Technical Reviews Module Space Systems Engineering, version 1.0 - PowerPoint PPT Presentation

About This Presentation
Title:

Technical Reviews Module Space Systems Engineering, version 1.0

Description:

... After launch and deployment, ... Operational Readiness Review - Are ... The following technical products for hardware and software system elements are ... – PowerPoint PPT presentation

Number of Views:128
Avg rating:3.0/5.0
Slides: 25
Provided by: spaceseSp1
Category:

less

Transcript and Presenter's Notes

Title: Technical Reviews Module Space Systems Engineering, version 1.0


1

Technical Reviews Module Space Systems
Engineering, version 1.0

2
Module Purpose Technical Reviews
  • To understand the purpose and value of conducting
    technical reviews.
  • To discuss the timing of technical reviews over
    the course of a projects life cycle.
  • To consider the entrance criteria and success
    criteria for the standard project technical
    reviews.
  • To understand when a technical review is
    complete.

3
Definition of Technical Reviews
  • Technical reviews are scheduled within a project
    or program to communicate an approach,
    demonstrate an ability to meet requirements, or
    establish status.
  • Technical reviews often serve as control gates
    for management to make a go/no-go decision on a
    project.
  • Control gates involve formal examination of a
    projects status in order to obtain approval to
    proceed.
  • Technical reviews may be held for subsystems too
    depending on their size and complexity. Subsystem
    reviews precede their corresponding system
    review.
  • When do technical reviews occur?
  • Throughout the entire life cycle of a project, as
    shown on the following life cycle chart.

4
Reviews in a NASA Projects Life Cycle
5
The Value of Technical Reviews
  • Technical reviews are key development milestones
    used to measure progress, assess project maturity
    and to infuse lessons from the past. They
  • Provide confirmation of completed effort and
    readiness to commit additional resources for the
    next phase.
  • Encourage and establish project discipline with
    an integrated project team perspective.
  • Identify risks and review mitigation options.
  • Describe plans and priorities for the next phase.
  • Technical reviews give everyone (design team,
    non-advocate discipline experts, customer and
    consumer) the opportunity to agree on the current
    project baseline (requirements, interfaces,
    allocations, margins, schedules, risks, budgets,
    etc.).
  • Functional, resource and performance allocations
    and assumptions are described and confirmed.
  • System development constraints and interfaces are
    described and agreed to by both sides.
  • Risks and development problems are identified and
    mitigation options discussed.

6
More Values of Technical Reviews
  • A significant, and perhaps unexpected, value to
    the development team is the preparation for a
    review. Usually everyone is busy in their own
    domain - preparing for a review forces the team
    to describe what they have done and understand
    what others are doing.
  • While there is great value in the preparation,
    there is also unique value in the execution. One
    Air Force officer once took Dwight D.
    Eisenhowers famous quote
  • Plans are nothing. Planning is everything.
  • too seriously and on the day before it was
    scheduled cancelled the PDR of a 100 million
    space mission. After a minor revolt, the PDR was
    reinstated and the team benefited from the
    preparation and the review.
  • Periodic project reviews are held to demonstrate
    that the appropriate products, accomplishments
    and plans have been completed before proceeding
    to the next phase.
  • Appropriate products, accomplishments and plans
    are based on the lessons of hundreds of past
    projects (best practices). NASA, for example,
    describes standard entrance and success criteria
    for all standard milestone reviews.

7
NASAs Minimum Set of Technical Reviews
  • Mission Concept Review (MCR),
  • System Requirements Review (SRR) and/or Mission
    Definition Review (MDR),
  • Preliminary Design Review (PDR),
  • Critical Design Review (CDR),
  • System Integration Review (SIR),
  • Test Readiness Review (TRR),
  • Operational Readiness Review (ORR),
  • Flight Readiness Review (FRR),
  • Post-Launch Assessment Review (PLAR),
  • Critical Event Readiness Review (CERR), and
  • Decommissioning Review (DR).
  • While this may seem like a large number of
    technical reviews, each has its own focus and
    proven value.
  • In addition, since mission lifetimes are several
    years, typically there is 6 months or more
    between major reviews.

8
The Primary Questions of Each Review
  • Mission Concept Review - Does the proposed
    concept meet the mission need and objectives?
  • System Requirements Review and/or Mission
    Definition Review - Do the functional and
    performance requirements and the selected concept
    satisfy the mission?
  • Preliminary Design Review - Does the preliminary
    design meet all the system requirements within
    acceptable cost, schedule, and risk?
  • Critical Design Review - Is the system design
    mature enough to proceed with full-scale
    fabrication, assembly, integration and test?
  • System Integration Review - Are the system,
    facilities, personnel, plans and procedures ready
    for system integration?
  • Test Readiness Review - Is the project ready to
    commence with verification testing?
  • Operational Readiness Review - Are all systems
    hardware, software, personnel, and procedures in
    place to support operations?
  • Flight Readiness Review - Is the system ready for
    launch? Are the ground facilities and personnel
    ready to support launch?
  • Post-Launch Assessment Review - After launch and
    deployment, are the spacecraft systems ready to
    proceed with routine operations?
  • Critical Event Readiness Review - Is the project
    ready to execute the missions critical
    activities during flight operation?
  • Decommissioning Review - Is the system ready to
    be terminated?

9
Pre-Phase A Reviews
  • Mission Concept Review (MCR)
  • A validation that the mission has clearly
    established needs, objectives, and top-level
    functional/performance requirements, and that at
    least one way of conducting the proposed mission
    is realistic and attainable within existing or
    projected technology and ROM cost.
  • An internal Center review(s) of all Pre-Phase A
    activities and products should be conducted prior
    to forwarding the Pre-Phase A report to
    Headquarters. Technical, management, resources,
    and scientific personnel should conduct the
    review.
  • Peer Reviews
  • Used informally during Pre-Phase A and Phase A.
  • The peer group is composed of individuals
    selected from outside the project according to
    their expertise in the applicable disciplines.
  • Throughout Pre-Phase A and Phase A, peer reviews
    should informally check the evolving mission
    concept against objectives, requirements, and
    constraints.
  • Peer reviews help you take advantage of other
    engineering experience from colleagues who have
    worked on different missions. They can point out
    issues they confronted that may be similar for
    your mission concept.

10
Phase A Reviews
  • System Requirements Review (SRR)
  • The primary focus of the SRR is to verify the
    realism of the functional and performance
    requirements, ensure their congruence with the
    mission and system configuration, and ensure the
    mission objectives can be satisfied.
  • The SRR encompasses all major participants (NASA
    and contractors), and is chaired by the Project
    Manager.
  • A product from the SRR is the project system
    specification that is formally baselined and
    placed under configuration management control.
  • Mission Definition Review (MDR)
  • A validation that the mission objectives can be
    satisfied, the partitioning of the functionality
    to each of the systems is adequate, the top-level
    performance requirements for each system have
    been defined, and the technology required to
    develop the systems and implement the mission is
    attainable.
  • The MDR is keyed to the end of Phase A and
    evaluates the mission definition, system design,
    operational concepts, schedule, and cost
    estimates.

11
Example Entrance Criteria System Requirements
Review
1. Successful completion of the Mission Concept
Review (MCR) and responses made to all MCR
Requests for Actions (RFAs). 2. A preliminary
SRR and/or MDR agenda, success criteria, and
charge to the board have been agreed to by the
technical team, project manager, and review chair
prior to the SRR and/or MDR. 3. The following
technical products for hardware and software
system elements are available to the cognizant
participants prior to the review a. System
Architecture. b. System requirements document. c.
System software functionality description. d.
Updated concept of operations. e. Updated mission
requirements, if applicable. f. Baselined
SEMP. g. Preliminary system requirements
allocation to the next lower level system. h.
Updated cost estimate. i. Technology Development
Maturity Assessment Plan. j. Preferred system
solution definition including major trades and
options. k. Updated risk assessment and
mitigations. l. Updated cost and schedule
data. m. Logistics documentation (preliminary
maintenance plan, etc.). n. Preliminary human
rating plan, if applicable. o. Software
Development Plan (SDP). p. System safety and
mission assurance plan. q. Configuration
management plan. r. Project management plan. s.
Initial document tree. t. Verification and
validation approach. u. Preliminary hazard
analysis (PHA).
12
Example Success Criteria System Requirements
Review
  1. The resulting overall concept is reasonable,
    feasible, complete, responsive to the mission
    requirements, and is consistent with system
    requirements and available resources (cost,
    schedule, mass power, etc.).
  2. The project utilizes a sound process for the
    allocation and control of requirements throughout
    all levels, and a plan has been defined to
    complete the definition activity within schedule
    constraints.
  3. Requirements definition is complete with respect
    to top level mission and science requirements,
    and interfaces with external entities and between
    major internal elements have been defined.
  4. Requirements allocation and flow down of key
    driving requirements have been defined down to
    subsystems.
  5. System and subsystem design approaches and
    operational concepts exist and are consistent
    with the requirements set.
  6. The requirements, design approaches, and
    conceptual design will fulfill the mission needs
    within the estimated costs.
  7. Preliminary approaches have been determined for
    how requirements will be verified and validated
    down to the subsystem level
  8. Major risks have been identified, and viable
    mitigation strategies have been defined.

13
Constellation Program Office Schedule of SRRs
You are Here!
2007
5/23
March
April
May
Provide Issue list w/ Resolution Plan Impacts
3/29
Rev. Issue Table, POC, Sched.
4/6
4/9
5/14
4/16
Develop PBS Presentation
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/23
4/30
(send updates to Cx SEI COB every other day in
May)
5/10
Provide Issue list w/ Resolution Plan Impacts
4/16
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/23
4/30
(send updates to Cx SEI COB every other day in
May)
CEV SRR
5/10
Provide Issue list w/ Resolution Plan Impacts
4/23
4/30
Provide Status on Issue Resolution (every Mon. _at_
Cx SEI 830 telecon)
4/16
(send updates to Cx SEI COB every other day in
May)
MO SRR
Provide Issue list w/ Resolution Plan Impacts
Develop PBS Presentation
GO SRR
Provide Status on Issue Resolution (send updates
to Cx SEI COB every other day in May)
Provide Issue list w/ Resolution Plan Impacts
Issue ID, Form Entry
Develop PBS Presentation
EVA SRR
Provide Status on Issue Resolution (send updates
to Cx SEI COB every other day in May)
14
Constellation Program Office Status - Closure of
SRR
  • RIDs
  • Total RID Count 6,283
  • 6225 Closed
  • 58 Open
  • Majority closed prior to PBS
  • All RIDs should be closed prior to CxP SDR
  • Board AI
  • Total AI Count 48 Total
  • 9 Closed
  • 39 Open
  • 30 are Past Due
  • 9 are in work, Not Due Yet
  • TBD/TBR
  • Total Count 2,532
  • Received plans for 2,064 TBRs/TBDs in 72 of 95
    documents (76 of docs.)
  • Need burn-down plans for 196 TBRs/TBDs in 16
    documents (17 of docs.)
  • 7 documents (274 TBRs/TBDs) will not be
    updated/baselined until post CxP PBS. These
    TBRs/TBDs will not be closed prior to CxP PBS

15
Preliminary Design Review (PDR)
  • The PDR is not a single review but a number of
    reviews starting with the specific component
    PDRs, followed by the system-level review.
  • The PDR establishes the design-to baseline and
    ensures that it meets the program, project ,
    system, subsystem, or specific component baseline
    requirements.
  • The PDR process should
  • Establish the ability of the selected design
    approach to meet the technical requirements
    (i.e., Verifiability/ Traceability)
  • Establish the compatibility of the interface
    relationships of the specific end item with other
    interfacing items
  • Establish producibility of the selected design
  • Establish the operability of the selected design
  • Assess compliance with reliability and system
    safety requirements
  • Establish the feasibility of the approach
  • Address status, schedule and cost relationships.

16
When is a Review Complete?
  • Reviews are considered complete when the
    following is accomplished
  • Agreement exists for the disposition of all
    Review Item Discrepancies (RID) and Request for
    Actions (RFA).
  • The review board report and minutes are complete
    and distributed.
  • Agreement exists on a plan to address the issues
    and concerns in the review boards report.
  • Agreement exists on a plan for addressing the
    actions identified out of the review.
  • Liens against the review results are closed, or
    an adequate and timely plan exists for their
    closure.
  • Differences of opinion between the project under
    review and the review board(s) have been
    resolved, or a timely plan exists to resolve the
    issues.
  • A report is given by the review board chairperson
    to the appropriate management and governing
    program management committees charged with
    oversight of the project.
  • Appropriate procedures and controls are
    instituted to ensure that all actions from
    reviews are followed and verified through
    implementation to closure.

17
Example Agenda for a Project System Design Review
by a Standing Review Board (SRB)
  • Purpose of Review Charge to SRB SRB Chair
  • Project Overview Status Project Manager
  • System Engineering Status Project SE
  • Requirements VV plans
  • Trade studies
  • Technical margins
  • WBS-level 2 Design State Status for each
    area WBS Managers
  • System Design
  • Key Requirements
  • Trade Studies
  • Technology Readiness
  • Acquisition Strategy Long Lead
  • Logistics Facilities
  • Challenges Risks
  • Integrated System (e.g., power) State Status
    for each area Discipline Leads
  • Integration Test Integration Manager
  • Safety Mission Assurance (SMA) SMA Manager
  • Human Rating Project HR Rep
  • Risk Risk Manager

18
Pause and Learn Opportunity
  • Student role-play
  • You are the chief systems engineer for a New
    Frontiers-class mission to Europa. Your PDR is
    scheduled in 3 months.
  • What do you do?
  • What do you ask the development team to do?
  • What benefits would you expect from having a PDR?
  • How might it waste time?
  • Or
  • Read and discuss the Crosslink article The Role
    of Independent Assessments for Mission Readiness
  • (Crosslink_Independent Review.pdf)

19
Module Summary Technical Reviews
  • Technical reviews are key development milestones
    used to measure progress, assess project maturity
    and to infuse lessons from the past. They
  • Provide confirmation of completed effort and
    readiness to commit additional resources for the
    next phase.
  • Encourage and establish project discipline with
    an integrated project team perspective.
  • Identify risks and review mitigation options.
  • Describe plans and priorities for the next phase.
  • There are 11 reviews in the minimum set of
    technical reviews for a NASA robotic mission.
    These reviews cover the entire mission life
    assessing the concepts and designs early
    readiness for test, flight and operations in
    mid-life and plans for disposal at the missions
    end.
  • These reviews are held to demonstrate that the
    appropriate products, accomplishments and plans
    have been completed before proceeding to the next
    phase.
  • Appropriate products, accomplishments and plans
    are based on the lessons of hundreds of past
    projects (best practices).

20
Backup Slidesfor Technical Review Module
21
Major Project Reviews Precede Each Key Decision
Point
FORMULATION
IMPLEMENTATION
A
B
C
D
E
F
Pre-A
Concept Technology Development
System Assembly, Test, Launch
Concept Studies
Preliminary Design Technology Completion
Final Design Fabrication
Closeout
Operations Sustainment
Project Phases
C
D
E
B
A
F
Key Decision Points
Mission Concept Review
Systems Requirements Review
Major Reviews
Mission/System Definition Review
Preliminary Design Review
Critical Design Review
Systems Integration Review
Independent Cost Estimates
Operational Readiness Review
Flight Readiness Review
Post Launch Assessment Review
Decommissioning Review
22
Purpose of Technical Reviews
  • A technical review is an evaluation of the
    project, or element thereof, by a knowledgeable
    group for the purposes of
  • Assessing the status of and progress toward
    accomplishing the planned activities.
  • Validating the technical tradeoffs explored and
    design solutions proposed.
  • Identifying technical weaknesses or marginal
    design and potential problems (risks) and
    recommending improvements and corrective actions.
  • Making judgments on the activities readiness for
    the follow-on events, including additional future
    evaluation milestones to improve the likelihood
    of a successful outcome.
  • Making assessments and recommendations to the
    project team, Center, and Agency management.
  • Providing a historical record that can be
    referenced of decisions that were made during
    these formal reviews.
  • Assessing the technical risk status and current
    risk profile.

23
Need for Management Reviews
  • The progress between life-cycle phases is marked
    by key decision points (KDPs). At each KDP,
    management examines the maturity of the technical
    aspects of the project. For example, management
    examines whether the resources (staffing and
    funding) are sufficient for the planned technical
    effort, whether the technical maturity has
    evolved, what the technical and non-technical
    internal issues and risks are, or whether the
    stakeholder expectations have changed. If the
    technical and management aspects of the project
    are satisfactory, including the implementation of
    corrective actions, then the project can be
    approved to proceed to the next phase.

24
Blue text indicates changes from last update
Write a Comment
User Comments (0)
About PowerShow.com