Title: Non-regulated Interconnectors NECA Seminar
1Non-regulated InterconnectorsNECA Seminar
2Opening Remarks
3Introduction
- Code provisions
- programme
- key issues
4Obligations on promoter
- establish connection agreements with NSPs
- register as market participant
- provide an access undertaking to ACCC
- apply to NECA
5Obligations on NECA
- establish rules for market participation
- within two years of market launch, develop
provisions to address financial risk to promoter
as a result of need for augmentation
6Change in status
- provision to switch from non-regulated to
regulated link, subject to conditions - meets Code criteria and technical standards
- passes net public benefit test
7Programme
- a role for entrepreneurial interconnectors?
- a proponents perspective
- introduction to working group proposals
- market participation
- structural and competition issues
- extensions and alternatives
- overall assessment
- conclusions and next steps
8Key issues
- generator competitors or TNSP companions?
- regulated and non-regulated links can they
co-exist? - hermaphrodite links a freak of nature?
- access, market power how light-handed can we
be? - safe harbour provisions smothering at birth?
9WHY NON-REGULATED INTERCONNECTORS ?An advocacy
statement ..
- Stephen Orr
- Hazelwood Power
10A REGIONAL MARKET DESIGN
- NEM is regionalised - conscious choice
- Simplified version of full nodal pricing -
- few intra-regional constraints (in real regions)
- mechanism to redefine if constraints occur
- Inter-regional constraints create heavy risks for
participants market awakening 25 Nov 97
11NEMMCO IRH PROCESS
- Settlement Residue Auction (SRA) process
developed as interim access to SR to underwrite
inter-regional hedges and mitigate IR risk - Also developed view of the future, issues being
- network performance drivers and standards
- firm inter-regional access - leading to IRHs
- regulatory risk for investing participant - hence
non-regulated interconnectors
12ISSUES FOR PARTICIPANTS
- Particularly generators, but others too
- Interconnectors look like wires, but ...
- They perform like competitors, ie -
- They introduce remote generation as new entrants
into a region - Conversely they add remote load to a region
- They also potentially redefine the region
13INVESTMENT RISK
- Investment criteria for regulated interconnectors
dont match market criteria, eg - n-1 transmission reliability standard
- Demand with 10 probability of exceedance
- ACCC reviewing criteria for NEMMCO to approve
regulated status for interconnectors
14INVESTMENT RISK contd
- Regulated interconnectors see little investment
risk - if transmission planner sees the need,
customers pay until next optimisation - Even if investment rules become
market-commercial, regulated interconnector not
at risk of failure - Hence, some propose higher discount rates for
regulated interconnector assessments
15REASONABLE INVESTMENT CERTAINTY
- Regulated interconnectors threaten the price
signals which underpin local generation and
demand-side investment regulatory risk - Generation/demand investor confidence up if
interconnector faces equivalent market risk - If you think its a good deal, you build
it!If you dont, dont ask the market to
underwrite your errors
16NON-REGULATED INTERCONNECTORS
- Are competitively neutral
- Reduce the need for central intervention
- Require a change in thinking away from
conventional interconnector perspectives - Can be free-flowing and open like normal
transmission lines, or alternatively - Can be actively traded in the market through
price-differential/volume offers
17NON-REGULATED INTERCONNECTORS
- Potentially remove the need for regulated
interconnectors at all, ie - - if regulated rules changed to achieve competitive
neutrality, no for regulated - if commercial hurdles not met, governments and
others can build NRIs, and take the risk
18TODAYS SESSION
- Reflects the initial results of efforts of a
diverse industry group to define the nature and
operation of non-regulated interconnectors - The group has diverse views on some key issues,
but sufficient consensus on the fundamentals to
encourage others to join the debate
19A Proponents Perspective
- Tony Cook
- TransÉnergie Australia
20Outline
- Code requirements
- DirectLink
- Transmission in a competitive market
21National Electricity CodeObligations of
Proponents
- Clause 5.6.6 (f) requires a connection applicant,
in relation to a non-regulated interconnector,
to - apply to NECA in accordance with clause 3.10 to
determine the rules that will apply in terms of
the connection applicants participation in the
market as a market participant in relation to
that interconnector. - TransEnergie Australia and NorthPower made
application to NECA on 1 October 1998.
22National Electricity CodeObligations of NECA
- Clause 5.6.6 (g) provides that, if an application
is made to NECA under clause 5.6.6 (f) (4), NECA
must determine those rules within a reasonable
time after receipt of the application.
23DirectLink Features
- 180 MVA capacity between Qld and NSW.
- DC technology.
- 1 January 2000 commissioning date.
- Non-regulated interconnector
- Recoup costs through trading in financial
instruments tied to the interconnector capacity.
24Geographic Location
25Transmission in Competitive Markets
- Objective
- Provide sufficient transmission capacity to
ensure a competitive energy market, while fairly
and efficiently pricing the use of that capacity.
- Outcomes
- Facilitate competition in
- generation,
- transmission (as an alternative to local
generation).
26Transmission in Competitive Markets
- Commercial framework for transmission expansion
- Top Down projects for reliability and
competition - determined by NEMMCO - Bottom Up projects in response to energy price
differentials - proposed by developers.
27Transmission in Competitive Markets
- Top Down Projects
- Competitive tendering e.g. Victoria
- Bottom Up Projects
- Entrepreneurial interconnectors.
28Benefits to Consumers and Generators
- Effective competition in generation.
- Lower transmission costs.
29Introduction to the Working Groups Proposals
30WGs Terms of Reference
- One of the groups terms of reference is -
- recommend rules to govern the participation of
entrepreneurial interconnectors in the national
electricity market and advise on implications for
other aspects of the market design such as
network augmentation criteria. - this is a problem - how can you write rules for
an unregulated interconnector? - need to define the boundary of acceptable
behaviour without being prescriptive
31WGs Terms of Reference
- Addressed in three stages
- identify safe harbour provisions
- define the degree of discretion used in other
approvals - define scope for future extensions and variations
to the safe harbour provisions - This workshop is a result of the first stage and
some progress has been made on the other stages - The work presented today is new and requires a
change in thinking - there are still many
challenges - inter-regional hedging
- completion of other stages etc
32Other Terms of Reference
- Remaining Tasks
- if possible recommend a practical and effective
implementation path for introducing firm
link-based inter-regional hedges, i.e.
inter-regional hedges that are underwritten by
settlements residues and are as firm as
practicable against residual risks such as those
associated with network availability. - advise on the scope and appropriateness of
aligning the inter-regional and intra-regional
hedging provisions with frameworks such as the
transmission congestion contract concept and
others. This should include identifying the
implications for other aspects of the market
design.
33What are Safe Harbour Provisions
- Safe harbour provisions.
- A set of provisions conformance to which would
ensure an applications approval. There is no
implication that non-conforming applications
would necessarily be rejected, although they
would not be assured of receiving approval. - not code requirements but a set of criteria to
judge automatic acceptability. - because we are naturally risk adverse the
provisions are conservative.
34What are Safe Harbour Provisions
- Obligations
- Configuration limits
- Must be scheduled
- Must have controllable flow
- Pay network service charges
- Enter into connection agreements
- Exposure to costs and benefits of interconnector
- NEMMCO to have power to direct
- Subject to competition
- Sunset clause
- Subject to market power provisions
- Ring-fencing provisions
- Must make an access undertaking
35What are Safe Harbour Provisions
- Rights
- Entitled to the spot market revenue
- Can enter into Reserve Trader contracts
- Option to convert to regulated status
- Having fulfilled the obligations, the
entrepreneurial interconnector has access to spot
market revenue
36Status of Working Group Paper
- The WG has not endorsed all the provisions
- There are still differing views
- However the WG has agreed that it is time for
wider consultation and exposure of the proposal - WG may need to review provisions in the light of
feedback from this workshop
37Post - implementation Review
- WG recommends post - implementation review
- gt one application but,
- lt 3 years
- Needed due to keep pace with innovation!
- Needed because the concepts are new and quite
different from other approaches - therefore need
to consider developments
38Definitions
- Interconnector. A network element that connects
networks located in different regions of the
National Electricity Market (NEM). - Entrepreneurial interconnector. An
interconnector for which there is an entitlement
to derive income through its participation in the
spot market. - Non-regulated interconnector. An entrepreneurial
interconnector for which there is no entitlement
to recover any revenue through regulated network
service charges.
39Definitions contd
- Regulated interconnector. An interconnector for
which there is an entitlement to recover a
determined level of revenue through the
imposition of regulated network service charges.
There is no entitlement to retain any additional
revenues arising from the operation of the
interconnector in the spot market.
40Definitions contd
- Hybrid interconnector. An entrepreneurial
interconnector for which there is an entitlement
to recover some revenue through the imposition of
regulated network service charges. As with other
entrepreneurial interconnectors, income may also
be obtained through participation in the spot
market. - A mix of regulated and non-regulated has been
identified but further work required. This and
general areas where the safe harbour provisions
can be extended in the future will be the subject
of Rod Ward and Dave Roberts talk at 215pm
41NECA WORSHOP ON ENTREPRENEURIAL INTERCONNECTORS
- Introduction - End User Perspectives
- Roman Domanski
- Executive Director
- Energy Users Group
- Sydney Airport Sheraton
- 8 December 1998
42Entrepreneurial Interconnectors
- Supportive of Concept
- Why?
- virtual generator competition for generators
- competition for TNSPs - right to provide
- adds depth to NEM by strengthening links between
regions - can help augmentation become more competitive
- consistent with reform
43Safe Harbours
44Safe Harbors Concept
- Could go without rules, but
- Rules provide some certainty for a new concept
- certainty for investors, owners customers
- may improve chances of getting proposals up
- Rules should not hinder proposals
- Need to be flexible enough to foster change
- but firm enough not to stop investment
45Need for Debate
- As rules are new and innovative, important to
expose to broader debate and get feedback. - Need to be prepared to modify SHP to take
account of informed comment. - Need to also consider links between this work and
ACCC review of regulated interconnectors
46Competition Issues
- Market Power
- considerable discussion about threshold market
shares - Access
- Ring Fencing
- Hybrids
- Conversion
- These issues need broader input
47The Future
- Monitor and review
- Adapt to practical experience NEM/reform
goalse.g. - review requirement that flow must be
independently controllable - perhaps move to calculating the price difference
with and without interconnector - Should all future links be entrepreneurial
- intra- inter-regional?
48Market Participation
- Stephen Wallace
- Snowy Mountains Hydro-Electric Authority
- Michael Green
- Transend Networks Pty Ltd
49Overview
- Market issues
- bidding, dispatch and pricing
- spot market revenues
- system security
- contracting
- Network issues
- configuration and controllability
- connection agreements and network pricing
50Spot Market Participation
- Networks characterised by
- economies of scale
- short run marginal costs are insufficient to
cover costs of optimally sized interconnector - Three models for interconnector operation
- passive participation
- bids capacity
- bids price differential (above marginal losses)
51Interconnector Market Model
- Passive participation - due to economies of scale
is likely to encourage undersized links - Bids capacity - subset of price differential
model - a capacity bid is equivalent to bidding two
prices, 0 and VoLL, with the MWs bid at 0 the
same as capacity offered - Bids price differential - best model
52Bidding Rebidding Price Differentials
- Similar to generators or customers
- 10 prices for each direction (monotonically
increasing) - For each price MWs of capacity offered for each
half hour - Total capacity offered each half hour is equal to
link capacity - Obliged to follow dispatch instructions and
provide PASA information
53Dispatch Pricing (SPD)
- Bidding model can be incorporated easily into SPD
framework - Objective function is maximise
- value of supply (demand bids dispatched)
- - cost of supply (gen offers dispatched)
- - cost of interconnector (link offers dispatched)
- - cost of ancillary services
54Dispatch Pricing (Ctd)
- Link energy balance
- export import link losses
- (this brings in dynamic marginal losses for flows
over link) - SPD essentially the same as now but current
interconnector violation penalties approach is
extended to transport capacity bids
55Spot Revenue (energy)
- Similar to other participants
- Metering at each terminal
- Prices at each terminal determined much the same
as for other participants - Since flows may change direction or be highly
variable there is an issue concerning choice of
marginal loss factors
56Spot Revenue (energy)
- export
- Buys F1 energy in region 1 at spot price adjusted
for marginal losses, SP1 x MLF1 - import
- Sells F2 energy in region 2 at spot price
adjusted for marginal losses, SP2 x MLF2 - revenue import - export
- Rev F2 x SP2 x MLF2 - F1 x SP1 x MLF1
- Note There are problems with flows and prices
on 5 minute dispatch interval vs half hour
averages
57Marginal Loss Factors (Prices for Energy at
Connection Points)
- Many possible models for marginal loss factors
(MLFs) - fixed
- variable with time of day/day of week/season etc
- variable with direction of flow and 1 or 2 above
- dynamic
- nodal pricing of connection point (dynamic
intra regional constraints)
58Ancillary services
- Co-optimisation approach allocates interconnector
capacity between energy and ancillary services - Interconnector receives spot market and ancillary
services income like other participants - Interconnector pays for ancillary services
- If optimal SPD will schedule ancillary services
to enhance flow
59System Security
- Same as for generators other participants
- NEMMCO has power to direct for system security
reasons - When directed interconnector is compensated in
the same way as for other participants (fair
market value -ACCC) - May be involved in Reserve Trader contracts
60Contracting
- Actively operates in contract market
- Offers inter-regional hedges (IRHs)
- May have firm access compensation arrangements
- Basically like any other participant
61Conclusion
- Market operation is much like a generator
- bidding
- requirement to be scheduled and provide
information - spot market revenue
- ancillary service income and charges
- subject to direction etc
- What about network connection, TUOS etc?
- Mike Green will reveal all
62(No Transcript)
63- TRANSEND NETWORKS PTY LTD
- MICHAEL GREEN
64CONFIGURATION NO. 1
Existing Interconnection
Region 2
Region 1
Proposed Interconnector
65- CONFIGURATION NO. 2
- Two Terminal Between Regions
- Regional Definitions
- Network Service Charges
- Bidding Scheduling
66- CONFIGURATION NO. 3
-
- 30MVA Minimum Capability
- In Line with Scheduled Generator, Clause
2.2.2 - Cross Zonal Boundary Windfalls
- Regulator Shopping
67- NEED FOR CONTROLLABILITY
- Follow Dispatch Instructions
- Avoid Adverse Impacts on other Network
Elements - Forms a Clear Basis for Settlements
68- FREE FLOWING
- Interconnector Actual Flows Depend Upon
- Generator Dispatch
- Customer Demands
- Network Characteristics
69- ISSUES IF NOT CONTROLLABLE
- Safe Harbour Does NOT Preclude This Option
- Need to Develop Basis of Settlements
- Need to Develop Basis of Compensation
70- CONNECTION AGREEMENTS
- Service Levels
- Connection Fees
- Arrangements Subject to Negotiation
71- CONNECTION AGREEMENTS
- CONNECTION FEES
- Dedicated Entry/Exit Assets - Payable by
Proponent - Attributable Agreed Deep Augmentation -
Payable by Proponent - Transmission Use of System - Matter for
Resolution
72- CONNECTION AGREEMENTS
- ISSUES NO. 1
- Is there a need for a level playing field
between - regulated non-regulated
interconnectors? - Regulated Face Stringent Regulatory Tests
- Non-regulated Face Connection Fees?
- Must Provide for Efficient Investment
- Interface with NECA Incidence Allocation
Review
73- CONNECTION AGREEMENTS
- ISSUES NO. 2
- See Appropriate Forward Looking Costs
- See Appropriate Forward Looking Benefits
- Difficulty With Identifying
- Magnitudes of Costs/Benefits
- Duration of Costs/Benefits
- Funding of Benefit Rebates
74- CONNECTION AGREEMENTS
- ISSUES NO. 3
- Should non-regulated interconnectors result
in - financial transfers between Network
Service Providers? - Many Factors Drive Financial Transfers.
75- SUMMARY
- MARKET ISSUES
- Spot Market Revenue
- Ancillary Services Revenue
- Required To Be Scheduled
- Able To Offer Into Market
- Subject To NEMMCO Direction
76- SUMMARY
- NETWORK ISSUES
- Configuration
- Controllable Flow
- Must Enter Into Connection Agreements
- Subject to Efficient Network Connection Fees
77STRUCTURAL AND COMPETITION ISSUESConversion to
Regulated Status, Sunset Clause, Market Power
Issues
- Stephen Orr
- Hazelwood Power
78CONVERSION TO REGULATED STATUS
- Safe harbour should allow interconnector owner to
apply for conversion to regulated status at any
time - Revenue entitlement assessed at the time
- Recognises uncertainty regarding non-regulated
design at present - hence may encourage investment
79CONVERSION TO REGULATED STATUS
- Also supports utilising economies of scale, eg
hybrid converts to fully regulated when justified - Proponent must not be shielded from commercial
risks, eg mis-assessment of demand or price - Hence apply rules at the time
- No scope for strategic alternation
80CONVERSION TO REGULATED STATUS
- Note -
- If rules for regulated interconnector investment
change to match commercial conditions, - Then why would the non-regulated interconnector
owner want the change to regulated status?
81SUNSET CLAUSE
- Conversion to regulated status offers protection
to the non-regulated interconnector investor - The sunset clause approach protects the market as
a whole from unexpected outcomes - Suggest 15 years minimum reasonable approval for
long life, high cost interconnectors - ACCC Code authorisation may limit approval period
to 2010
82MARKET POWER ISSUES
- Active trading models create potential for
exercise of market power - Economies of scale, easements etc may limit scope
for competitive interconnectors - Cross ownership potential
- Hence we have considered control to maximum of
35 of either interconnected areas as limit for
safe harbour
83MARKET POWER ISSUES
- Concentration of control could be limited by
divesting rights to the revenue stream, if
operational control ring-fenced - Cross-ownership with regulated interconnector
should be OK, provided ring-fencing in place
84MARKET POWER ISSUES
- However this proposal is arbitrary
- It excludes, for example, Delta and Macgen
immediately - There is a serious question whether the market
rules should endeavour to anticipate and
constrain market power - Perhaps safe harbour provisions should not be
specific - let ACCC decide case-by-case?
85EXPOSURE TO COMPETITION
- No restriction on entry of competing regulated
and non-regulated interconnectors - Providing they meet the criteria at the time
- This assumes level playing field through the
rules governing approval of regulated
interconnectors
86Entrepreneurial Interconnectors
Hugh Gleeson (United Energy) Ken Brunette
(Integral Energy)
87Exposure to competition
- No restrictions on the entry of competing
inter-connectors (regulated or unregulated) - Aim to achieve a level playing field to ensure
comfort of consistency in regulation - Various views
- (Generators) desire to force regulated
augmentations to be based on the same investment
criteria as unregulated. - (Retailers) preference to see a stable playing
field, not restrict regulated decision making. - (Customers) desire to see most efficient (lowest
cost) generation used first irrespective of
geographic location in NEM.
88Sunset clause
- Initial approval to operate as a non-regulated
inter-connector and actively participate in the
market may be limited to a specific interval - safeguard against undesirable unforeseen
outcomes. - proposed right to apply to convert to regulated
status and receive regulated revenue assessed on
the deprival value upon reaching the sunset
date. - fifteen year minimum approval proposed (by some
of group) as appropriate to match level of
investment. - May in practice be shorter horizon as the ACCC
Code authorisation expires in 2010. - No protection from effect of Code changes
intended by this clause
89Ring fencing
- Isolation from the operations of any co-owned
regulated network business - Ensure the operation is not influenced by
consequential profit or loss from the
non-regulated business. - Concern regarding potential to influence timing
of outages (by related regulated network
business) for unreasonable financial advantage.
90Submission of an access undertaking
- Access undertaking to be in the form specified in
the Code - Must be available in accordance with the Code.
- Applicable Code provisions will likely differ
from standard (as exist for regulated assets). - Right to trade (as determined) in the spot market
- No right to receive regulated revenues (Chapter
6) - ACCC acceptance of access undertaking to protect
the asset from declaration under the Trade
Practices Act.
91Beyond the Safe-Harbour
- Rod Ward - Delta Electricity
92Beyond the Safe Harbour - Overview
- Purpose of Safe Harbour Provisions
- Key Limitations of the Safe Harbour Provisions?
- Trading non-controlled interconnectors
- The Way Forward?
93Purpose of Safe Harbour
- Conformance to safe harbour provisions should
guarantee approval. - There is no implication that non-conforming
applications would necessarily be rejected
94Beyond the Safe Harbour
- Further work required to
- explore the scope for further extensions and
variations - define the degree of discretion for other
applications (within and beyond safe harbour)
95Key Limitations of the Safe Harbour Provisions -
case examples
- The provisions do not cover
- intra-regional interconnectors
- non-transmission interconnector capacity upgrade
- free flowing AC links - loop and parallel flows
- participant or an interconnector controlling more
than 35 of the capacity in either of the supply
regions - hybrid of regulated and non regulated
interconnection
96Key Limitations of the Safe Harbour Provisions -
case examples
- The provisions do not cover
- intra-regional interconnectors
- non-transmission interconnector capacity upgrade
- free flowing AC links - loop and parallel flows
- participant or an interconnector controlling more
than 35 of the capacity in either of the supply
regions - hybrid of regulated and non regulated
interconnection
definition of capacity and access to the
market (if controllable or switchable could be
considered)
97Key Limitations of the Safe Harbour Provisions -
case examples
- The provisions do not cover
- intra-regional interconnectors
- non-transmission interconnector capacity upgrade
- free flowing AC links - loop and parallel flows
- participant or an interconnector controlling more
than 35 of the capacity in either of the supply
regions - hybrid of regulated and non regulated
interconnection
Impact on the capacity of incumbents and
competitive trading solutions
98Interconnector Trading
- energy supplied to a region does not have to be
delivered by that interconnector -
inter-regional capacity can be shared - an interconnector flow does not have to be
controlled - inter-regional transfers is
controlled by generator loading in merit order
99Concept of Notional Capacity
- Parallel interconnectors treated as a single
notional interconnector - revenues are split according to relative
capabilities and bids (notional dispatch) - However, complexities arise when the capacity of
an incumbent is affected or loop flows occur.
100Concept of Notional CapacityBidding
- Similar to generators
- 10 prices for each direction (monotonically
increasing) - for each price MWs of capacity offered in each
half hour (total capacity equal to the link) - Any regulated capacity bid at zero
- dispatch algorithm will dispatch lowest merit
order bids up to the notional capacity of all
interconnection capacity - However, residual capacity could be constrained
off
101Concept of Notional CapacityCase Study -
Capacity rights affected
- Examples
- New interconnector impacts the capacity of
another remote interconnector e.g the capacity of
SA/NSW interconnector is limited by flows on the
NSW/VIC interconnector. - Total capacity of two parallel interconnectors
less than sum of individual capacity. - Issues
- Prior capacity rights - incremental capacity only
recognised? - No prior capacity rights - full competitive
bidding and residual capacity effectively
constrained off? - Technical prerequisites?
- Firm access to network?
102Loop Flows
- Example
- Additional complexity on parallel interconnectors
where a connection to a region at two remote
points create loop flows. - Issues
- current regional model inadequate - more regions
or progression to nodal model approach - prior rights to capacity become increasing
complex - complexities of notional capacity allocations
would have to be modelled, continuous assessed
and resolved in dispatch
loop flows could resolve to parallel flows
103Key Limitations of the Safe Harbour Provisions -
case examples
- The provisions do not cover
- intra-regional interconnectors
- non-transmission interconnector capacity upgrade
- free flowing AC links - loop and parallel flows
- participant or an interconnector controlling more
than 35 of the capacity in either of the supply
regions - hybrid of regulated and non regulated
interconnection
anti-competitive conduct, control, timing of
problem
104Market Power
- Why is an interconnector different to generation?
- When is it likely to be material?
- Is it ownership, control or cross-subsidy between
competitive businesses? - Does it safe harbour anti-competitive behaviour
of a substantial interconnector - ACCC issue - Possible Solutions
- provisions of the TPA appropriate to apply to all
owners of interconnectors - Transition requirement
- assets ring-fenced with separate reporting
requirements - defined reasonable level of capacity contracts in
the market - Alternative - safe harbour applies to small
interconnectors only, regardless of ownership
105The Way Forward
- Determine the principles to define capacity and
the market trading mechanisms for non-controlled
interconnectors - Understand the application and merit of capacity
rights and develop firm access where one
interconnector affects the operation of another - Better appreciate the market power implications
of interconnectors without unnecessarily
restricting their development
106Key Limitations of the Safe Harbour Provisions -
case examples
- The provisions do not cover
- intra-regional interconnectors
- non-transmission interconnector capacity upgrade
- free flowing AC links - loop and parallel flows
- participant or an interconnector controlling more
than 35 of the capacity in either of the supply
regions - hybrid of regulated and non regulated
interconnection
David Roberts Presentation to follow
107Hybrid Interconnectors
- David Roberts
- Basslink Development Board
108Purpose
- Endorsement for the Concept
- Highlight Issues to be Resolved
- Commitment to Progress
109Outline
- Reasons for Hybrid Interconnectors
- Relevant Situations
- Examples
- Principles
- Issues to Resolve
- The Way Forward
- Summary
110Reasons for
- Economies of Scale
- Increase in Load Demand does not Automatically
Increase Value - Beneficiaries not Necessarily Obvious
- Approval of Regulated
- Transition between Non Regulated and Regulated
111Relevant Situations
- Initial Trading may be Limited
- Most Trading is One Way
- No Market History to Support Non Regulated
- Regulated Asset Owner unwilling to Develop
- Non Regulated applies to become Regulated
112Examples
- X Regulated Y Non Regulated
- Enhancement to Existing Interconnectors
- Regulated One Way Non Regulated the Other
- Regulated at Certain Times Non Regulated at
Others - Combinations
113Principles
- Regulated Portion of an Interconnector can be
Defined - Regulated Portion Subject to Rules for Regulated
Interconnectors (Including Approval,
Availability, Dispatch, Network Pricing
Revenues, Settlements Residues IRHs etc) - Remainder Subject to Rules for Non Regulated
114Issues to Resolve
- Who Defines Regulated Portion and How
- Which takes Precedence
- Partial Outage
- Dispatch at Zero Price
- Ring Fencing
- Required for Network Businesses
- Some Complexity with Hedge Contracts
115Issues to Resolve
- Non Linear Allocations
- Adjustment of Settlements Residue for Allocation
of Losses - Required if Regulated and Non Regulated contracts
treated differently - Network Charges/Revenues
- Regulated Portion
- Non Regulated Portion
116Issues to Resolve
- Approval Criteria
- Look Ahead or Based on Market Results
- Who bears the Market Risk
- Review of Regulated Portion
- Discretion for Adjusting up or Down
117The Way Forward
- Depends on Arrangements for Regulated
Interconnectors (Approval, Settlements Residue
and Hedging) - Also Dependent on the Rules for Non Regulated
Interconnectors - Common Factors Needed
118Summary
- Hybrid Interconnectors needed as a Bridge between
Regulated and Non Regulated Interconnectors - Simple Arrangements should be Possible which
could be Adapted to Different Situations - Commitment to Progress Arrangements
119Next Steps
120Next steps
- working group supplementary comments
- transmission and distribution pricing review
121Review timetable
- publication of draft report Jan / Feb 1999
- consultation with key stakeholders Feb/March
1999 - publication of final report end-March 1999