Title: FACILITY LAYOUT
1FACILITY LAYOUT
- Facility layout means
- the configuration of departments, work
centers, and equipment, with particular emphasis
on the flow patterns of materials and people
around, into, and within buildings. - Layout decisions are very important because they
- - Require substantial investments of money
and effort - - Involve long-term commitments
- - Have significant impact on cost and
efficiency of short-term operations
2Characteristics of the Facility Layout Decisions
- Location of the work centers and departments
impacts the flow through the system. - The layout can affect productivity and costs
generated by the system. - Layout alternatives are limited by
- the amount and type of space required for the
various areas - the amount and type of space available
- the operations strategy
- . . . more
3Characteristics of the Facility Layout Decision
- Layout decisions tend to be
- Infrequent
- Expensive to implement
- Studied and evaluated extensively
- Long-term commitments
4Basic Layout Forms
- Process
- Product
- Cellular
- Fixed position
- Hybrid
5Process (Job Shop) Layouts
- Equipment that perform similar processes are
grouped together - Used when the operations system must handle a
wide variety of products in relatively small
volumes (i.e., flexibility is necessary)
6Process Layout
Process Layout (functional)
Used for Intermittent processing Job Shop or Batch
7Characteristics of Process Layouts
- General-purpose equipment is used
- Changeover is rapid
- Material flow is intermittent
- Material handling equipment is flexible
- Operators are highly skilled
- Technical supervision is required
- Planning, scheduling and controlling functions
are challenging - Production time is relatively long
- In-process inventory is relatively high
8Product (Assembly Line) Layouts
- Operations are arranged in the sequence required
to make the product - Used when the operations system must handle a
narrow variety of products in relatively high
volumes - Operations and personnel are dedicated to
producing one or a small number of products
9Product Layout
Figure 6.4
Raw materials or customer
Station 2
Station 3
Station 4
Finished item
Station 1
Material and/or labor
Material and/or labor
Material and/or labor
Material and/or labor
Used for Repetitive or Continuous Processing
10Characteristics of Product Layouts
- Special-purpose equipment are used
- Changeover is expensive and lengthy
- Material flow approaches continuous
- Material handling equipment is fixed
- Operators need not be as skilled
- Little direct supervision is required
- Planning, scheduling and controlling functions
are relatively straight-forward - Production time for a unit is relatively short
- In-process inventory is relatively low
11Cellular Manufacturing (CM) Layouts
- Operations required to produce a particular
family (group) of parts are arranged in the
sequence required to make that family - Used when the operations system must handle a
moderate variety of products in moderate volumes
12Characteristics of CMRelative to Process Layouts
- Equipment can be less general-purpose
- Material handling costs are reduced
- Training periods for operators are shortened
- In-process inventory is lower
- Parts can be made faster and shipped more quickly
13Characteristics of CMRelative to a Product Layout
- Equipment can be less special-purpose
- Changeovers are simplified
- Production is easier to automate
14Fixed-Position Layouts
- Product remains in a fixed position, and the
personnel, material and equipment come to it - Used when the product is very bulky, large, heavy
or fragile
15Hybrid Layouts
- Actually, most manufacturing facilities use a
combination of layout types. - An example of a hybrid layout is where
departments are arranged according to the types
of processes but the products flow through on a
product layout.
16New Trends in Manufacturing Layouts
- Designed for quality and flexibility
- Ability to quickly shift to different product
models or to different production rates - Cellular layout within larger process layouts
- Automated material handling such as automated
guided vehicle systems (AGVs)and automated
storage and retrieval sytems (AS/RS) - U-shaped production lines have potential to
improve employee morale - More open work areas with fewer walls,
partitions, or other obstacles - Smaller and more compact factory layouts
- Less space provided for storage of inventories
throughout the layout
17A U-Shaped Production Line
18Designing and Analyzing a Product Layout
- Line Balancing Problem
- Characteristics
- Inputs
- Design Procedure
- How Good Is The Layout?
19Line Balancing Problem
- Work stations are arranged so that the output of
one is an input to the next, i.e., a series
connection - Layout design involves assigning one or more of
the tasks required to make a product to work
stations - . . . more
20Line Balancing Problem
- The objective is to assign tasks to minimize the
workers idle time, therefore idle time costs,
and meet the required production rate for the
line - In a perfectly balanced line, all workers would
complete their assigned tasks at the same time
(assuming they start their work simultaneously) - This would result in no idle time
- . . . more
21Line Balancing Problem
- Unfortunately there are a number of conditions
that prevent the achievement of a perfectly
balanced line - The estimated times for tasks
- The precedence relationships for the tasks
- The combinatorial nature of the problem
22Inputs
- The production rate required from the product
layout or the cycle time. - Cycle time is the maximum time allowed at each
workstation to complete its set of tasks on a
unit. The cycle time is the reciprocal of the
production rate and visa versa. - All of the tasks required to make the product
- It is assumed that these tasks can not be divided
further - . . . more
23Inputs
- The estimated time to do each task
- The precedence relationships between the tasks
- These relationships are determined by the
technical constraints imposed by the product - These relationships are displayed as a network
known as a precedence diagram
24Precedence Diagram
Precedence diagram Tool used in line balancing
to display elemental tasks and sequence
requirements
25Line Balancing Procedure
- Determine which tasks must be performed to
complete one unit of a product - Draw a precedence diagram which shows the
sequence in which the tasks must be performed. - Estimate task times
- 4 Calculate the cycle time for the line.
Remember the cycle time is the reciprocal of the
production rate. Make sure the cycle time is
expressed in the same time units as the estimated
task times. - . . . more
26Line Balancing Procedure
- Calculate the minimum number of workstations that
can provide the required production rate. - Cycle TimeProductive Time per hour / Demand per
hour - min of workstations Sum of all task times /
Cycle Time - 6. Use a line-balancing heuristic such as
longest-task-time heuristic to assign tasks to
workstations so that the production line is
balanced.
27Design Procedure
- 7. Open a new workstation with the full cycle
time remaining. - 8. Determine which tasks are feasible, i.e., can
be assigned to this work station at this time.
For a task to be feasible, two conditions must be
met - All tasks that precede that task must have
already been assigned - The estimated task time must be less than or
equal to the remaining cycle time for that work
station.
28Design Procedure
- Note that if there is only one feasible task,
assign it to the work station. If there is more
than one feasible task, use the heuristic (step
6) to determine which task to assign. Reduce the
work stations remaining cycle time by the
selected tasks time. - If there are no feasible tasks and
assignments to that work station are complete, go
back to step 7 (or stop, if all tasks have been
assigned). -
29Longest-Task-Time Heuristic
- Heuristic methods, based on simple rules, have
been used to develop very good, not optimal,
solutions to line balancing problems. - Longest-Task-Time Heuristic - adds tasks to a
workstation one at a time in the order of task
precedence, choosing - when a choice must be made
- the task with the longest time.
30How Good Is the Design?
31Example 1 The ALB Problem
- Youve just been assigned the job a setting up an
electric fan assembly line with the following
tasks
32Example 1 The ALB Problem The Precedence Diagram
- Which process step defines the maximum rate of
production?
33Example 1 The ALB ProblemThe Bottleneck
34Example 1 The ALB Problem We want to assemble
100 fans per day
- What do these numbers represent?
35Example 1 The ALB Problem We want to assemble
100 fans per day
Why should we always round up?
36Example 1 The ALB ProblemSelected Task
Selection Rules
- Primary Assign tasks according to the largest
number of following tasks. - Secondary (tie-breaking) Assign tasks in order
of the longest operating time
37Example 1 The ALB ProblemSelected Task
Selection Rules
38Station 3
Slide 37 of 96
39Station 3
A (4.2-22.2)
Slide 38 of 96
40Station 3
A (4.2-22.2) B (2.2-11.2)
Slide 39 of 96
41Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
Slide 40 of 96
42Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
Slide 41 of 96
43Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
Slide 42 of 96
44Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3
Slide 43 of 96
45Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3
Slide 44 of 96
46Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3 E (3-.5)2.5
Slide 45 of 96
47Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3 E (3-.5)2.5 F (2.5-1)1.5
Slide 46 of 96
48Station 3
D (4.2-1.2)3 E (3-.5)2.5 F (2.5-1)1.5 H
(1.5-1.4).1
C (4.2-3.25).95
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2)
Idle.2 Idle.95 Idle.1
Slide 47 of 96
49Example 1 The ALB Problem
- Which station is the bottleneck?
- What is the effective cycle time?