Title: Second Airport for Mumbai


1
  • W E L C O M E
  • Navi Mumbai International Airport (NMIA)
  • 21st May 2011

2
Outline of Presentation
  • Project Brief
  • Site Orientation
  • Master Plan NMIA
  • Project Activities Status
  • Project Schedule

3
Mumbai Metropolitan Region
  • - Area - 4355 Sq. Km
  • - Population 17.81 M (2001)
  • - Proj. Population - 23.50 M (2011)
  • Major Growth Centers
  • Gr. Mumbai, Navi Mumbai, Thane,
  • Vasai-Virar Kalyan

4
Navi Mumbai
  • Area - 344 Sq. Km.
  • Target Population - 2.0 M
  • Target Employment 0.75M
  • Existing Population - 1.7 M
  • Existing Employment - 0.4 M
  • Fast Growth Rate - 12 per annum

5
Need of 2nd Airport
  • MMR Present Air Travel Demand (2009-10) - 25.
    60 MPPA
  • MMR Air Travel Demand projected - 119 MPPA by
    2030-31
  • Mumbai airport experiencing severe congestion
    delays
  • Mumbai airport estimated to handle 40 MPPA
    maximum
  • Mumbai needs 2nd Airport

6
SITE ORIENTATION
MIA
VASHI
KHARGHAR
Sion-Panvel Expressway
KALAMBOLI
NERUL

NMIA
MTHL
ULWE
Bombay-Pune Expressway
MMSEZ
NMSEZ
7
Project Detail Accessibility
Existing Linkages Roads NH-4B, SH-54, City
Roads Rail Khandeshwar Stn. Proposed
Linkages Roads MTHL Rail Metro Water
Hovercraft Service
8
Master Plan

9
Salient Features - NMIA
SR .NO. ITEMS FACILITIES DETAILS
1 AIRPORT ZONE AREA (HA) 1405
i) AERONAUTICAL AREA (HA) 1160
ii) ESSENTIAL NON AERONAUTICAL AREA (HA) 276
2 NO. OF RUNWAYS 2
3 LENGTH OF RUNWAYS (METERS) 3700
4 RUNWAY SPACING (METERS) 1550
5 TOTAL NUMBER OF GATES 101
i) CONTACT GATES 77
ii) REMOTE PARKING 24
7 AIRPORT CAPACITY (MPPA) 59.62
10
Layout Details
  • Airport Plan has H-shaped terminal building in
    the centre with runways on either side
  • On completion of first phase (2014) - 10 million
    passengers
  • Operational with one runway in the north, two
    taxiways, 15 contact gates, passenger building
    built across 86,000 sqm.
  • It will require an investment of Rs4,424 crore

11
Layout Details
  • By the second phase, in 2020, both runways and
    four taxiways will be operational and it will be
    able to handle 25 million passengers.
  • It will handle 60 million passengers by 2030.
  • Overall investment in the airport is estimated at
    around Rs8,300 crore

12
Layout Details
  • Terminal will have a built up of 3 lakh sqm
    across five levels and will have separate
    domestic and international concourse
  • Passengers will be able to enter from two sides
    those from Mumbai Ulwe from Pune Panvel
  • To be made accessible via road, metro rail,
    suburban rail and hovercraft service

13
Project Phasing
14
CRITICAL ACTIVITIES
  • Forest Clearance
  • Master Plan/Bidding Documents by Prime Consultant
  • Amendment to NMDP
  • Enhancing Airport Connectivity
  • Land Acquisition
  • Re-Settlement Rehabilitation (RR)
  • Shifting of EHVT Lines
  • Compliance EC
  • Selection of Strategic Partner

15
Project Activities - Status
  • 1. Forest Clearance
  • Proposal for Forest Clearance fulfilling
    requirements submitted on 6.12.2010 and in
    process with Chief Conservator of Forest.
  • Draft application for filing Notice of Motion in
    Hon. Mumbai High Court prepared will be taken
    up upon receipt of Forest Clearance

16
Project Activities - Status
  • 2. Master Plan by Prime Consultant (M/s. LBG,
    USA)
  • Air Traffic Forecast Alternative Concept
    Master Plan
  • approved in 6th Steering Committee
    Meeting - Nov. 2009
  • Draft Master Plan Report reviewed by ICAO
  • Work on Preliminary Designs, DPR and Bidding
    Documents in progress

17
NMIA MASTER PLAN
18
Approvals For NMIA GoI / GoM
  • 31st July 2007 MOCA , GoI granted
    in-principle approval
  • 17th Aug. 2007 CIDCO Board approved
    development
  • 30th July 2008 State Cabinet, GoM approved
    development
  • 11th Oct 2010 Ministry of Defense (MoD)
    granted Defense clearance
  • 22nd Nov 2010 MoEF granted Environmental
    Clearance to NMIA
  • 16th May 2011 Final approval for the NMIA
    revised master plan from the steering committee

19
Project Activities - Status
  • 3. Amendment to Navi Mumbai Development Plan
    (NMDP)
  • Based on conditions given in MoEF Environmental
    Clearance, CIDCO is modifying Navi Mumbai
    Development Plan and revised Development Plan
    will be put up for GoM approval shortly.
  • Land based connectivity is crucial for success
    of any airport
  • CIDCO has planned widening of two main access
    roads - Aamra Marg and NH4-B in co-ordination
    with MJPRCL, an SPV of NHAI

4. Enhancing Airport Connectivity
20
Project Activities - Status
  • 5. Land Status
  • Total land earmarked for Airport Project is
    2020 Ha
  • Out of this 1333 Ha (66) land is in possession
    of CIDCO
  • About 263 Ha (13) Government land under
    transfer
  • About 424 Ha (21) is private land and is in
    process

21
Project Activities - Status
Land Status
22
Project Activities - Status
  • 6. Resettlement Rehabilitation (RR)
  • About 3000 families from 10 settlements of 7
    villages to be rehabilitated
  • Discussion on draft RR policy with stake holders
    in progress
  • Policy incorporating stake holders views being
    finalized in consultation with GoM
  • Sites for R R for relocation of Airport
    Project Affected People identified and
    developmental works initiated at sites

23
Project Activities - Status
Resettlement Rehabilitation Plan
24
Project Activities - Status
  • 7. Shifting of EHVT Lines
  • EHVT lines of Tata Power and MSETC passing
    through airport area and require shifting.
  • M/s LBG has submitted draft report for shifting
    of EHVT Lines for safe operation of Airport.
  • Consultant now revising report as per approved
    layout of MoEF.
  • Meeting with power companies will be arranged
    shortly to finalize program of implementation.

25
Progress on EC - Compliance of MoEF
MoEF Condition Compliance/ Status
Revise Master plan/ Development plan of Navi Mumbai as per NMIA. CIDCO Board approved modifications to NMDP and statutory process of approval as per MRTP Act is being followed.
Rehabilitation of families as per the R R policy of GoI/GoM Draft R R Policy is prepared and being discussed with Airport Project Affected Families.
Prepare a detailed traffic management plan, Improvement of connectivity and mass public transportation . MTSU through M/s. Lea Associates is carrying out connectivity study.
Obtain permission from Hon. Mumbai High Court for cutting or damaging of mangroves Process of obtaining Forest Clearance has commenced on 6th December, 2010 and proposal being processed with Forest Dept. Hon. Mumbai High Court will be approached for permission of cutting of mangroves .
26
Progress on EC - Compliance of MoEF
MoEF Condition Compliance/ Status
Risk assessment plan and disaster management plan and dedicated professional team/cell to handle disaster and associated risks. National Institute of Disaster Management, New Delhi is being appointed.
Design of Ulwe recourse channel and measures to avoid flooding CWPRS, Pune is revising 1D - 2D mathematical models and physical model study.
Conduct the baseline survey of avian fauna. BNHS is being appointed to carry out avian fauna survey.
27
Progress on EC - Compliance of MoEF
MoEF Condition Compliance/ Status
Obtain the Environmental and CRZ clearance separately for off airport facilities and other off infrastructure projects. Proposal for offsite physical infrastructure has been approved by MCZMA.
A high level advisory and monitoring committee for compliance of MoEF conditions. High level advisory and monitoring committee is being constituted by GoM.
Obtain all other statutory clearances as applicable by project proponents from the respective competent authorities. MoCA Defense Clearance obtained and other statutory clearances shall be obtained at appropriate time.
28
Project Activities - Status
  • 8. Strategic Partner
  • A strategic partner for Airport development will
    be selected through global bidding .
  • Bidding documents are being prepared by prime
    consultant M/s Louis Berger Group , USA

29
Project Implementation Structure
  • PPP Model
  • Special Purpose Company (SPC) to be formed
  • Selection of Strategic Investor through
    bidding
  • SPC to design, plan, finance, construct,
    market , operate maintain
  • SPC to return project to CIDCO/GoM on expiry
    of concession period

30
Action Plan
  • Clearances Obtained
  • Ministry of Civil Aviation (MoCA)
  • Government of Maharashtra ( GoM)
  • Ministry of Environment Forests ( MoEF)
  • Ministry of Defence ( MoD)
  • Clearances Required
  • Forest Clearance
  • Hon. High Court of Mumbai
  • Selection of Strategic Partner shortly
  • Commencement of work in a year
  • Commencement of NMIA Phase 1 2015

31
Project Implementation Schedule
32
Time Frame
1. Preparation of Master Plan, DPR Bid Documents In progress
2. Invitation of Bids for Selection of Developer May - Dec 2011
3. Financial Closure April 2012
4 Commencement of Work May 2012
5. Opening of Airport Phase 1 2014 - 15
33