Title: CONOPS Elements
1 JBSA Energy
JBSA Energy team
2JBSA Energy Team
- Randolph,
- Lackland
- Fort Sam Houston
3Goals
- Reduce energy use by 3 per year
- Reduce potable water usage intensity by 2 per
year - Reduce fuel use by 3 per year
- Increase alternative fuels use by 2 per year
- Install required electric, gas and water meters
AETC contract(s) - Renewable Energy vs goal not required if not
feasible - Audits - accomplished through AETC contract(s)
- Energy Security
- Enhance base energy infrastructure and facilities
- Develop innovative ways to operate maintain
facilities to reduce utility costs - JBSA-wide Awareness campaign
4Initiatives Requirements
- Building Metering and Control Methodology to
deliver higher energy performance - Last years
Workshop - Water Conservation and Efficiency Development
and demonstration of technologies - Energy Conservation and Efficiency Technologies
that support sustainable building design and
operations - Alternative Energy Sources Alternative energy
from centralized power generation sources - Renewable Energy Generation Developing and
demonstrating renewable technologies - Audit/Commissioning technology Data
collection/modeling for energy sustainability - Innovation Center share tech info other
peoples money - Energy Efficient Fuels/Vehicles
5Energy Intensity vs Goal
- Consumption
- JBSA MBTU per sqft vs goal
6Utility Cost
- Utilities Cost (000) FY11 12
7Goal Analysis
000 Kwh
FY11 FY12 FY13 FY14 FY15
Total Projects Kwh Savings Total Projects Kwh Savings 52,629 62,703 79,631 97,869 97,869
Kwh needed to meet Goal Kwh needed to meet Goal 153,197 175,147 190,245 204,031 236,056
8JBSA Energy News
- From last years workshop
- EMCS Project Progress
- Lackland
- Fort Sam Houston
- Randolph
9JBSA Initiatives
- Traditional Focus Funding leaving us short
- Partnerships (DTI) Innovation Center
- Public Awareness
- Commissioning/re-commissioning
- High Performance Specification beyond LEED
- ESPCs/ECIP
- New Technology Opportunities
- ESTCPs Plasma lighting, facility system, HVAC
condensate - AFRL- JBSA facility energy technology
Concentrated Solar - Utility provider
- Joint Awareness Campaign
- LED Lighting FSH
- Home Network
- Area-wide Contract ECMs/UESC
10Goal Analysis
000 Kwh
FY11 FY12 FY13 FY14 FY15
Total Projects Kwh Savings Total Projects Kwh Savings 52,629 62,703 79,631 97,869 97,869
Kwh needed to meet Goal Kwh needed to meet Goal 153,197 175,147 190,245 204,031 236,056
Kwh needed with ECMs/ Initiatives Kwh needed with ECMs/ Initiatives 30,983 27,867 20,745
11Questions?
12JBSA/Randolph AFB
- Virtual Chilled Water Plant
13Initial Concept
- Central Chiller Plant B991 with TES
- ESPC Project to construct chiller plant, Thermal
Energy Storage (TES), and interconnect multiple
facilities - Removed inefficient building air cooled chillers
- Solid results
14Replication
- B395, B738, and B496 had large centrifugal
chiller plants with excess capacity - Interconnect surrounding facilities
- Remove inefficient individual air cooled chillers
15Plant Interconnection
- Excess capacity at B991, B738, B395, and B496.
- Interconnect plants
- Connect additional buildings on east and south
side of installation - Removal of more inefficient air cooled chillers
16Replace Plant
- B496 AFPC plant reconstructed to serve renovated
facility along with additional buildings on west
side of installation - Removal of inefficient air cooled chillers,
replacement of inefficient centrifugal chillers - Excess capacity available
17EMCS Status
- Complete FY12 EMCS project to add building BTU
metering and central plant optimization - Connect other buildings to virtual plant
18Final Randolph Chilled Water Loop Vision
- Interconnect B496 to B395 and B991 plants
- Install Thermal Energy Storage (TES) at B496 and
B395 plants - Perform retro-commissioning of all buildings
served by district plants to maximize efficiency
and energy savings
19JBSA/Randolph AFB
- End Status and Project Highlights