AASHTO Subcommittee on Construction Contract Administration Section Panel on Unbalanced Bidding Procedures

1 / 28
About This Presentation
Title:

AASHTO Subcommittee on Construction Contract Administration Section Panel on Unbalanced Bidding Procedures

Description:

Byron Coburn (A. Morton Thomas & Associates, Inc representing Virginia DOT) * * * * * * * * * * * * In response to the audit finding, the ULBMRT was formed to ... –

Number of Views:158
Avg rating:3.0/5.0
Slides: 29
Provided by: ger114
Category:

less

Transcript and Presenter's Notes

Title: AASHTO Subcommittee on Construction Contract Administration Section Panel on Unbalanced Bidding Procedures


1
AASHTO Subcommittee on ConstructionContract
Administration SectionPanel on Unbalanced
Bidding Procedures
  • Jerry Yakowenko (FHWA Headquarters)Dean Word
    (Dean Word Construction)Brenda OBrien (Michigan
    DOT)Byron Coburn (A. Morton Thomas Associates,
    Inc representing Virginia DOT)

2
Background
  • Bid tabulation and bid reviews are an important
    part of ensuring a transparent, fair and
    competitive procurement system.
  • While the frequency of unbalanced bids is
    relatively rare, unbalanced bidding reviews are
    an important step in the letting and award
    process.

3
FHWA Regulatory Policy
  • Definitions (23 CFR 635.102)
  • Mathematically unbalanced bid means a bid
    containing lump sum or unit bid items which do
    not reflect reasonable actual costs plus a
    reasonable proportionate share of the bidder's
    anticipated profit, overhead costs, and other
    indirect costs.
  • Materially unbalanced bid means a bid which
    generates a reasonable doubt that award to the
    bidder submitting a mathematically unbalanced bid
    will result in the lowest ultimate cost to the
    Federal Government.

4
FHWA Regulatory Policy (continued)
  • 23 CFR 635.114 Award of contract and
    concurrence in award.
  • (c) Following the opening of bids, the STD
    shall examine the unit bid prices of the apparent
    low bid for reasonable conformance with the
    engineer's estimated prices. A bid with extreme
    variations from the engineer's estimate, or where
    obvious unbalancing of unit prices has occurred,
    shall be thoroughly evaluated.
  • (d) Where obvious unbalanced bid items exist, the
    STD's decision to award or reject a bid shall be
    supported by written justification. A bid found
    to be mathematically unbalanced, but not found to
    be materially unbalanced, may be awarded.
  • (e) When a low bid is determined to be both
    mathematically and materially unbalanced, the
    Division Administrator will take appropriate
    steps to protect the Federal interest. This
    action may be concurrence in a STD decision not
    to award the contract. If, however, the STD
    decides to proceed with the award and requests
    FHWA concurrence, the Division Administrator's
    action may range from nonconcurrence to
    concurrence with contingency conditions limiting
    Federal participation.

5
2004 AASHTO SOC CA Section Survey
  • 1) Does your state have written procedures for
    determining when a bid is materially unbalanced?
  • 2) In the past three years, how many times has a
    bid been declared to be materially unbalanced?
  • 3) What was the disposition of these
    circumstances?

6
2004 Survey (continued)
  • 27 State DOT responses were received by the FHWA
    Office of Program Administration.
  • From 2001-2003
  • twelve states did not declare a bid to be
    materially unbalanced,
  • eleven states had between 1- 4 materially
    unbalanced bids,
  • two states had 5 10 materially unbalanced bids,
    and
  • two states provided a not applicable response.
  • From 2001-2003 states responded to irregular bids
    in the following manner
  • eleven states rejected all bids and readvertised,
  • four states indicated that they declared the
    irregular bid non-responsive and awarded to the
    lowest responsive bidder, and
  • ten states responded with not applicable reply.

7
2004 Survey (continued)
  • Seven State DOTs (CA, FL, NC, NV, TN, TX and WI)
    provided their formal procedures for evaluating
    unbalancing.
  • Florida DOTs procedure includes the use of an
    Unbalanced Bid Item program that utilizes a
    bell curve distribution to develop a statistical
    average unit price for comparison purposes.
  • TxDOTs procedure analyzes
  • unbalanced prices that vary from the estimate
    outside a specific range.
  • utilizes a comparison of the balanced vs.
    unbalanced monthly payout rates
  • calculates monthly payout during the life of the
    contract based on an assumed schedule.
  • Wisconsin DOT Construction and Materials Manual,
    Section 2.10.2.1 Unbalanced Bid Analysis, defines
    significant item and provides a procedure for
    reviewing unbalanced bids http//roadwaystandards
    .dot.wi.gov/standards/cmm/210.pdf
  • Link to the 2004 Survey Summary
  • http//construction.transportation.org/Documents/2
    004surveyonmateriallyunbalancedbids.pdf

8
Caltrans Low Bid vs. EE and Average Number of
Bidders
http//www.dot.ca.gov/hq/esc/oe/download.php?idcp
rchart
9
The Contracting Industrys PerspectiveDean Word
(Dean Word Construction)
10
A State DOTs Perspective (Michigan)Brenda
OBrien (Michigan DOT)
11
Unbalanced Bids Michigan DOT Practices
  • AASHTO Subcommittee on Construction
  • August 17, 2010
  • Brenda OBrien, Michigan Department of
    Transportation

12
Unbalanced Bids Michigan DOT
  • Audit Finding Lacking a documented review of
    bids for unbalanced unit prices
  • Unbalanced Low Bid Management Review Team
    (ULBMRT) established April 2009
  • Reviews every letting
  • Identifies potential materially unbalanced bids

13
Unbalanced Bids Michigan DOT
  • Project Selection
  • All projects over 5 Million
  • AND
  • Random selection of 1/3 of all projects let
  • Screening Criteria
  • Line item /- 15 from engineers estimate
  • Engineers estimate line item amount of /- 1000
  • Secondary screening
  • Contractors historical bids for respective line
    item

14
(No Transcript)
15
Bid Item Analysis Check
16
Unbalanced Bids Michigan DOT
  • First year results
  • 21 lettings
  • 353 contracts reviewed
  • 65 contracts sent for further field review
  • 7990 line items reviewed
  • No individual bids rejected
  • Two letters of clarification
  • Two projects pulled, corrected, and re-let

17
A State DOTs Perspective (Virginia)Byron
Coburn (A. Morton Thomas Associates, Inc
representing Virginia DOT)
18
Byron Coburn, PE AMT Associate Former
State Construction Engineer August 17, 2010
Unbalanced Bids
19
(No Transcript)
20
VDOT History
  • VDOT has not rejected a bid for being unbalance
    in over 10 years. VDOTs methods have to date
    overcome the need to reject for unbalance.
  • VDOT awards between 400 to 600 road work
    contracts per year.
  • Nearly all contracts are unit priced type
    contracts. The actual number of units used during
    construction multiplied by the unit price is what
    the contractor is paid.
  • However, VDOT does use some lump sum pay items
    but there use is limited.

21
How VDOT Estimates
  • Just prior to receipt of bids, VDOT performs a
    rational (real world) estimate. The estimator
    puts together a virtual crew, gets quotes on
    materials, adds transportation cost, etc
    mimicking what a contractor would do. This is
    done on all but very simplest of projects. This
    Engineers Estimate becomes in essence VDOTs
    bid for the project. This is the estimate used
    to determine good value.
  • The low bid should be within 7 of EE to be
    considered acceptable. When it is not, VDOT seeks
    to know why. Since VA Code allows for negotiation
    to bring price within the budget, and is
    otherwise silent to the analysis of bids, VDOT
    can ask the contractor questions about how he
    prepared his bid.
  • It should be noted that there is no actual
    negotiations during this analysis merely
    discovery. Therefore, federal regulations are
    not violated. The bids are examined primarily for
    ultimate value (or materially balance) and are
    primarily focused on the bottom line.

22
Memorandum of Understanding (MOU)
  • If an unusual unit price is detected that
    suggests a mathematically unbalanced bid, the
    contractor is asked to explain why he priced the
    item that way. After meeting with the bidder, the
    VDOT estimator may consider the information
    gleaned from the contractor to re-price the item,
    and again makes a comparison.
  • If the price is still outside acceptable range,
    VDOT usually uses a Memorandum of Understanding
    (MOU) to limit exposure to overruns.
  • A MOU is a supplement to the contract signed by
    the contractor and the Department, outlining the
    terms of the agreement related to unbalanced
    item. Usually the MOU will limit the payment of
    the bid unit price to the quantity listed in the
    schedule of items. Any additional units
    (overruns) are agreed to be supplied at a new
    established price that is priced at the current
    market price. MOUs are used on about 25 times per
    year.
  • A MOU can also limit the Contractors risk to
    underruns if desired.

23
Zero or Penny Bids
  • VDOT will accept a zero or penny bid as a
    legitimate bid if the contractor can explain and
    demonstrate why he priced the item that way. The
    reason could include that the cost was included
    in other related items, the cost is being paid
    for on another project, there is no intrinsic
    value for that work, the contractors methods
    eliminate the need for that work, etc.
  • Example On a recent Woodrow Wilson Bridge
    project, the Contractor bid a penny on traffic
    control barrels. He had figured his total traffic
    control cost for the project, and it was his
    companys practice to covered that cost in his
    traffic barrels. He explained that he was
    concerned that the quantity shown in the schedule
    of items would not actually be used, so he would
    not recoup his cost if indeed the barrels
    underran. His strategy instead was to added his
    traffic control cost to his mobilization and
    place no cost on the barrels. VDOT noted this in
    the MOU so the contractor could not later claim
    that he made a mistake.

24
Zero or Penny Bids
  • Example The contract calls for allying dust thru
    water truck hours. The contractor plans to
    control dust with calcium chloride, the cost for
    which he places in another item.
  • Example A contractor is currently working on an
    adjacent project that has surplus earthwork. He
    bids .01 for borrow on the new project because he
    is being fully compensated for disposal on the
    current project. This will likely ensure he is
    the low bidder.

25
Unusually Low Bids
  • When the bottom line price is below the EE by
    25, and there is a 25 difference between 1st
    and 2nd bidders, VDOT will allow the low bidder
    to withdraw without penalty if the contractor has
    made a mistake.
  • If the 1st bidder wants to withdraw his bid, the
    2nd bid is analyzed in the same fashion. If the
    2nd is deemed a good value, VDOT may make award
    to the 2nd.

26
Rejection of Bids Re-advertisement
  • State law gives the agency the right to reject
    all bids if deemed in the best interest of the
    Commonwealth for any reason other than to
    eliminate a particular vendor.
  • Re-bids in competitive markets usually result in
    lower bids with the next advertisement. Last year
    VDOT saved about 8 million by re-advertising
    projects where bids exceeded the estimate. The
    saving is primarily due to identifying the risk
    through the discussions with the contractor, and
    then mitigating that risk in the second
    advertisement.

27
(No Transcript)
28
Questions?
  • Should be directed to
  • Don Silies
  • State Contract Engineer
  • At email address
  • Don.Silies_at_VDOT.Virginia.gov
Write a Comment
User Comments (0)
About PowerShow.com