Pixel Update - PowerPoint PPT Presentation

About This Presentation
Title:

Pixel Update

Description:

Title: Pixel Update Author: LBNL Last modified by: LBNL Created Date: 10/1/2005 8:57:46 PM Document presentation format: On-screen Show Company: LBNL – PowerPoint PPT presentation

Number of Views:114
Avg rating:3.0/5.0
Slides: 57
Provided by: LBNL2
Category:
Tags: pixel | update

less

Transcript and Presenter's Notes

Title: Pixel Update


1
Pixel Update
  • October 3, 2005

2
Outline
  • Barrel status and repair strategy
  • Revised ATLAS installation schedule
  • Finishing pixel work at LBNL
  • Disk/endcap schedule
  • Service panels and related
  • Work at CERN

3
Barrel Staves
  • Stave loading started about 1 year ago.
  • 44/112 (39) staves have been loaded (one
    partially) till now
  • First problem (April) MCC wire-bonds break.
    Reason seems contamination of MCC surface by
    SE4445 used to glue MCC to FlexHybrid (Maurice
    figured this out). All MCC encapsulated must be
    rebonded.. Bonn is the only site who developed
    the technique.
  • 28 (7 Wu, 8 CPPM, 13 Genova) staves in total have
    MCC encapsulation.
  • 3 done. Note this affects disks also, repairs in
    progress at LBL
  • Second problem (May) Omega delamination from
    TMT. Loading stopped for one month.
  • 2 staves have been found to be delaminated
  • Peek collar designed and successfullyapplied to
    several bare and loaded staves.
  • Strength to delamination increaseof 6x for
    pull/torque.
  • Third problem (August Crisis) Al pipe
    corrosion production halted

4
MCC problem
5
Inspection
Clean 32 staves
Salted 28 staves
Nickel peals off 18 staves
6
Corrosion
  • Galvanic corrosion from nickel-aluminum
    interface, nickel necessary to braze on fittings
  • Thermal tests done using water-antifreeze mixture
    and insufficient drying in many cases
  • In addition to visual signs of corrosion, leaks
    develop.
  • About ½ of staves looked at and 15 leak, in some
    cases with a dozen or more holes caused by
    corrosion.
  • Develops over time gt replace all stave pipes
  • Note that no corrosion has been seen in
    production disk sectors made at LBL different
    process, no water

7
More corrosion
8
Repair Strategy
  • 43 loaded staves. Insert another pipe inside the
    existing pipe and inject glue with good thermal
    properties but there will be an increase in the
    module temperature. Glue on fittings. Pipes of
    appropriate diameters ordered, some preliminary
    tests but not proven yet.
  • Staves without modules. Dismantle staves. It
    turns out that the gluing was not great so using
    tooling local heat can take apart stave,
    replace pipe and put back together. Demonstrated
    on one stave, tooling, procedures in progress.
  • Make new staves, particularly for the innermost
    layer. New materials ordered or about to be
  • In addition, change to fitting scheme developed
    at LBNL for everything no nickel or dissimilar
    metals.

9
Who is Doing What
  • Insert pipe in loaded staves. Marseille and CERN
    but exact responsibilities TBD
  • Qualify process using dummy staves with heaters.
    What is increased temperature and pressure drop
  • Develop procedures
  • Dismantle and reassemble. Genoa. Likely to yield
    fixed staves first.
  • Build new staves
  • Material procurement LBL and Germany
  • Machining of thermal management tiles LBL and
    Wuppertal
  • Assembly company(IVW) in Germany and Wuppertal

10
Resuming Module Loading
  • The critical path is to produce and qualify new
    aluminum tubes. Marseille with some help from LBL
  • Maybe can resume loading of modules in December
    but guess that more likely January before really
    ramped up
  • Must increase by 1.5-2 rate of stave loading and
    testing, which is done at Marseille, Wuppertal
    and Genoa.
  • Plans how to do this but will be a challenge
  • Goal is to reach loading of 4 staves per week and
    testing of 5 per week.

11
Schedule version 7.09
  • Reasons for change?
  • Delays accumulated with ID services (especially
    pipes on barrel calorimeter)
  • Barrel calorimeter moves to z0 on 26 October.
    Installation of ID services (type II/III) follows
    critical path for all ATLAS.
  • Field map of solenoid needs both EC calorimeters
  • Install pixel system as late as possible.
  • Off-detector systems need to be in place for
    barrel then end cap commissioning
  • ID barrel and EC integration should keep working
    to previous RFI dates

12
Critical ID dates
Integration tests in SR1 complete (Heinz P.) Previous installation date New 7.09 installation date Change in installation date
Barrel 16 March 06 1 March 06 11 May 06 10 weeks
EC-C 26 June 06 25 May 06 6 July 06 6 weeks
EC-A 21 July 06 30 June 06 5 August 06 5 weeks
Pixels Not yet updated 5 Oct 06 13 Feb 07 4.5 months
13
C
today
14
26 October 05
15
B-map
26 April 06
16
11 May 06
17
30 June 06
18
3 July 05
19
5 July 06
20
6 July 06
21
10 July 06
22
19 December 06
23
(No Transcript)
24
(No Transcript)
25
30 May 07
26
Installation animation Side A
  • Partial subset with ID highlights

27
A
26 October 05
28
B-map
25 April 06
29
11 May 06
30
12 May 06
31
15 May 06
32
23 May 06
33
2 August 06
34
4 August 06
35
5 August 06
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
14 September 06
40
23 October 06 Side A closed. Hope to have
access to end of ID EC-A.
41
(No Transcript)
42
Lots of steps for big wheels to get to here
43
Reopen to get pixels in
44
(No Transcript)
45
13 February 07
46
(No Transcript)
47
(No Transcript)
48
(No Transcript)
49
(No Transcript)
50
Used to be April 2007
20 June 07
51
Overall Disk Status
52
Schedule
Side C
Side A
53
(No Transcript)
54
Service Panels
  • Production ongoing in 77A
  • Goal is to complete production by June 2006 but
    dont have enough experience yet to make a
    credible schedule
  • But rate will have to increase to meet June 2006
    goal
  • Note that some assembly(optical fibers) will only
    take place at CERN
  • Schedule is tight, even with revised installation
    schedule.

55
LBNL Work at CERN in Next Year
  • Finish Pixel Support Tube installation
  • Receive disks, use first for extended system test
    of 10 of system with mostly real
    components(cooling, readout, .)
  • Receive service panels, install fibers and
    checkout
  • Services installation a huge job, some LBNL
    role
  • Assist in barrel repair and later barrel
    integration(need to double rate here also)
  • In general, EU groups will be very busy with
    barrel rescue, try to offload

56
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com