Title: Technical Reviews Module Space Systems Engineering, version 1.0
1Technical Reviews Module Space Systems
Engineering, version 1.0
2Module Purpose Technical Reviews
- To understand the purpose and value of conducting
technical reviews. - To discuss the timing of technical reviews over
the course of a projects life cycle. - To consider the entrance criteria and success
criteria for the standard project technical
reviews. - To understand when a technical review is
complete.
3Definition of Technical Reviews
- Technical reviews are scheduled within a project
or program to communicate an approach,
demonstrate an ability to meet requirements, or
establish status. - Technical reviews often serve as control gates
for management to make a go/no-go decision on a
project. - Control gates involve formal examination of a
projects status in order to obtain approval to
proceed. - Technical reviews may be held for subsystems too
depending on their size and complexity. Subsystem
reviews precede their corresponding system
review. - When do technical reviews occur?
- Throughout the entire life cycle of a project, as
shown on the following life cycle chart.
4Reviews in a NASA Projects Life Cycle
5The Value of Technical Reviews
- Technical reviews are key development milestones
used to measure progress, assess project maturity
and to infuse lessons from the past. They - Provide confirmation of completed effort and
readiness to commit additional resources for the
next phase. - Encourage and establish project discipline with
an integrated project team perspective. - Identify risks and review mitigation options.
- Describe plans and priorities for the next phase.
- Technical reviews give everyone (design team,
non-advocate discipline experts, customer and
consumer) the opportunity to agree on the current
project baseline (requirements, interfaces,
allocations, margins, schedules, risks, budgets,
etc.). - Functional, resource and performance allocations
and assumptions are described and confirmed. - System development constraints and interfaces are
described and agreed to by both sides. - Risks and development problems are identified and
mitigation options discussed.
6More Values of Technical Reviews
- A significant, and perhaps unexpected, value to
the development team is the preparation for a
review. Usually everyone is busy in their own
domain - preparing for a review forces the team
to describe what they have done and understand
what others are doing. - While there is great value in the preparation,
there is also unique value in the execution. One
Air Force officer once took Dwight D.
Eisenhowers famous quote - Plans are nothing. Planning is everything.
- too seriously and on the day before it was
scheduled cancelled the PDR of a 100 million
space mission. After a minor revolt, the PDR was
reinstated and the team benefited from the
preparation and the review. - Periodic project reviews are held to demonstrate
that the appropriate products, accomplishments
and plans have been completed before proceeding
to the next phase. - Appropriate products, accomplishments and plans
are based on the lessons of hundreds of past
projects (best practices). NASA, for example,
describes standard entrance and success criteria
for all standard milestone reviews.
7NASAs Minimum Set of Technical Reviews
- Mission Concept Review (MCR),
- System Requirements Review (SRR) and/or Mission
Definition Review (MDR), - Preliminary Design Review (PDR),
- Critical Design Review (CDR),
- System Integration Review (SIR),
- Test Readiness Review (TRR),
- Operational Readiness Review (ORR),
- Flight Readiness Review (FRR),
- Post-Launch Assessment Review (PLAR),
- Critical Event Readiness Review (CERR), and
- Decommissioning Review (DR).
- While this may seem like a large number of
technical reviews, each has its own focus and
proven value. - In addition, since mission lifetimes are several
years, typically there is 6 months or more
between major reviews.
8The Primary Questions of Each Review
- Mission Concept Review - Does the proposed
concept meet the mission need and objectives? - System Requirements Review and/or Mission
Definition Review - Do the functional and
performance requirements and the selected concept
satisfy the mission? - Preliminary Design Review - Does the preliminary
design meet all the system requirements within
acceptable cost, schedule, and risk? - Critical Design Review - Is the system design
mature enough to proceed with full-scale
fabrication, assembly, integration and test? - System Integration Review - Are the system,
facilities, personnel, plans and procedures ready
for system integration? - Test Readiness Review - Is the project ready to
commence with verification testing? - Operational Readiness Review - Are all systems
hardware, software, personnel, and procedures in
place to support operations? - Flight Readiness Review - Is the system ready for
launch? Are the ground facilities and personnel
ready to support launch? - Post-Launch Assessment Review - After launch and
deployment, are the spacecraft systems ready to
proceed with routine operations? - Critical Event Readiness Review - Is the project
ready to execute the missions critical
activities during flight operation? - Decommissioning Review - Is the system ready to
be terminated?
9Pre-Phase A Reviews
- Mission Concept Review (MCR)
- A validation that the mission has clearly
established needs, objectives, and top-level
functional/performance requirements, and that at
least one way of conducting the proposed mission
is realistic and attainable within existing or
projected technology and ROM cost. - An internal Center review(s) of all Pre-Phase A
activities and products should be conducted prior
to forwarding the Pre-Phase A report to
Headquarters. Technical, management, resources,
and scientific personnel should conduct the
review. - Peer Reviews
- Used informally during Pre-Phase A and Phase A.
- The peer group is composed of individuals
selected from outside the project according to
their expertise in the applicable disciplines. - Throughout Pre-Phase A and Phase A, peer reviews
should informally check the evolving mission
concept against objectives, requirements, and
constraints. - Peer reviews help you take advantage of other
engineering experience from colleagues who have
worked on different missions. They can point out
issues they confronted that may be similar for
your mission concept.
10Phase A Reviews
- System Requirements Review (SRR)
- The primary focus of the SRR is to verify the
realism of the functional and performance
requirements, ensure their congruence with the
mission and system configuration, and ensure the
mission objectives can be satisfied. - The SRR encompasses all major participants (NASA
and contractors), and is chaired by the Project
Manager. - A product from the SRR is the project system
specification that is formally baselined and
placed under configuration management control. - Mission Definition Review (MDR)
- A validation that the mission objectives can be
satisfied, the partitioning of the functionality
to each of the systems is adequate, the top-level
performance requirements for each system have
been defined, and the technology required to
develop the systems and implement the mission is
attainable. - The MDR is keyed to the end of Phase A and
evaluates the mission definition, system design,
operational concepts, schedule, and cost
estimates.
11Example Entrance Criteria System Requirements
Review
1. Successful completion of the Mission Concept
Review (MCR) and responses made to all MCR
Requests for Actions (RFAs). 2. A preliminary
SRR and/or MDR agenda, success criteria, and
charge to the board have been agreed to by the
technical team, project manager, and review chair
prior to the SRR and/or MDR. 3. The following
technical products for hardware and software
system elements are available to the cognizant
participants prior to the review a. System
Architecture. b. System requirements document. c.
System software functionality description. d.
Updated concept of operations. e. Updated mission
requirements, if applicable. f. Baselined
SEMP. g. Preliminary system requirements
allocation to the next lower level system. h.
Updated cost estimate. i. Technology Development
Maturity Assessment Plan. j. Preferred system
solution definition including major trades and
options. k. Updated risk assessment and
mitigations. l. Updated cost and schedule
data. m. Logistics documentation (preliminary
maintenance plan, etc.). n. Preliminary human
rating plan, if applicable. o. Software
Development Plan (SDP). p. System safety and
mission assurance plan. q. Configuration
management plan. r. Project management plan. s.
Initial document tree. t. Verification and
validation approach. u. Preliminary hazard
analysis (PHA).
12Example Success Criteria System Requirements
Review
- The resulting overall concept is reasonable,
feasible, complete, responsive to the mission
requirements, and is consistent with system
requirements and available resources (cost,
schedule, mass power, etc.). - The project utilizes a sound process for the
allocation and control of requirements throughout
all levels, and a plan has been defined to
complete the definition activity within schedule
constraints. - Requirements definition is complete with respect
to top level mission and science requirements,
and interfaces with external entities and between
major internal elements have been defined. - Requirements allocation and flow down of key
driving requirements have been defined down to
subsystems. - System and subsystem design approaches and
operational concepts exist and are consistent
with the requirements set. - The requirements, design approaches, and
conceptual design will fulfill the mission needs
within the estimated costs. - Preliminary approaches have been determined for
how requirements will be verified and validated
down to the subsystem level - Major risks have been identified, and viable
mitigation strategies have been defined.
13Constellation Program Office Schedule of SRRs
You are Here!
2007
5/23
March
April
May
Provide Issue list w/ Resolution Plan Impacts
3/29
Rev. Issue Table, POC, Sched.
4/6
4/9
5/14
4/16
Develop PBS Presentation
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/23
4/30
(send updates to Cx SEI COB every other day in
May)
5/10
Provide Issue list w/ Resolution Plan Impacts
4/16
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/23
4/30
(send updates to Cx SEI COB every other day in
May)
CEV SRR
5/10
Provide Issue list w/ Resolution Plan Impacts
4/23
4/30
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/16
(send updates to Cx SEI COB every other day in
May)
MO SRR
Provide Issue list w/ Resolution Plan Impacts
Develop PBS Presentation
GO SRR
Provide Status on Issue Resolution (send updates
to Cx SEI COB every other day in May)
Provide Issue list w/ Resolution Plan Impacts
Issue ID, Form Entry
Develop PBS Presentation
EVA SRR
Provide Status on Issue Resolution (send updates
to Cx SEI COB every other day in May)
14Constellation Program Office Status - Closure of
SRR
- RIDs
- Total RID Count 6,283
- 6225 Closed
- 58 Open
- Majority closed prior to PBS
- All RIDs should be closed prior to CxP SDR
- Board AI
- Total AI Count 48 Total
- 9 Closed
- 39 Open
- 30 are Past Due
- 9 are in work, Not Due Yet
- TBD/TBR
- Total Count 2,532
- Received plans for 2,064 TBRs/TBDs in 72 of 95
documents (76 of docs.) - Need burn-down plans for 196 TBRs/TBDs in 16
documents (17 of docs.) - 7 documents (274 TBRs/TBDs) will not be
updated/baselined until post CxP PBS. These
TBRs/TBDs will not be closed prior to CxP PBS
15Preliminary Design Review (PDR)
- The PDR is not a single review but a number of
reviews starting with the specific component
PDRs, followed by the system-level review. - The PDR establishes the design-to baseline and
ensures that it meets the program, project ,
system, subsystem, or specific component baseline
requirements. - The PDR process should
- Establish the ability of the selected design
approach to meet the technical requirements
(i.e., Verifiability/ Traceability) - Establish the compatibility of the interface
relationships of the specific end item with other
interfacing items - Establish producibility of the selected design
- Establish the operability of the selected design
- Assess compliance with reliability and system
safety requirements - Establish the feasibility of the approach
- Address status, schedule and cost relationships.
16When is a Review Complete?
- Reviews are considered complete when the
following is accomplished - Agreement exists for the disposition of all
Review Item Discrepancies (RID) and Request for
Actions (RFA). - The review board report and minutes are complete
and distributed. - Agreement exists on a plan to address the issues
and concerns in the review boards report. - Agreement exists on a plan for addressing the
actions identified out of the review. - Liens against the review results are closed, or
an adequate and timely plan exists for their
closure. - Differences of opinion between the project under
review and the review board(s) have been
resolved, or a timely plan exists to resolve the
issues. - A report is given by the review board chairperson
to the appropriate management and governing
program management committees charged with
oversight of the project. - Appropriate procedures and controls are
instituted to ensure that all actions from
reviews are followed and verified through
implementation to closure.
17Example Agenda for a Project System Design Review
by a Standing Review Board (SRB)
- Purpose of Review Charge to SRB SRB Chair
- Project Overview Status Project Manager
- System Engineering Status Project SE
- Requirements VV plans
- Trade studies
- Technical margins
- WBS-level 2 Design State Status for each
area WBS Managers - System Design
- Key Requirements
- Trade Studies
- Technology Readiness
- Acquisition Strategy Long Lead
- Logistics Facilities
- Challenges Risks
- Integrated System (e.g., power) State Status
for each area Discipline Leads - Integration Test Integration Manager
- Safety Mission Assurance (SMA) SMA Manager
- Human Rating Project HR Rep
- Risk Risk Manager
18Pause and Learn Opportunity
- Student role-play
- You are the chief systems engineer for a New
Frontiers-class mission to Europa. Your PDR is
scheduled in 3 months. - What do you do?
- What do you ask the development team to do?
- What benefits would you expect from having a PDR?
- How might it waste time?
- Or
- Read and discuss the Crosslink article The Role
of Independent Assessments for Mission Readiness - (Crosslink_Independent Review.pdf)
19Module Summary Technical Reviews
- Technical reviews are key development milestones
used to measure progress, assess project maturity
and to infuse lessons from the past. They - Provide confirmation of completed effort and
readiness to commit additional resources for the
next phase. - Encourage and establish project discipline with
an integrated project team perspective. - Identify risks and review mitigation options.
- Describe plans and priorities for the next phase.
- There are 11 reviews in the minimum set of
technical reviews for a NASA robotic mission.
These reviews cover the entire mission life
assessing the concepts and designs early
readiness for test, flight and operations in
mid-life and plans for disposal at the missions
end. - These reviews are held to demonstrate that the
appropriate products, accomplishments and plans
have been completed before proceeding to the next
phase. - Appropriate products, accomplishments and plans
are based on the lessons of hundreds of past
projects (best practices).
20Backup Slidesfor Technical Review Module
21Major Project Reviews Precede Each Key Decision
Point
FORMULATION
IMPLEMENTATION
A
B
C
D
E
F
Pre-A
Concept Technology Development
System Assembly, Test, Launch
Concept Studies
Preliminary Design Technology Completion
Final Design Fabrication
Closeout
Operations Sustainment
Project Phases
C
D
E
B
A
F
Key Decision Points
Mission Concept Review
Systems Requirements Review
Major Reviews
Mission/System Definition Review
Preliminary Design Review
Critical Design Review
Systems Integration Review
Independent Cost Estimates
Operational Readiness Review
Flight Readiness Review
Post Launch Assessment Review
Decommissioning Review
22Purpose of Technical Reviews
- A technical review is an evaluation of the
project, or element thereof, by a knowledgeable
group for the purposes of - Assessing the status of and progress toward
accomplishing the planned activities. - Validating the technical tradeoffs explored and
design solutions proposed. - Identifying technical weaknesses or marginal
design and potential problems (risks) and
recommending improvements and corrective actions. - Making judgments on the activities readiness for
the follow-on events, including additional future
evaluation milestones to improve the likelihood
of a successful outcome. - Making assessments and recommendations to the
project team, Center, and Agency management. - Providing a historical record that can be
referenced of decisions that were made during
these formal reviews. - Assessing the technical risk status and current
risk profile.
23Need for Management Reviews
- The progress between life-cycle phases is marked
by key decision points (KDPs). At each KDP,
management examines the maturity of the technical
aspects of the project. For example, management
examines whether the resources (staffing and
funding) are sufficient for the planned technical
effort, whether the technical maturity has
evolved, what the technical and non-technical
internal issues and risks are, or whether the
stakeholder expectations have changed. If the
technical and management aspects of the project
are satisfactory, including the implementation of
corrective actions, then the project can be
approved to proceed to the next phase.
24Blue text indicates changes from last update