Title: Alameda Unified School District
1Alameda Unified School District
- 2008 Construction Progress Report
2Overview
- Construction Goals
- Build a new K-5 school
- Work at existing schools
- Address Americans with Disabilities Act (ADA)
compliance requirements - Upgrade Fire Alarm Systems as needed
- Upgrade HVAC Systems
- Repair aging building systems - i.e. roofs,
windows doors as needed - Repair worn or damaged finishes
- Perform site specific projects including play
structures, seal and re-line asphalt, irrigation
3 Source of the 91.4 Million Budget
4Current Budget all fund sources
PHASE 1 PHASE 4
Ruby Bridges 22,050,880 EHS 3,090,000
sub total 22,050,880 Franklin 430,000
PHASE 2 Chipman part 2 0
AHS 9,166,249 WCDC 750,000
Lincoln 8,550,000 sub total 4,270,000
Earhart 5,504,457 PHASE 5
Haight Elementary 5,560,000 Wood 1,380,000
Miller/Island 2,340,000 Bay Farm 1,200,000
sub total 31,120,706 Adult 630,000
PHASE 3 HAHS 7,000,000
HAHS MIDDLE 50,000 Woodstock 1,516,992
Paden 1,680,000 Longfellow 1,253,000
Edison 2,335,000 sub total 12,979,992
Lum 1,812,000 TECHNOLOGY 5,000,000
Otis 1,910,000 FFE 1,995,318
Washington 2,670,000 INTERIM HOUSING 2,200,000
Chipman part 1 1,370,000 sub total 9,195,318
11,827,000 Total 91,443,896
5 Board Approved Projects
School Approved Bid BOE Current Budget Including CM, and AE
Ruby Bridges- 9/6/05 22,050,880
Earhart 5/24/05 5,504,457
Lincoln 5/24/05 8,550,000
Alameda 5/30/05 9,166,249
Miller 5/30/05 2,340,000
Haight 5/09/06 5,560,000
Edison 5/08/07 2,335,000
Lum 5/08/07 1,812,000
Otis 5/08/07 1,910,000
Washington 5/08/07 2,670,000
Chipman increment 1 5/08/07 1,370,000
Paden 5/08/07 1,680,000
6Ruby Bridges Elementary School
- Scope
- Construct New K-5 School
- Accommodate students from Miller and Woodstock
Elementary Schools - Increased capacity ( increment II ) to
accommodate Longfellow students
- Project Start Date 6/13/05
- Current Status Completed
- Warrantee Work
- Electrical
- HVAC
- Current Budget 22,050,880
- Funds Expended 20,918,639
7Amelia Earhart Elementary School
- Scope
- Fire Alarm
- HVAC
- Portable Relocation
- ADA Compliance
- Project Start Date 6/21/05
- Current Status Completed
- Current Budget 5,504,457
- Funds Expended 4,966,040
8Lincoln Middle School
- Scope
- HVAC
- Electrical upgrade
- ADA compliance
- Restrooms
- 2 story addition
- Project Start Date 6/21/05
- Current Status 90 Complete
- Current Budget 8,550,000
- Funds Expended 8,266,070
9Haight Elementary School
- Scope
- Seismic Retrofit
- HVAC
- Alarm Systems
- ADA Compliance
- Exterior Paint
- Project Start Date 6/24/06
- Current Status Complete
- Current Budget 5,560,000
- Funds Expended 5,542,006
10Alameda High School
- Scope
- HVAC
- Fire Alarm
- ADA Compliance
- Electrical upgrade
- Interior finishes
- Grounds upgrades
- Exterior Paint
- Project Start Date 6/22/06
- Current Status 99 Completed
- HVAC
- Irrigation
- Current Budget 9,166,249
- Funds Expended 8,949,609
11Miller (Island High School)
- Scope
- HVAC
- ADA Compliance
- Interior Finishes
- Alarms
- Project Start Date 6/22/06
- Current Status Completed
- Warrantee Phase
- HVAC
- Current Budget 2,340,000
- Funds Expended 2,330,363
12Edison Elementary School
- Scope
- Heat and Ventilation
- ADA Compliance
- Alarms
- Project Start Date 6/18/07
- Current Status Complete
- Current Budget 2,335,000
- Funds Expended 2,320,269
13Otis Elementary School
- Scope
- Heat and Ventilation
- ADA Compliance
- Alarms
- Project Start Date 6/18/07
- Current Status Complete
- Current Budget 1,910,000
- Funds Expended 1,881,809
14Lum Elementary School
- Scope
- HVAC
- ADA Compliance
- Alarms
- Electrical Upgrade -Paging/Intercom
- Project Start Date 6/18/07
- Current Status Complete
- Warrantee Phase
- HVAC
- Electrical
- Casework
- Current Budget 1,812,000
- Funds Expended 1,791,739
15Washington Elementary School
- Scope
- Heat and Ventilation
- ADA Compliance
- Alarms
- Electrical Upgrade -Paging/Intercom
- Window Replacement
- Project Start Date 6/18/07
- Current Status Complete
- Current Budget 2,670,000
- Funds Expended 2,636,000
16Paden Elementary School
- Scope
- HVAC
- ADA Compliance
- Alarms
- Project Start Date 6/18/07
- Current Status Complete
- Current Budget 1,680,000
- Funds Expended 1,671,449
17Chipman Middle School Increment 1
- Scope
- ADA Compliance Restrooms
- Exterior Paint
- Project Start Date 6/18/07
- Current Status Complete
- Current Budget 1,370,000
- Funds Expended 1,362,926
18FFE Interim Housing and Technology
Budget Expended Balance
TECHNOLOGY 5,000,000 4,327,426 672,574
Furniture Fixtures Equipment 1,995,318 597,415 1,397,903
INTERIM HOUSING 2,200,000 1,924,355 275,645
19Remaining Projects PHASE IV
- Preliminary Construction Estimates
- Chipman Middle School part II
- HVAC retrofit
- ADA Compliance parking lot, sidewalks, and other
minor work - Encinal High School
- HVAC coil replacement 200, 300, and 400 wing HV
systems - HVAC Gym system upgrade
- ADA Compliance major site accessibility work on
the gym and building 400 - Fire Alarm System Upgrade system replacement
- Woodstock Child Development Center
- Minor ADA work at entry of building
- HVAC repairs
- Floor coverings and interior paint
- Lighting retrofit
- Adult School
- Exterior Windows South and West restoration or
replacement - Repair Plaster and wood trim
- Exterior paint
- Historical Alameda High School
20Remaining Projects PHASE V
- Franklin Elementary School
- Minor ADA work at entry of building
- HVAC repairs to controls, boiler, circulation
pumps and 3-way valves - Replace worn blinds
- Wood Middle School
- ADA compliance in affected areas
- Fire Alarm System replacement
- HVAC repairs to most systems
- Exterior paint
- Bayfarm Elementary School
- ADA compliance path of travel and entrances to
classrooms - HVAC in Media Center
- Fire Alarm
- Utility retrofit Natural Gas flex connector
- Longfellow Education Center
- ADA compliance in affected areas
- Fire Alarm System replacement
- HVAC repairs to most systems
- Exterior paint
21Moving Forward
Summary
Budget Expenditures Expenditures Balance
Measure C 62,995,318 52,022,606 52,022,606 10,972,712
Modernization-Award 12,642,330 12,642,330 12,642,330 0
Growth 7,760,984 2,760,984 2,760,984 5,000,000
Developer Fees 6,210,264 6,210,264 6,210,264 0
Deferred Maintenance 1,835,000 1,835,000 1,835,000 0
TOTALS 91,443,895 75,471,184 75,471,184 15,972,712
Measure C Detail Measure C Detail Measure C Detail Measure C Detail Measure C Detail
Balance from above 10,972,712 10,972,712
TECHNOLOGY -672,574 -672,574
FFE -1,397,903 -1,397,903
Working Balance 8,902,235 8,902,235
22Calendar of events
- June 24th 2008 Measure C Oversight Committee
Report - June 24th Authorization to Advertise for Bids on
phase 4 and 5 approved projects. - Construction Updates
- October 2008 Construction Update
- February 2009 Construction Update
- June 2009 Construction Update
23Measure C
- The largest portion of the work identified in
this report was funded through a bond measure
passed in 2004. Alameda Unified School District
would like to express our thanks to the citizens
of Alameda for your support of Bond Measure C. -