Title: Opportunities and Incentives for CHP in Massachusetts
1 Opportunities and Incentives for CHP in
Massachusetts Interconnection Procedures June
19, 2013 Tim Roughan
2Agenda
- MA interconnection process
- Federal Energy Regulatory Commission (FERC)
interconnection process at ISO-NE - Appendix Technical considerations
- Appendix Net metering in MA
3Safety Moment
- This mornings session provides a great safety
moment. - All the benefits derived from Distributed
Generation quickly lose their value if someone is
injured as a result of an improper
interconnection.
4DG Activity Trends National Grid
- Received over 491 applications worth more than 77
MW of interconnection applications in Q1 2013
(Last year estimated 1,811 apps, actual was 2086) - Small (lt100kW) Interconnection application are
triggering large studies because of the aggregate
generation on the circuit. - More projects are in construction phase
- Some circuits have over 20 interconnected
generators
4
5Massachusetts Interconnection Standard
- In late 2002, the MA DTE directed the investor
owned utilities to commence a collaborative
process to propose unified interconnection
standards, policies, and procedures for
distributed generation. - In 2009, DPU approved tariff that included net
metering provisions. - In the summer of 2012, DPU convened a Distributed
Generation Working Group (DGWG) to recommend
improvements to the MA DG Tariff. The DGWG,
comprised of utility, state and DG community
stakeholders, reached consensus on all but one
issue and the DPU approved the revised tariff on
3/20/13 and went into effect May 1, 2013. - This interconnection standard covers all forms of
generation operating in parallel with the grid
(it does not apply to emergency generation).
6What is the Interconnection Process?
- Process of getting an interconnection agreement
from your local utility (or distribution company)
to connect a distributed generation system to
their distribution system. - This process is used by the four investor owned
utilities (IOU) in Massachusetts (NSTAR, National
Grid, Unitil and Western Mass Electric) - Municipally-owned utilities are not required to
follow this process, and may follow a different
criteria. - The process is used to make sure interconnecting
DG systems are integrated into the distribution
system responsibly with respect to impacts on
reliability, power quality and safety - Can not allow DG to affect neighbors on feeder
7Importance of the Interconnection Process for CHP
- Following the interconnection process is
important because a DG system changes the one-way
power flow from the utility to customer, which
can present dangers to utility workers if proper
equipment is not installed - While robust and capable of handling minor
disturbances, the quality of grid power is
extremely important. The interconnection process
ensures the DG meets safety, reliability, power
quality requirements with regard to - Islanding
- Transient Voltage Conditions
- Noise and Harmonics
- Frequency
- Voltage Level
- Machine Reactive Capability
- It is essential that each interconnection get an
interconnection agreement with the utility before
installing any generation. You are proceeding at
your own risk if you choose to install a system
without utility approval.
8Pre-Application Report
Customer needs to provide
Utility to provide
- Contact Person
- Mailing Address
- City
- Telephone E-Mail Address
- Alternative Contact Information (e.g., system
installation contractor or coordinating Facility
Information - Proposed Facility Location (street address with
cross streets, including town, and a Google Map
still picture and GPS coordinates) - Generation Type
- Size (AC kW)
- Single or Three Phase Generator Configuration
- Stand-alone (no on-site load, not including
parasitic load)? - If there is existing service at the Proposed
Facility site, provide - Interconnecting Customer Account Number
- site minimum and maximum (if available) current
or proposed electric loads - Minimum kW
- Maximum kW
- Is new service or service upgrade needed?
- Circuit voltage at the substation
- Circuit name
- Circuit voltage at proposed Facility
- Whether Single or three phase is available near
site If single phase distance from three phase
service - Aggregate connected Facilities (kW) on circuit
- Submitted complete applications of Facilities
(kW) on circuit that have not yet been
interconnected - Whether the Interconnecting Customer is served by
an area network, a spot network, or radial
system - Identification of feeders within ¼ mile of the
proposed interconnection site through a snap-shot
of GIS map or other means and - Other potential system constraints or critical
items that may impact the proposed Facility.
9Everything starts with the Application
- A complete complex application package includes
- All appropriate sections of 4-page application
completely filled out. Customer will likely need
assistance from vendor/engineer. - Copy of Pre-Application Report
- Application fee 4.50/KW (300 minimum and 7,500
maximum). This fee covers the initial review.
(Proposed change in 2012 raises these costs) - Stamped electric one-line diagram, preferably
showing relay controls (one copy) (Stamped by
Massachusetts Electrical PE) - Site diagram (one copy)
- One copy of any supplemental information (if
electronic single copy acceptable) - Identify electric customer and owner of proposed
generation - Schedule Z if planning to Net Meter
- Errors or problems with application will slow
down the process and stop the clock - Send Electronic copy of all documents preferred
if possible Easier to distribute, saves paper,
and is faster. However, submit first page of
application with application fee.
10Expedited Review Path
- Applies to
- Single phase customers with listed single-phase
inverter based systems gt15 kW on a radial feed - Three phase customers with listed three-phase
inverter based systems gt25kW on a radial feed. - Maximum size is based on review of screens
- Does not Apply to
- Non-listed inverters or other generators
(induction / synchronous / asynchronous) - Aggregate generation capacity of listed inverters
that exceed the above-mentioned limits
11Table 1 of Section 3 in the Interconnection Tariff
Expedited Review Path
Expedited
Eligible Facilities Listed DG
Acknowledge Receipt of Application (Note 2) (3 days)
Review Application for Completeness 10 days
Complete Review of All Screens 25 days
Complete Supplemental Review (if needed) (Note 3) 20 days or Standard Process
Send Executable Agreement (Note 4) 10 days
Construction Schedule By Mutual Agreement
Total Maximum Days (Note 5) 40/60 days (Note 6)
Notice/ Witness Test lt 1 day with 10 day notice or by mutual agreement
- Typically little or no (utility) system
modifications required. If meter only usually
no charges passed to customer - Application fee plus any Supplemental Review
charges up to 30 hours of engineering time _at_
150/hr (if needed) - Relay control system must be well defined to make
supplemental review easier. - Witness test fee of up to 300 plus travel is
required.
12Supplemental Review
- If one or more Screens are not passed, the
Company will provide a Supplemental Review
Agreement. - Threshold is whether project is less than 67 of
minimum load on the feeder - Then other screens review voltage quality ,
reliability and safety to reduce the potential
need for impact studies. - DPU order allowed for the 67 screen, but
requires utilities to document how the use of a
100 screen would change the screening process - Customer signs agreement and pays fee for
additional engineering time (max fee is now
4,500). - The Supplemental Review may be able to determine
what impacts the generation system will have and
what (if any) modifications are required. If so
- an interconnection agreement will be sent to
customer detailing - System modification requirements, reasoning, and
costs for these modifications - Specifics on protection requirements as necessary
- If Supplemental Review cannot determine
requirements, an Impact Study Agreement (or
equal) will be sent to the customer. (You shift
to the Standard Process.)
13Standard Review Path
- Applies to
- Non-listed inverters or other generators
- Induction
- Synchronous
- Asynchronous
- Other large MW and Multi MW Projects
- Renewable DG Customers / Developers
14Standard Review Path
Table 1 of Section 3 in the Interconnection Tariff
- After initial review and/or supplemental review,
customer may need to enter Standard Process - Customer can request Standard Process
- Appropriate study agreement sent for signature
and payment - Studies could include
- Impact Study Determine the impact of the new
generator on potentially affected systems,
including EPS, other customers and other
generators - Detailed Facility Study Determine utility system
modifications required and cost - ISO notification and possibly Transmission Study
if over 1 MW - After studies interconnection agreement sent
for signature - Witness test fee is actual cost.
Standard
Eligible Facilities Any DG
Acknowledge Receipt of Application (Note 2) (3 days)
Review Application for Completeness 10 days
Complete Standard Process Initial Review 20 days
Send Follow-on Studies Cost/Agreement 5 days
Complete Impact Study (if needed) 55 days
Complete Detailed Study (if needed) 30 days
Send Executable Agreement (Note 3) 15 days
Construction Schedule By Mutual Agreement
Total Maximum Days (Note 4) 125/150 days (Note 5)
Notice/ Witness Test 10 days or by mutual agreement
15MA Revised Interconnection Tariff
- 1st payment of 25 of estimate is only required
within 120 business days of signing an ISA - Estimates are only good for 60 business days and
we have the right to re-estimate if customer
payment is not received before then - Company is not obligated to order equipment
without receiving adequate payment as defined
in customers ISA - Company not required to begin construction prior
to receipt of full payment - If payment is not made within the applicable
timeframe, the Company shall require the Customer
to reapply for interconnection. - Increased study times for large projects
- Those that require modification at substation
- Instead of 55 business days for an Impact Study,
now have 75 (2013 and 2014), then to 70 (2015),
and then 60 (2016) - Projects gt 200,000 estimated costs (not
including on-site work, metering, recloser, riser
pole, etc.) - Instead of 30 business day for a Detailed Study,
now have 75 (2013 and 2014), then to 70 (2015),
and then 60 (2016) - Projects gt 1 million, all study timelines are by
mutual agreement - Require more detailed reporting on project status
- For both studies and construction timelines
- ISA must include a mutually agreed upon timeline
for construction - DPU has asked DG WG to investigate an
incentive/penalty mechanism to ensure timeline
compliance
16Timeline Compliance
- Regulatory obligation for both the distribution
company and the customer - Study times are suspended until such time as
company receives the requested info from customer - if an applicant requests additional time at or
near a milestone, the Company will get additional
time to achieve that milestone - if an applicant requests a significant project
change -- as determined by the distribution
company -- the applicant will be required to
submit a new interconnection application - at any time, an applicant may request a review
of time-frame compliance by the distribution
company, and the distribution company must
respond within ten business days - There is a process to remove customers from the
queue if they dont abide by the timelines or
extensions - Customer can request refund of application fee if
the Company does not comply with timeline(s)
17Responsibility of Costs
- Interconnecting customer responsible for
- Application Fee
- Expedited and Standard 4.50/kW (300 min and
7,500 max - Costs of impact and detailed studies if required
- Grid modification requirements can include
ongoing charges - Witness Test Fee
- Costs associated with design, construction and
installation of the facility and all associated
interconnection equipment on the customers side
of the meter - Not all projects will require impact or detailed
studies or EPS upgrades
18Third Party Ownership
- Application must include information for both
generation owner (interconnecting Customer) and
electric or retail customer (Customer) - Utility will correspond with owner, customer and
installer - Listing email addresses for all parties on
application makes communication easier and faster
- Utility will enter into agreement with our
electric customer (Attachment G of tariff) - Note Any Ownership change would require
updated documentation submitted to the Utility
Company
19Common Application Mistakes
- Number of inverters being used not indicated
- Utility account or meter number not included or
incorrect - Address of facility not correct
- Name on application differs from name on utility
account - Application not signed
- Ownership of property not identified
- Not identifying third party ownership of
generator
20Common process delays
- New construction or service upgrade
- Host/Owner misidentification
- Changing inverter or other equipment
- Not supplying electrical permit
- Certificate of Completion (CoC) signed and dated
before date given approval to install
21Behind the scenes at utility
- Review and replacement of metering, modifications
to billing - Modifications to protection systems as required
(e.g. replace or install fusing, install switch,
modify breaker/recloser set-points, transfer
trip, etc.) - Larger generators require review by NEPOOL
reliability committee and registration with
ISO-NE - Adding generation asset to geographic information
systems, maps, system one-lines, dispatch
systems, etc. - Publish internal special operating guidelines for
utility field personnel on larger generators. - Set up future testing for relay protection, meter
calibration, insurance tracking, etc.
22Many Stakeholders Involved
Utility
Interconnecting Customer
- Application analyst processes application and
contracts - Lead Engineer for reviews/studies
- Relay Engineering
- Distribution Planning
- Distribution Dispatch
- Distribution Design Engineering
- Meter Operations
- Meter Engineering
- Meter Data Services
- Relay Telecom Operations
- Inspection team
- Customer Service / Billing
- Legal
- Customer
- Equipment vendor
- Lead contractor
- Electrician
- Electrical Engineer (PE)
- Relay Engineer
- Relay testing firm
- Legal
ISO-NE (If necessary)
23Interconnection Summary and Recommendations
- Submit your interconnection application with
National Grid early, during conception phase
before committing to buy no matter how simple or
small the DG might be. - You can always request general utility
information about a specific location from your
utility - Large interconnection application take longer to
study - Stand alone (no load behind the meter)
interconnection application take longer to study - Interconnection timeframes do not apply to
Electric Power System construction if required.
24Summary and Recommendationscontinued
- The Interconnection Standard is a wealth of
information get to know it - Time frames are standard working days and do not
include delays due to missing information or
force majeure events - Interconnection expenses such as application
fees, required studies, potential system
modifications and witness tests should be
budgeted into each project - Consider hiring an engineer to help with
interconnection process - ISO-NE notification not included in time frame
- Interconnection applications have increased
significantly in the past few years APPLY
EARLY!!!
25Compensation for excess CHP generation
- If the customer will never export power no
concern - If under 60 kWs, customer can net usage over
billing period - Paid average clearing price for load zone for
excess - If customer will export power they can sell
their exported power to the market through a
registered market participant. - Customer will need a Qualifying Facility (QF)
certificate from FERC for the generator, to
sell to local utility (Power Purchase Schedule) - Receive hourly clearing price for load zone for
excess - Customer can work with any registered market
participants to sell power - Customer must pay for all power they use.
- Energy is netted for each hour, not over the
billing period - FERC QF page http//www.ferc.gov/industries/elec
tric/gen-info/qual-fac.asp
26State vs. ISO-NE Process
- If project is large enough (gt6 -10 MWs), will
need to interconnect to transmission system
through Small Generator Interconnection
Procedures (SGIP) - Need to apply to the New England Independent
System Operator (ISO-NE) - If you will be selling your power to a third
party, or bidding in capacity to the Forward
Capacity Market (FCM) you may have to apply
through ISO-NE - If circuit is already FERC Jurisdictional and
project is selling to a third party, it will need
to apply to ISO-NE. - If another generator is selling to the wholesale
market, then the circuit is FERC jurisdictional - http//www.iso-ne.com/genrtion_resrcs/nwgen_inter/
index.html
27Interconnection Contacts Tariff Links
- National Grid
- Email Distributed.Generation_at_us.ngrid.com
- Phone Alex Kuriakose (781) 907-1643, Bob
Moran (508) 897-5656 - W. Adam Smith (781) 907-5528,
Vishal Ahirrao (781) 907-3002 - Sean Diamond (781) 907-2611, Chandra
Bilsky (401) 784-7174 - Kevin G. Kelly (978) 725-1325
- http//www.nationalgridus.com/non_html/shared_int
erconnectStds.pdf - NSTAR
- Joseph Feraci (781) 441-8196
(joseph.feraci_at_nstar.com) - Paul Kelley (781) 441-8531 (paul.kelley_at_nstar.c
om) - http//www.nstar.com/business/rates_tariffs/inter
connections - Unitil
- Tim Noonis 603-773-6533 (noonis_at_unitil.com)
- http//www.unitil.com/energy-for-residents/electr
ic-information/distributed-energy-resources/renewa
ble-energy-generation - WMECo
- Phone 413-787-1087
28Other Information Resources
- MA DG and Interconnection Website
http//sites.google.com/site/massdgic/ - Net Metering Basicshttp//sites.google.com/site/
massdgic/Home/net-metering-in-ma -
- Interconnection Guide for Distributed Generation
(Mass-CEC)http//www.masscec.com/masscec/file/I
nterconnectionGuidetoMA_Final28129.pdf
28
29Appendix Technical Aspects of Integrating
DGwith the Utility Distribution EPS
30Interconnection StandardsLocal Rules National
Grid
- What are the local rules that apply to DG
interconnections? - National Grid ESB 756 Parallel Generation
Requirements - Originates from the ESB 750 Series and applicable
Company tariffs in each state jurisdiction - ESB 756 main document
- Appendices to ESB 756 for Jurisdictional
Requirements - Some key factors that influence the
revision/update of Electric Service Requirements
are - Government
- DPU (Massachusetts), PSC (NY), and PUC (one each
for NH RI) - FERC
- Federal, State, and Local Laws
- MA Court Rules Solar PV Installations are
Electrical. PHYSICAL INSTALLATION of PV Systems
Must Be Done by LICENSED ELECTRICIANS. July 2012
ruling by Suffolk Superior Court - Company tariffs
- Company policies practices
- National codes
Each utility has their requirements pursuant to
the regulations that govern them as varying from
state-to-state based on the NESC.
www.nationalgridus.com/electricalspecifications
31Interconnection Standards (contd) National Grid
ESB 750 Series
- Key Points for Electric Service Requirements
- Require some means of disconnect and main
overcurrent protection, i.e., service equipment. - Billing meters secure.
- Interface points clear to avoid potential
operating and safety problems.
- Key Points for Parallel Generation Requirements
- Company determines the interconnect voltage and
method of interconnection. - Prior notification to and approval by the Company
is required for any generation to be installed or
operated in parallel with the Company EPS.
32Technical Issues
- Technical Process End-to-End (Study to
Energization/Synchronization) with National Grid - Technical Submittals for Utility Review
- Potential Impacts of Parallel Generation on
Distribution Electrical Power Systems (EPS) - Limits on National Grid Distribution EPS
- Radial Systems
- Network Systems
- Service Connections of Small Net Metered DGs lt
600V - Typical Distribution EPS Upgrade Costs for
Complex DG Installations
33Technical IssuesTechnical Submittals for
Utility Review
Recommended Guidelines for Residential and
Commercial Single-line Diagram Submittals (for
example, see Exhibit 5 Figures 1 2 in ESB 756
Appendix C)
- 1. Identify the project, Companys electric
service order (ESO) number, location and
submitters name and address. - 2. Indicate standard and any non-standard system
voltages, number of phases, and frequency of the
incoming circuit. Indicate wye and delta systems
show whether grounded or ungrounded. - 3. Identify cable, conductors and conduit, the
type and number including Point of Common
Coupling. (The Company is interested in how the
power is getting from the service point to the
protective equipment.)
34Technical Issues (contd)Limits on Distribution
EPS - Radial
- Typical Planning Limits for DG Connection to
Radial Distribution Feeder
DG installations are classified into two types -
those interconnecting to the National Grid system
on a dedicated radial feeder and those
interconnecting on a non-dedicated radial feeder.
35Technical Issues Anti-Islanding on Distribution
EPS - Radial
- Anti-Islanding Protection
- The Companys position is that the
interconnection of all parallel generators
requires safeguards for synchronization and
back-feed situations. A parallel generator is
prohibited to energize a de-energized Company
circuit. - The Company uses three main tests any
determine if anti-islanding protection is
required for exceeding minimum load issue or a
protection issue or operating concern - Feeder Load versus Generation Test
- Fault Sensitivity Test
- Feeder Selectivity Test
- Tips
- DG Customers protective device coordination
study demonstrates generation voltage and/or
frequency protection will trip within 2.00
seconds for the loss of the utility source. - Type-tested inverter-based parallel generation
operated in regulated current mode, transient
overvoltage protection is required upon detection
of an island. - When DTT is specified for a parallel generation
project, the Company will determine the
requirements and responsibilities for equipment,
installation, and communications media in the
interconnection study.
36Technical IssuesLimits on Distribution EPS -
Network
- Unlike radial distribution systems that deliver
power to each customer in a single path from
source to load, underground secondary area
network systems deliver power to each customer
through a complex and integrated system of
multiple transformers and underground cables that
are connected and operate in parallel. - Area Networks consist of one or more primary
circuits from one or more substations or
transmission supply points arranged such that
they collectively feed secondary circuits serving
one (a spot network) or more (an area network)
electric customers.
37Technical Issues (contd)Limits on Distribution
EPS - Network
Area Networks consist of one or more primary
circuits from one or more substations or
transmission supply points arranged such that
they collectively feed secondary circuits serving
one (a spot network) or more (an area network)
Interconnecting Customers. Portions of the
following cities are served by area networks
(customers in these areas should ask where the
nearest radial system is located for possible
tie-in)
WMECo Unitil National Grid NSTAR
Greenfield Pittsfield Springfield West Springfield Fitchburg Brockton Lynn Worcester Boston New Bedford Cambridge
(For National Grid, see Exhibit 3 in ESB 756
Appendix B, or C, or D.)
37
38Technical Issues (contd)Limits on Distribution
EPS - Network
- The connection of customer DG facilities on
networks is an emerging topic, which - (i) poses some issues for the Company to maintain
adequate voltage and worker safety and - (ii) has the potential to cause the power flow on
network feeders to shift (i.e., reverse) causing
network protectors within the network grid to
trip open.
- To ensure network safety and reliability
additional information will be required for the
Companys engineering analysis such as - Electric demand profile showing minimum load
during peak generation time, - Expected generation profile shown for a 24-hour
period and typical 7-day duration, and - Customers complete electric service single-line
diagram up to the service point supplied by the
Companys secondary network EPS.
39Technical Issues Upgrades and System
Modifications
Some Upper End Typical Utility Interconnection
Costs Duration Scheduling for Complex DG
Installations
Notes 1) Distribution EPS relates to 15kV class
system. 2) These are representative estimates
only and are not inclusive of all costs i.e.
land rights, removal costs, taxes, etc. which
will vary from job to job and that they are
presented here for budgetary purposes only.
40Post ISA CoordinationWitness Testing (overview)
- 1.) Relay Witness Testing
- National Grid Witnesses relays trip based on
settings approved by NG Protection Engineer - 2.) DTT Witness Testing
- Communication (RFL) to the Local Substation
- Typically Fiber or Lease line
- 3.) RTU Witness Testing (1MW)
- Provide Real time monitoring of Large DG at
National Grids Regional Control Center. - Ordering Correct (MPLS) communication circuit
from Verizon - Verizon Regional Account Teams consults with
Verizons Service Delivery Department
41Appendix Net Metering
42Net Metering in Massachusetts
- December 2009 Net Metering Tariff
- Three Net Metering Classes
- Class 1 Any generator up to 60 KW is eligible
- Class 2 Agricultural, solar, or wind net
metering facility over 60 KW but less than or
equal to 1 MW (for municipal or government its
per unit) - Class 3 Agricultural, solar, or wind net
metering facility over 1 MW but less than or
equal to 2 MW (for municipal or government its
per unit) - Recent changes
- limits projects to 2 MWs per parcel of land and a
single meter - Must apply to the System of Assurance (SofA) at
massaca.org for net metering services
43Net Metering Tariff
- Eligible customers can apply by submitting a
Schedule Z. - Eligibility determined when approved within the
SoA - Utility can not allow net metering without SofA
approval - Class 2 and Class 3 will need a production meter
on generation. - Net Metering is limited to 3 of each utilitys
peak MW for private and 3 of peak for public
projects for NG-MA this total limit is 308 MWs. - Contribution towards total 6 limit is posted on
each utilitys web site and updated monthly - As of 4/16, NG-MA is at 94 MWs for the private
and of 52 MW toward the public cap
44Net Metering changes
- Three Factor Approach (order 11-11C)
- Single parcel / single interconnection point /
single meter - Enacted to limit gaming and limits one meter per
parcel of land with a limit of 2 MWs on the
parcel for private entities - A governmental entity can have a total of 10 MWs
of net-metered accounts throughout the state or
on a parcel - No more 6 1 MW projects on a parcel
- We can not provide more than one interconnection
point (POI) - In addition, if theres an existing meter(s) on a
parcel, then customer cant request a meter just
for the net metering facility, it must be behind
an existing meter - Otherwise separate metered project could earn
higher credits than if it was behind an existing
meter
45Net Metering and Interconnection Order
- Net Metering eligibility
- The DPU ruled in the interconnection tariff order
(10-75E) that Early ISAs will NOT meet the
executed ISA requirement for entrance into the
System of Assurance, and will refer the matter to
DPU 11-11 for further investigation. - Until such time as the DPU reaches a resolution
of the issue, Distribution Companies are directed
to clearly mark Early ISAs on the title page and
on the signature page with the words Early ISA
for identification purposes.
46Net Metering Credits
- Energy use is netted over the billing month
- If there is net energy use utility will bill
customer for net use - If net energy export export kWH the following
- Renewable installations will be credited at near
retail rate for excess kWH (minus conservation
and renewable energy charges). - Non-Renewable credited at average monthly
clearing price ISO-NE - Tariff allows credits to be allocated (with
limitations) - Customer still responsible for customer charges
and demand charges, even if net export
Credit the following charges Credit the following charges Credit the following charges Credit the following charges
Tier min max Type Default Service kWH Dist- ribution kWH Trans- mission kWH Trans- ition kWH
1 0 60 KW Agriculture Wind, PV X X X X
2 gt60 KW 1 MW Agriculture Wind, PV X X X X
3 gt1 MW 2 MW Agriculture Wind, PV X Govt only X X
47 48(No Transcript)
49(No Transcript)
50Net Metering Production Reporting
- Net Metering Tariff requires reporting of
generators kWH output. - Class 1 Facilities to provide in writing by
January 31 and September 30 - Class 2 and Class 3 Facilities may participate in
production tracking system (PTS). - Mass CEC provided PTS data to the utilities,
still working through implementation issues - Utility will request data from Class 2 and 3
Facilities
51Net Metering Summary
- If planning to Net Meter, submit Schedule Z with
interconnection application - Correctly fill out Schedule Z
- Name must match electric account of Host Customer
- Must be signed by Host Customer
- If allocating, verify name/address/account info
of customer(s) or will need to submit corrected
form - Production reporting is required.
- Over 60 kWs require registration as a settlement
only generator (SOG) associated ISO OP 18
metering requirements