FACILITY LAYOUT - PowerPoint PPT Presentation

About This Presentation
Title:

FACILITY LAYOUT

Description:

Facility layout means: the configuration of departments, work centers, and equipment, with particular emphasis on the flow patterns of materials and people around ... – PowerPoint PPT presentation

Number of Views:952
Avg rating:3.0/5.0
Slides: 49
Provided by: MickPeter5
Category:

less

Transcript and Presenter's Notes

Title: FACILITY LAYOUT


1
FACILITY LAYOUT
  • Facility layout means
  • the configuration of departments, work
    centers, and equipment, with particular emphasis
    on the flow patterns of materials and people
    around, into, and within buildings.
  • Layout decisions are very important because they
  • - Require substantial investments of money
    and effort
  • - Involve long-term commitments
  • - Have significant impact on cost and
    efficiency of short-term operations

2
Characteristics of the Facility Layout Decisions
  • Location of the work centers and departments
    impacts the flow through the system.
  • The layout can affect productivity and costs
    generated by the system.
  • Layout alternatives are limited by
  • the amount and type of space required for the
    various areas
  • the amount and type of space available
  • the operations strategy
  • . . . more

3
Characteristics of the Facility Layout Decision
  • Layout decisions tend to be
  • Infrequent
  • Expensive to implement
  • Studied and evaluated extensively
  • Long-term commitments

4
Basic Layout Forms
  • Process
  • Product
  • Cellular
  • Fixed position
  • Hybrid

5
Process (Job Shop) Layouts
  • Equipment that perform similar processes are
    grouped together
  • Used when the operations system must handle a
    wide variety of products in relatively small
    volumes (i.e., flexibility is necessary)

6
Process Layout
Process Layout (functional)
Used for Intermittent processing Job Shop or Batch
7
Characteristics of Process Layouts
  • General-purpose equipment is used
  • Changeover is rapid
  • Material flow is intermittent
  • Material handling equipment is flexible
  • Operators are highly skilled
  • Technical supervision is required
  • Planning, scheduling and controlling functions
    are challenging
  • Production time is relatively long
  • In-process inventory is relatively high

8
Product (Assembly Line) Layouts
  • Operations are arranged in the sequence required
    to make the product
  • Used when the operations system must handle a
    narrow variety of products in relatively high
    volumes
  • Operations and personnel are dedicated to
    producing one or a small number of products

9
Product Layout
Figure 6.4
Raw materials or customer
Station 2
Station 3
Station 4
Finished item
Station 1
Material and/or labor
Material and/or labor
Material and/or labor
Material and/or labor
Used for Repetitive or Continuous Processing
10
Characteristics of Product Layouts
  • Special-purpose equipment are used
  • Changeover is expensive and lengthy
  • Material flow approaches continuous
  • Material handling equipment is fixed
  • Operators need not be as skilled
  • Little direct supervision is required
  • Planning, scheduling and controlling functions
    are relatively straight-forward
  • Production time for a unit is relatively short
  • In-process inventory is relatively low

11
Cellular Manufacturing (CM) Layouts
  • Operations required to produce a particular
    family (group) of parts are arranged in the
    sequence required to make that family
  • Used when the operations system must handle a
    moderate variety of products in moderate volumes

12
Characteristics of CMRelative to Process Layouts
  • Equipment can be less general-purpose
  • Material handling costs are reduced
  • Training periods for operators are shortened
  • In-process inventory is lower
  • Parts can be made faster and shipped more quickly

13
Characteristics of CMRelative to a Product Layout
  • Equipment can be less special-purpose
  • Changeovers are simplified
  • Production is easier to automate

14
Fixed-Position Layouts
  • Product remains in a fixed position, and the
    personnel, material and equipment come to it
  • Used when the product is very bulky, large, heavy
    or fragile

15
Hybrid Layouts
  • Actually, most manufacturing facilities use a
    combination of layout types.
  • An example of a hybrid layout is where
    departments are arranged according to the types
    of processes but the products flow through on a
    product layout.

16
New Trends in Manufacturing Layouts
  • Designed for quality and flexibility
  • Ability to quickly shift to different product
    models or to different production rates
  • Cellular layout within larger process layouts
  • Automated material handling such as automated
    guided vehicle systems (AGVs)and automated
    storage and retrieval sytems (AS/RS)
  • U-shaped production lines have potential to
    improve employee morale
  • More open work areas with fewer walls,
    partitions, or other obstacles
  • Smaller and more compact factory layouts
  • Less space provided for storage of inventories
    throughout the layout

17
A U-Shaped Production Line
18
Designing and Analyzing a Product Layout
  • Line Balancing Problem
  • Characteristics
  • Inputs
  • Design Procedure
  • How Good Is The Layout?

19
Line Balancing Problem
  • Work stations are arranged so that the output of
    one is an input to the next, i.e., a series
    connection
  • Layout design involves assigning one or more of
    the tasks required to make a product to work
    stations
  • . . . more

20
Line Balancing Problem
  • The objective is to assign tasks to minimize the
    workers idle time, therefore idle time costs,
    and meet the required production rate for the
    line
  • In a perfectly balanced line, all workers would
    complete their assigned tasks at the same time
    (assuming they start their work simultaneously)
  • This would result in no idle time
  • . . . more

21
Line Balancing Problem
  • Unfortunately there are a number of conditions
    that prevent the achievement of a perfectly
    balanced line
  • The estimated times for tasks
  • The precedence relationships for the tasks
  • The combinatorial nature of the problem

22
Inputs
  • The production rate required from the product
    layout or the cycle time.
  • Cycle time is the maximum time allowed at each
    workstation to complete its set of tasks on a
    unit. The cycle time is the reciprocal of the
    production rate and visa versa.
  • All of the tasks required to make the product
  • It is assumed that these tasks can not be divided
    further
  • . . . more

23
Inputs
  • The estimated time to do each task
  • The precedence relationships between the tasks
  • These relationships are determined by the
    technical constraints imposed by the product
  • These relationships are displayed as a network
    known as a precedence diagram

24
Precedence Diagram
Precedence diagram Tool used in line balancing
to display elemental tasks and sequence
requirements
25
Line Balancing Procedure
  • Determine which tasks must be performed to
    complete one unit of a product
  • Draw a precedence diagram which shows the
    sequence in which the tasks must be performed.
  • Estimate task times
  • 4 Calculate the cycle time for the line.
    Remember the cycle time is the reciprocal of the
    production rate. Make sure the cycle time is
    expressed in the same time units as the estimated
    task times.
  • . . . more

26
Line Balancing Procedure
  • Calculate the minimum number of workstations that
    can provide the required production rate.
  • Cycle TimeProductive Time per hour / Demand per
    hour
  • min of workstations Sum of all task times /
    Cycle Time
  • 6. Use a line-balancing heuristic such as
    longest-task-time heuristic to assign tasks to
    workstations so that the production line is
    balanced.

27
Design Procedure
  • 7. Open a new workstation with the full cycle
    time remaining.
  • 8. Determine which tasks are feasible, i.e., can
    be assigned to this work station at this time.
    For a task to be feasible, two conditions must be
    met
  • All tasks that precede that task must have
    already been assigned
  • The estimated task time must be less than or
    equal to the remaining cycle time for that work
    station.

28
Design Procedure
  • Note that if there is only one feasible task,
    assign it to the work station. If there is more
    than one feasible task, use the heuristic (step
    6) to determine which task to assign. Reduce the
    work stations remaining cycle time by the
    selected tasks time.
  • If there are no feasible tasks and
    assignments to that work station are complete, go
    back to step 7 (or stop, if all tasks have been
    assigned).

29
Longest-Task-Time Heuristic
  • Heuristic methods, based on simple rules, have
    been used to develop very good, not optimal,
    solutions to line balancing problems.
  • Longest-Task-Time Heuristic - adds tasks to a
    workstation one at a time in the order of task
    precedence, choosing - when a choice must be made
    - the task with the longest time.

30
How Good Is the Design?
  • Balance Efficiency is

31
Example 1 The ALB Problem
  • Youve just been assigned the job a setting up an
    electric fan assembly line with the following
    tasks

32
Example 1 The ALB Problem The Precedence Diagram
  • Which process step defines the maximum rate of
    production?

33
Example 1 The ALB ProblemThe Bottleneck
34
Example 1 The ALB Problem We want to assemble
100 fans per day
  • What do these numbers represent?

35
Example 1 The ALB Problem We want to assemble
100 fans per day
Why should we always round up?
36
Example 1 The ALB ProblemSelected Task
Selection Rules
  • Primary Assign tasks according to the largest
    number of following tasks.
  • Secondary (tie-breaking) Assign tasks in order
    of the longest operating time

37
Example 1 The ALB ProblemSelected Task
Selection Rules
  • Precedence Diagram

38
Station 3
Slide 37 of 96
39
Station 3
A (4.2-22.2)
Slide 38 of 96
40
Station 3
A (4.2-22.2) B (2.2-11.2)
Slide 39 of 96
41
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
Slide 40 of 96
42
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
Slide 41 of 96
43
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
Slide 42 of 96
44
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3
Slide 43 of 96
45
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3
Slide 44 of 96
46
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3 E (3-.5)2.5
Slide 45 of 96
47
Station 3
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2) Idle
.2
C (4.2-3.25).95 Idle .95
D (4.2-1.2)3 E (3-.5)2.5 F (2.5-1)1.5
Slide 46 of 96
48
Station 3
D (4.2-1.2)3 E (3-.5)2.5 F (2.5-1)1.5 H
(1.5-1.4).1
C (4.2-3.25).95
A (4.2-22.2) B (2.2-11.2) G (1.2-1 .2)
Idle.2 Idle.95 Idle.1
Slide 47 of 96
49
Example 1 The ALB Problem
  • Which station is the bottleneck?
  • What is the effective cycle time?
Write a Comment
User Comments (0)
About PowerShow.com