dust with calcium chloride, the cost for
which he places in another item. - Example A contractor is currently working on an
adjacent project that has surplus earthwork. He
bids .01 for borrow on the new project because he
is being fully compensated for disposal on the
current project. This will likely ensure he is
the low bidder.
25Unusually Low Bids
- When the bottom line price is below the EE by
25, and there is a 25 difference between 1st
and 2nd bidders, VDOT will allow the low bidder
to withdraw without penalty if the contractor has
made a mistake. - If the 1st bidder wants to withdraw his bid, the
2nd bid is analyzed in the same fashion. If the
2nd is deemed a good value, VDOT may make award
to the 2nd.
26Rejection of Bids Re-advertisement
- State law gives the agency the right to reject
all bids if deemed in the best interest of the
Commonwealth for any reason other than to
eliminate a particular vendor. - Re-bids in competitive markets usually result in
lower bids with the next advertisement. Last year
VDOT saved about 8 million by re-advertising
projects where bids exceeded the estimate. The
saving is primarily due to identifying the risk
through the discussions with the contractor, and
then mitigating that risk in the second
advertisement.
27(No Transcript)
28Questions?
- Should be directed to
- Don Silies
- State Contract Engineer
- At email address
- Don.Silies_at_VDOT.Virginia.gov