Earned Value Analysis by John Cornman - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Earned Value Analysis by John Cornman

Description:

Title: Earned Value Analysis Author: John McHugh Last modified by: Karl A Smith Created Date: 2/10/1999 4:40:46 PM Document presentation format: On-screen Show – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 18
Provided by: JohnMc167
Category:

less

Transcript and Presenter's Notes

Title: Earned Value Analysis by John Cornman


1
Earned Value AnalysisbyJohn Cornman
2
Introduction
  • Earned Value Analysis is an industry standard
    way to measure a projects progress, forecast its
    completion date and final cost, and provide
    schedule and budget variances along the way.
  • Based on just 3 data points, it can provide
    consistent, numerical indicators with which you
    can evaluate and compare projects.

3
The 3 fundamental metrics
  • Budgeted Cost of Work Performed.
  • Budgeted Cost of Work Scheduled.
  • Actual Cost of Work Performed.

4
Budgeted Cost of Work Performed
  • This is the Earned Value.
  • Abbreviated as BCWP.
  • For completed work, it is the cost originally
    budgeted to accomplish that work.
  • How much work was actually done?

5
Budgeted Cost of Work Scheduled
  • Abbreviated BCWS.
  • It is the total budgeted cost up to the analysis
    date.
  • Approximated by the total budget multiplied by
    the fraction of total project duration at the
    analysis date.
  • How much work should have been done?

6
Actual Cost of Work Performed
  • Abbreviated ACWP.
  • What it actually cost to accomplish all the work
    completed as of the analysis date.
  • What did the work that was actually done
    actually cost?

7
Derived Metrics
  • Schedule Variance (SV)
  • Schedule Performance Index (SPI)
  • Cost Variance (CV)
  • Cost Performance Index (CPI)

8
A Few More Acronyms
  • BAC - Budget At Completion
  • Total Original Budgeted Cost
  • Same as BCWS at completion
  • EAC - Estimate At Completion
  • Cumulative Actuals Estimate-To-Complete
  • VAC - Variance At Completion
  • Forecast of final cost variance

9
Doing The Math
  • SV BCWP - BCWS
  • Negative means Behind Schedule
  • SPI BCWP / BCWS
  • Less than 1.00 means Behind Schedule
  • CV BCWP - ACWP
  • Negative means Over Budget
  • CPI BCWP / ACWP
  • Less than 1.00 means Over Budget
  • EAC BAC / CPI

10
An Example Lemonade
  • Make 1,000 cups over 50 days
  • Steady rate of 20 cups per day
  • Budgeted cost per cup is 0.50
  • Total project budget is 500

11
Lemonade Progress
  • At end of day 10
  • 150 cups have been made
  • Total actual cost is 90 (ACWP)

12
Lemonade Status
  • BCWS 100
  • 10 days x 20 cups per day x .50/cup budget
  • BCWP 75 (Earned Value)
  • 150 cups x .50/cup budget
  • SV BCWP - BCWS -25
  • SPI BCWP / BCWS 0.75
  • CV BCWP - ACWP 75 - 90 -15
  • CPI BCWP / ACWP 0.833

13
Lemonade Forecast
  • EAC BAC / CPI 500 / 0.833 600
  • VAC BAC - EAC 500 - 600 100
    (unfavorable)
  • Schedule at Completion 50 / SPI 50 / 0.75
    66.67 days

14
MS Project 98 Support
15
Five Simple Criteria forEarned Value Applications
  • 1. Define (scope) the project. . .with a WBS
  • 2. Plan and schedule the project scope
  • 3. Budget cost account plans to functions
  • 4. Establish and maintain a performance baseline
  • 5. Monitor performance and forecast final results
  • Fleming Hoppleman. 1996. Earned Value
    Management. PMI

16
(No Transcript)
17
Earned Value Management http//www.acq.osd.mil/pm
/
Write a Comment
User Comments (0)
About PowerShow.com