LCLS Ultrafast Science Instruments (LUSI) - PowerPoint PPT Presentation

About This Presentation
Title:

LCLS Ultrafast Science Instruments (LUSI)

Description:

Title: Director's Review Charts-PMCS Author: F.B. Fernandez Last modified by: dmitchell Created Date: 8/8/2006 10:19:49 PM Document presentation format – PowerPoint PPT presentation

Number of Views:172
Avg rating:3.0/5.0
Slides: 86
Provided by: FB8
Category:

less

Transcript and Presenter's Notes

Title: LCLS Ultrafast Science Instruments (LUSI)


1
LCLS Ultrafast Science Instruments (LUSI)
Project Management Control System
Felix B. Fernandez Project Controls August, 2008
2
PMCS
  • Topics
  • System Overview
  • PMCS Development Process
  • PMCS Current Status
  • Summary and Questions

3
PMCS Overview
  • The LUSI Project Management Control System
  • Complies with DOE Order 413.3A
  • Complies with the 32 criteria from ANSI/EIA-748-A
  • Complies with the LUSI Project Execution Plan
  • Modeled after the LCLS Project PMCS

4
PMCS Overview
5
PMCS Overview
SLAC Accounting System
Schedule Baseline
Analysis Tool Hammer
Schedule Reports
Cost Reports
6
PMCS Overview
  • LUSI PMCS is defined and controlled by LCLS
    Procedures
  • Earned Value Management System Description LCLS
    1.1-015
  • CA and WP Planning Procedure LCLS 1.1-018
  • Change Control Procedure LCLS 1.1-019
  • Project Schedule Procedure LCLS 1.1-020
  • Cost Estimating Procedure LCLS 1.1-021
  • Monthly Status and Reporting Procedure LCLS
    1.1-022
  • Subcontract Management Procedure LCLS 1.1-023

7
PMCS Overview
  • Using Primavera (P3) as the Scheduling tool
  • Have established a Project group with supporting
    project files maintained independently
  • LUSI Project Group
  • Project Management (SLAC)
  • XPP Instrument (SLAC)
  • CXI Instrument (SLAC)
  • XCS Instrument (SLAC)
  • Diagnostics and Common Optics (SLAC)
  • Controls and Data Acquisition (SLAC)
  • XPP and XCS Detector Systems (BNL)

8
PMCS Overview
  • Using Cobra as the Budgeting tool
  • Have created a Cobra project file for MIE funded
    effort.
  • The project also uses a web based tool called the
    PMCS Hammer that integrates Primavera, Cobra
    and Accounting data.
  • The PMCS Hammer is updated monthly following
    the month end cycle and provides team members a
    way of accessing/analyzing their data and writing
    their VARs.

9
PMCS Overview
10
PMCS Overview
11
PMCS Development Process
12
PMCS Development Process
  • Define Schedule and Budget assumptions
  • Finalize the WBS, WBS Dictionary
  • Finalize a Responsibility Assignment Matrix (RAM)
  • Finalize the Milestone Hierarchy and Dictionary
  • Finalize the set of SLAC/BNL Resources and Rates
  • Finalize the resource loaded Integrated Master
    Schedule
  • Use the Schedule baseline to create a Budget
    baseline
  • Establish a prelim Performance Measurement
    Baseline

13
PMCS Development Process
  • Schedule Assumptions
  • Within the funding limitations, get to an Early
    Science capability with the Instruments as early
    as possible.
  • Establish priority order of Instruments as XPP,
    CXI and XCS.
  • Establish multiple CD-4 milestones, one for each
    Instrument.
  • Components not required for Early Science
    operations can be installed for final CD-4
    milestone.
  • Establish multiple CD-3 milestones to allow
    procurement of components for each Instrument as
    early as possible.
  • Establish a complete performance measurement
    baseline for all project equipment and conduct
    one CD-2.
  • Assume a Long Lead Authorization approval for Key
    critical components following CD-2 and prior to
    CD-3.

14
PMCS Development Process
  • Budget Assumptions
  • Plan for an MIE funding profile of
  • Plan for a Continuing Resolution for the first
    half of FY2009 (approx. 500k/month).
  • The balance of FY2009 funding will be available
    in the third quarter(12M).
  • Use Resources and Rates (Direct/Indirect)
    provided by SLAC and BNL.

15
PMCS Development Process
  • Project WBS and WBS Dictionary
  • The Work Breakdown Structure has been placed
    under change control
  • PM-391-000-96
  • The WBS Dictionary has been updated to reflect
    the latest structure and has been placed under
    change control
  • PM-391-001-12
  • The Responsibility Assignment Matrix (RAM) has
    been developed that identifies Control Accounts
    and CA Managers

16
PMCS Development Process
  • Control Account Managers
  • T. Fornek - WBS 1.1 Project Management
  • J. Langton - WBS 1.2 XPP Instrument
  • P. Montanez - WBS 1.3 CXI Instrument
  • E. Bong - WBS 1.4 XCS Instrument
  • E. Ortiz - WBS 1.5 Diagnostics Common Optics
  • G. Haller - WBS 1.6 Controls Data Acquisition
  • Niels van Bakel - WBS 1.2.03 1.4.03 BNL
    Detectors
  • Except for BNL Detector effort

17
PMCS Development Process
  • Project Milestone Hierarchy and Dictionary
  • The Milestone Hierarchy has been created and
    defines the relationship between the levels of
    milestones.
  • Six levels of milestones have been identified
  • Level 1 2 - DOE
  • Level 3 Project
  • Level 4 Instruments/Systems
  • Level 5 Interface / Handoff
  • Level 6 Commitments / Awards
  • The Milestone Dictionary has been developed to
    assure a thorough understanding of agreements

18
PMCS Development Process
Several types of Level 5, Interface / Handoff
Milestones have been defined and represent
contractual agreements. LUSI is currently
monitoring 904 Interface Milestones
19
PMCS Development Process
20
PMCS Development Process
Level 6 milestones have been identified as the
Awards of subcontracts / procurements and
supports funding reconciliations
efforts. Planning when the budget is to be spent
will support performance measurement. LUSI is
currently monitoring 224 Award Milestones.
21
PMCS Development Process
22
PMCS Development Process
  • Project Resources and Rates
  • Define a set of Resources for effort to be
    performed by SLAC with the appropriate planning
    rates.
  • Define a set of Resources for effort to be
    performed by BNL with the appropriate planning
    rates.
  • Use the appropriate indirect rates, as defined by
    SLAC/BNL, and apply to the direct rates as
    defined.
  • Apply a consistent escalation to activities as
    they get scheduled.
  • The Bay Area uses a 4 escalation rate for labor
  • Used standard 2.3 escalation for non-labor

23
PMCS Development Process
  • Integrated Schedule Development Process
  • Use WBS as foundation to assure 100 of scope
    covered
  • Define the detailed tasks required to accomplish
    the scope
  • Define the required resources to accomplish the
    tasks
  • Based on the detailed Basis of Estimates
  • Define the optimal logic relationships between
    tasks
  • Incorporate all levels of DOE and Project
    milestones
  • Incorporate all Interface / handoff milestones.

24
PMCS Development Process
  • Integrated Schedule Development Process (cont.)
  • Validate links to confirm timephasing and float
    calculations are accurate and appropriate.
  • Where applicable, base activity durations on
    recent LCLS and/or related experience.
  • Define and use standard calendars throughout with
    all the appropriate non-work days.
  • Plan for a standard work week (8 hours/day 5
    days/week) except where appropriate.
  • Develop flexible and appropriate activity coding
    for reporting and summarizations

25
PMCS Development Process
  • Integrated Schedule Development Process (cont.)
  • Because the project recognizes the importance of
    managing schedule contingency like it manages
    money contingency, blocks of time will be built
    into the schedule to mitigate the inevitable
    schedule issues.
  • These reserves of time will be planned as
    activity relationship lags between the Project
    controlled Level 3 milestones and the DOE
    controlled Level 2 milestones.
  • These blocks of schedule contingency were used
    during the development of the detail schedules
    and were removed to set preliminary baseline
    dates. The blocks will be added back into the
    schedule to impose control over float utilization.

26
PMCS Development Process
  • The project has reserved time between DOE level
    2 milestones and DOE level 1 milestones to allow
    for DOE processing
  • Project Ready 40 days DOE Review 40 days
    CD-3a
  • Project Ready 60 days DOE Review 40 days
    CD-4a
  • Project Ready 40 days DOE Review 40 days
    CD-3b
  • Project Ready 60 days DOE Review 40 days
    CD-4b
  • Project Ready 40 days DOE Review 40 days
    CD-3c
  • Project Ready 60 days DOE Review 40 days
    CD-4a

27
PMCS Development Process
  • For the purposes of managing Total Float, time
    reserves will be set aside between project level
    3 milestones and DOE level 2 milestones
  • Project Ready 40 days DOE Review 40 days
    CD-3a
  • Project Ready 60 days DOE Review 40 days
    CD-4a
  • Project Ready 40 days DOE Review 40 days
    CD-3b
  • Project Ready 60 days DOE Review 40 days
    CD-4b
  • Project Ready 40 days DOE Review 40 days
    CD-3c
  • Project Ready 60 days DOE Review 40 days
    CD-4a

28
PMCS Development Process
Each one of the 3 Instruments will have 100 days
of schedule contingency controlled by the project
office.
29
PMCS Development Process
  • In addition to the WBS, project phase coding for
    each activity will facilitate the creation of
    summary schedules as well as define the budget
    work packages.
  • Management / Administration
  • Design / Engineering
  • Procurement
  • Subcontract
  • Fabrication / Assembly
  • Testing
  • Installation

30
PMCS Development Process
  • Additional activity coding will facilitate
    sorting, filtering and additional summarizations
  • Work Breakdown Structure
  • Control Account number
  • Work Package number
  • Project Phase
  • Milestone Level
  • Control Account Manager name
  • Performance Measurement Technique
  • Earned Value Milestone (EVM) ID number
  • EVM Weight
  • Design Maturity
  • Judgment Factor

31
PMCS Development Process
  • Funding Reconciliation
  • The project started with a bottom-up planning
    approach which required budget authority
    inconsistent with the levels that were
    established.
  • Reconciliation required the identification of
    opportunities and the prioritizations of effort
    to adjust for funding issues at the lowest level.
  • The project next used a iterative top-down
    approach to shift entire blocks of effort to
    optimize the schedule flow while accelerating the
    Instrument availability.

32
PMCS Development Process
  • Once the schedule was iterated and a reasonable
    schedule was achieved that met the project
    objectives and stayed within the available
    funding, the preliminary schedule baseline was
    established.
  • With a baseline established in the Primavera
    file, the next step was to import the schedule
    data into Cobra to create the budget baseline and
    to establish a preliminary performance
    measurement baseline (PMB).

33
PMCS Development Process
  • Control Account and Work Package planning is
    based entirely on the time-phasing as defined by
    the schedule.
  • Work packages are based on the project phase and
    represents the cost collection intersection with
    the SLAC accounting system.
  • The work package is the lowest level at which
    earned value is calculated.

34
PMCS Development Process
  • The majority of the near term effort for the
    project will be focused on Engineering and
    Design.
  • Procurement, Subcontract, Fabrication Assembly,
    Testing and Installation work packages are coded
    as Planning Packages.
  • The detail planning for work packages coded as
    planning packages will be reassessed at the
    appropriate time.

35
PMCS Development Process
LUSI uses only a subset of the Performance
Measurement Technique (PMT) codes used by Cobra
to calculate Earned Value are coded into the
schedule as a reference
36
PMCS Status
37
Critical Decision Requirements
  • Employ an Earned Value Management System that is
    compliant with ANSI/EIA-748-A-1998 for projects
    with a Total Project Cost or Environmental
    Management Total Project Cost greater than or
    equal to 20M. Projects having a Total Project
    Cost or Environmental Management Total Project
    Cost between 20M and 50M must have an Earned
    Value Management System that is self-certified by
    the contractor as ANSI/EIA-748-A-1998 compliant.
    Projects having a Total Project Cost or
    Environmental Management Total Project Cost
    greater than or equal to 50M require an
    ANSI/EIA-748-A-1998 compliant system certified by
    the Office of Engineering and Construction
    Management. For projects not required to utilize
    an Earned Value Management System (e.g., firm
    fixed-price contract projects), an alternative
    performance management system must be described
    in the Project Execution Plan.
  • Completed SLAC/LCLS Project was reviewed and
    successfully demonstrated compliance at a review
    in June 2008
  • Subsequent to the June review a formal letter
    from DOE was received confirming the compliance
    of the SLAC Earned Value Management System.

38
Critical Decision Requirements
39
Critical Decision Requirements
  • Perform a Performance Baseline Validation
    External Independent Review or a Performance
    Baseline Validation Independent Project Review.
    External Independent Reviews are conducted by the
    Office of Engineering and Construction Management
    to validate the Performance Baseline for projects
    with a Total Project Cost or Environmental
    Management Total Project Cost greater than or
    equal to 100M. Independent Project Reviews are
    conducted by the Project Management Support
    Office to validate the Performance Baseline for
    projects with a Total Project Cost or
    Environmental Management Total Project Cost less
    than 100 M.
  • The Independent Review is to be accomplished as
    part of the CD-2 review

40
EIR Lines of Inquiry
EIR ELEMENT COMMENT CD2 Ready
1. Work Breakdown Structure PM-391-000-96 (Structure) ?
2. Project Cost Resource Loaded Schedule Working baselines set as of month end March 2008 for both the schedule in P3 and the project cost in Cobra ?
3. Cost Schedule Assumptions Covered in this presentation ?
4. Critical Path Critical paths for CD-4a, CD-4b and CD-4c available ?
5. Risk Management Mgmt presentation ?
6. Funding Profile Mgmt presentation ?
7. Project Controls/EVMS Overview and status covered in this presentation ?
8. Basis of Design Engineering presentation ?
9. Design Review Engineering presentation ?
10. System Functions Reqs Engineering presentation ?
11. Sustainability Not applicable ?
12. Hazards Analysis PM-391-001-01 ?
13. Value Management/Engineering LUSI Value Management Plan (Doc No. PM-391-000-02) ?
14. Start-up Test Plan SP-391-001-15, -16, -17 (XPP, CXI, XCS) ?
15. Project Execution Plan Draft ready for signature pending CD-2 review changes ?
16. Acquisition Strategy ?
17. Integrated Project Team This presentation the PEP ?
41
PMCS Status
42
PMCS Status
  • Using Primavera (P3) as the Scheduling tool
  • Currently the statistics for the LUSI Project
    group with supporting project files are
  • LUSI Project Group - 4131 activities 6159
    relationships
  • Project Management (SLAC) - 191 activities
  • XPP Instrument (SLAC) - 531 activities
  • CXI Instrument (SLAC) - 899 activities
  • XCS Instrument (SLAC) - 539 activities
  • Diagnostics and Common Optics (SLAC) - 599
    activities
  • Controls and Data Acquisition (SLAC) - 1297
    activities
  • XPP and XCS Detector Systems (BNL) - 75 activities

43
LUSI Project Summary Schedule
44
LUSI Critical Paths/Envelopes
  • Schedule Critical Path(s)
  • Because each Instrument represents a separate
    major deliverable, critical paths have been
    identified and are being monitored to the Approve
    Start of Operations milestones
  • CD-4a for the XPP Instrument
  • CD-4b for the CXI Instrument
  • CD-4c for the XCS Instrument
  • As a general rule, critical paths/envelopes are
    regularly monitored for all three instruments and
    the two supporting systems.

45
XPP Schedule Critical Path
Driving Milestones LL Approval, CD-3 CD-4
Diffractometer Design Effort
Diffractometer Awards Vendor effort
46
XPP Schedule Critical Path
Diffractometer deliveries to the Installation
effort
47
CXI Schedule Critical Path
Driving Milestones LL Approval, CD-3 CD-4
KB Mirrors Reqmts/Design Effort
KB Mirrors AWARD Vendor Design
Post Vendor Effort and Installation
48
CXI Schedule Critical Path
49
XCS Schedule Critical Path
Driving Milestones LL Approval, CD-3, CD-4
Funding M/S
Delayed Design Start due to Funding
XCS Path moves to DCO Procurements
XCS Instrument Installation effort
50
XCS Schedule Critical Path
Design initial procurement was completed for
the XPP Instrument
Procurement of DCO components delayed to FY11 due
to funding
51
XCS Schedule Critical Path
52
DCO Schedule Critical Envelope
DCO has one design effort and multiple
procurements to support the Instrument reqmts.
The project will monitor strings of activities
with the least float
53
DCO Schedule Critical Envelope
54
CDA Schedule Critical Envelope
CDA has multiple deliveries to the instruments
and is heavily driven by their needs. The project
will monitor strings of activities with the least
float
55
CDA Schedule Critical Envelope
56
PMCS Status
57
PMCS Status
58
PMCS Status
59
PMCS Status
60
PMCS Status
61
PMCS Hammer
62
Statusing and Reporting
SLAC Accounting System
Schedule Baseline
Analysis Tool Hammer
Schedule Reports
Cost Reports
63
Statusing and Reporting
LUSI Project data is now stored on the LCLS
website. https//slacspace.slac.stanford.edu/sites
/LCLS20Document20Storage/default.aspx Toward
the bottom theres a PMCS section.
64
Statusing and Reporting
PMCS data will be stored and available in the
folders as described. The PMCS Hammer is an
interactive tool team members will use to view,
analyze data and write VARs
65
Statusing and Reporting
The PMCS Hammer is a utility that was customized
for SLAC/LCLS that integrates Primavera, Cobra
and Accounting data for any team member to use.
The LCLS Hammer and LUSI Hammer pages are access
controlled and access is granted as appropriate.
66
Statusing and Reporting
The Drilldown CPR and DCE will probably be the
most often used utilities, but other information
is available.
67
Statusing and Reporting
The CPR Drilldown identifies areas that have
broken a threshold that requires a VAR.
68
Statusing and Reporting
By double-clicking on the highlight variance, the
VAR form will be enabled.
69
In Conclusion
  • The project set preliminary schedule and budget
    baselines as of March 2008.
  • The project team is ready for CD-2. We are ready
    to formally establish a performance measurement
    baseline and to proceed with the project.
  • Thank you for your participation

70
PMCS Backup
71
PMCS Status
72
PMCS Status
73
PMCS Status
74
PMCS Status
75
PMCS Status
76
PMCS Status
77
PMCS Status
78
PMCS Status
79
PMCS Status
80
PMCS Status
81
PMCS Status
82
PMCS Status
83
Milestones with PO Contingency
84
Milestones without PO Contingency
85
Milestones with no Funding Limits
Write a Comment
User Comments (0)
About PowerShow.com