Opportunities and Incentives for CHP in Massachusetts - PowerPoint PPT Presentation

About This Presentation
Title:

Opportunities and Incentives for CHP in Massachusetts

Description:

This process is used by the four investor owned utilities (IOU) in Massachusetts (NSTAR, National Grid, Unitil and Western Mass Electric) ... – PowerPoint PPT presentation

Number of Views:205
Avg rating:3.0/5.0
Slides: 52
Provided by: bdod9
Learn more at: https://maeep.org
Category:

less

Transcript and Presenter's Notes

Title: Opportunities and Incentives for CHP in Massachusetts


1
Opportunities and Incentives for CHP in
Massachusetts Interconnection Procedures June
19, 2013 Tim Roughan
2
Agenda
  • MA interconnection process
  • Federal Energy Regulatory Commission (FERC)
    interconnection process at ISO-NE
  • Appendix Technical considerations
  • Appendix Net metering in MA

3
Safety Moment
  • This mornings session provides a great safety
    moment.
  • All the benefits derived from Distributed
    Generation quickly lose their value if someone is
    injured as a result of an improper
    interconnection.

4
DG Activity Trends National Grid
  • Received over 491 applications worth more than 77
    MW of interconnection applications in Q1 2013
    (Last year estimated 1,811 apps, actual was 2086)
  • Small (lt100kW) Interconnection application are
    triggering large studies because of the aggregate
    generation on the circuit.
  • More projects are in construction phase
  • Some circuits have over 20 interconnected
    generators

4
5
Massachusetts Interconnection Standard
  • In late 2002, the MA DTE directed the investor
    owned utilities to commence a collaborative
    process to propose unified interconnection
    standards, policies, and procedures for
    distributed generation.
  • In 2009, DPU approved tariff that included net
    metering provisions.
  • In the summer of 2012, DPU convened a Distributed
    Generation Working Group (DGWG) to recommend
    improvements to the MA DG Tariff. The DGWG,
    comprised of utility, state and DG community
    stakeholders, reached consensus on all but one
    issue and the DPU approved the revised tariff on
    3/20/13 and went into effect May 1, 2013.
  • This interconnection standard covers all forms of
    generation operating in parallel with the grid
    (it does not apply to emergency generation).

6
What is the Interconnection Process?
  • Process of getting an interconnection agreement
    from your local utility (or distribution company)
    to connect a distributed generation system to
    their distribution system.
  • This process is used by the four investor owned
    utilities (IOU) in Massachusetts (NSTAR, National
    Grid, Unitil and Western Mass Electric)
  • Municipally-owned utilities are not required to
    follow this process, and may follow a different
    criteria.
  • The process is used to make sure interconnecting
    DG systems are integrated into the distribution
    system responsibly with respect to impacts on
    reliability, power quality and safety
  • Can not allow DG to affect neighbors on feeder

7
Importance of the Interconnection Process for CHP
  • Following the interconnection process is
    important because a DG system changes the one-way
    power flow from the utility to customer, which
    can present dangers to utility workers if proper
    equipment is not installed
  • While robust and capable of handling minor
    disturbances, the quality of grid power is
    extremely important. The interconnection process
    ensures the DG meets safety, reliability, power
    quality requirements with regard to
  • Islanding
  • Transient Voltage Conditions
  • Noise and Harmonics
  • Frequency
  • Voltage Level
  • Machine Reactive Capability
  • It is essential that each interconnection get an
    interconnection agreement with the utility before
    installing any generation. You are proceeding at
    your own risk if you choose to install a system
    without utility approval.

8
Pre-Application Report
Customer needs to provide
Utility to provide
  • Contact Person
  • Mailing Address
  • City
  • Telephone E-Mail Address
  • Alternative Contact Information (e.g., system
    installation contractor or coordinating Facility
    Information
  • Proposed Facility Location (street address with
    cross streets, including town, and a Google Map
    still picture and GPS coordinates)
  • Generation Type
  • Size (AC kW)
  • Single or Three Phase Generator Configuration
  • Stand-alone (no on-site load, not including
    parasitic load)?
  • If there is existing service at the Proposed
    Facility site, provide
  • Interconnecting Customer Account Number
  • site minimum and maximum (if available) current
    or proposed electric loads
  • Minimum kW
  • Maximum kW
  • Is new service or service upgrade needed?
  • Circuit voltage at the substation
  • Circuit name
  • Circuit voltage at proposed Facility
  • Whether Single or three phase is available near
    site If single phase distance from three phase
    service
  • Aggregate connected Facilities (kW) on circuit
  • Submitted complete applications of Facilities
    (kW) on circuit that have not yet been
    interconnected
  • Whether the Interconnecting Customer is served by
    an area network, a spot network, or radial
    system
  • Identification of feeders within ¼ mile of the
    proposed interconnection site through a snap-shot
    of GIS map or other means and
  • Other potential system constraints or critical
    items that may impact the proposed Facility.

9
Everything starts with the Application
  • A complete complex application package includes
  • All appropriate sections of 4-page application
    completely filled out. Customer will likely need
    assistance from vendor/engineer.
  • Copy of Pre-Application Report
  • Application fee 4.50/KW (300 minimum and 7,500
    maximum). This fee covers the initial review.
    (Proposed change in 2012 raises these costs)
  • Stamped electric one-line diagram, preferably
    showing relay controls (one copy) (Stamped by
    Massachusetts Electrical PE)
  • Site diagram (one copy)
  • One copy of any supplemental information (if
    electronic single copy acceptable)
  • Identify electric customer and owner of proposed
    generation
  • Schedule Z if planning to Net Meter
  • Errors or problems with application will slow
    down the process and stop the clock
  • Send Electronic copy of all documents preferred
    if possible Easier to distribute, saves paper,
    and is faster. However, submit first page of
    application with application fee.

10
Expedited Review Path
  • Applies to
  • Single phase customers with listed single-phase
    inverter based systems gt15 kW on a radial feed
  • Three phase customers with listed three-phase
    inverter based systems gt25kW on a radial feed.
  • Maximum size is based on review of screens
  • Does not Apply to
  • Non-listed inverters or other generators
    (induction / synchronous / asynchronous)
  • Aggregate generation capacity of listed inverters
    that exceed the above-mentioned limits

11
Table 1 of Section 3 in the Interconnection Tariff
Expedited Review Path
Expedited
Eligible Facilities Listed DG
Acknowledge Receipt of Application (Note 2) (3 days)
Review Application for Completeness 10 days
Complete Review of All Screens 25 days
Complete Supplemental Review (if needed) (Note 3) 20 days or Standard Process
Send Executable Agreement (Note 4) 10 days
Construction Schedule By Mutual Agreement
Total Maximum Days (Note 5) 40/60 days (Note 6)
Notice/ Witness Test lt 1 day with 10 day notice or by mutual agreement
  • Typically little or no (utility) system
    modifications required. If meter only usually
    no charges passed to customer
  • Application fee plus any Supplemental Review
    charges up to 30 hours of engineering time _at_
    150/hr (if needed)
  • Relay control system must be well defined to make
    supplemental review easier.
  • Witness test fee of up to 300 plus travel is
    required.

12
Supplemental Review
  • If one or more Screens are not passed, the
    Company will provide a Supplemental Review
    Agreement.
  • Threshold is whether project is less than 67 of
    minimum load on the feeder
  • Then other screens review voltage quality ,
    reliability and safety to reduce the potential
    need for impact studies.
  • DPU order allowed for the 67 screen, but
    requires utilities to document how the use of a
    100 screen would change the screening process
  • Customer signs agreement and pays fee for
    additional engineering time (max fee is now
    4,500).
  • The Supplemental Review may be able to determine
    what impacts the generation system will have and
    what (if any) modifications are required. If so
    - an interconnection agreement will be sent to
    customer detailing
  • System modification requirements, reasoning, and
    costs for these modifications
  • Specifics on protection requirements as necessary
  • If Supplemental Review cannot determine
    requirements, an Impact Study Agreement (or
    equal) will be sent to the customer. (You shift
    to the Standard Process.)

13
Standard Review Path
  • Applies to
  • Non-listed inverters or other generators
  • Induction
  • Synchronous
  • Asynchronous
  • Other large MW and Multi MW Projects
  • Renewable DG Customers / Developers

14
Standard Review Path
Table 1 of Section 3 in the Interconnection Tariff
  • After initial review and/or supplemental review,
    customer may need to enter Standard Process
  • Customer can request Standard Process
  • Appropriate study agreement sent for signature
    and payment
  • Studies could include
  • Impact Study Determine the impact of the new
    generator on potentially affected systems,
    including EPS, other customers and other
    generators
  • Detailed Facility Study Determine utility system
    modifications required and cost
  • ISO notification and possibly Transmission Study
    if over 1 MW
  • After studies interconnection agreement sent
    for signature
  • Witness test fee is actual cost.

Standard
Eligible Facilities Any DG
Acknowledge Receipt of Application (Note 2) (3 days)
Review Application for Completeness 10 days
Complete Standard Process Initial Review 20 days
Send Follow-on Studies Cost/Agreement 5 days
Complete Impact Study (if needed) 55 days
Complete Detailed Study (if needed) 30 days
Send Executable Agreement (Note 3) 15 days
Construction Schedule By Mutual Agreement
Total Maximum Days (Note 4) 125/150 days (Note 5)
Notice/ Witness Test 10 days or by mutual agreement
15
MA Revised Interconnection Tariff
  • 1st payment of 25 of estimate is only required
    within 120 business days of signing an ISA
  • Estimates are only good for 60 business days and
    we have the right to re-estimate if customer
    payment is not received before then
  • Company is not obligated to order equipment
    without receiving adequate payment as defined
    in customers ISA
  • Company not required to begin construction prior
    to receipt of full payment
  • If payment is not made within the applicable
    timeframe, the Company shall require the Customer
    to reapply for interconnection.
  • Increased study times for large projects
  • Those that require modification at substation
  • Instead of 55 business days for an Impact Study,
    now have 75 (2013 and 2014), then to 70 (2015),
    and then 60 (2016)
  • Projects gt 200,000 estimated costs (not
    including on-site work, metering, recloser, riser
    pole, etc.)
  • Instead of 30 business day for a Detailed Study,
    now have 75 (2013 and 2014), then to 70 (2015),
    and then 60 (2016)
  • Projects gt 1 million, all study timelines are by
    mutual agreement
  • Require more detailed reporting on project status
  • For both studies and construction timelines
  • ISA must include a mutually agreed upon timeline
    for construction
  • DPU has asked DG WG to investigate an
    incentive/penalty mechanism to ensure timeline
    compliance

16
Timeline Compliance
  • Regulatory obligation for both the distribution
    company and the customer
  • Study times are suspended until such time as
    company receives the requested info from customer
  • if an applicant requests additional time at or
    near a milestone, the Company will get additional
    time to achieve that milestone
  • if an applicant requests a significant project
    change -- as determined by the distribution
    company -- the applicant will be required to
    submit a new interconnection application
  • at any time, an applicant may request a review
    of time-frame compliance by the distribution
    company, and the distribution company must
    respond within ten business days
  • There is a process to remove customers from the
    queue if they dont abide by the timelines or
    extensions
  • Customer can request refund of application fee if
    the Company does not comply with timeline(s)

17
Responsibility of Costs
  • Interconnecting customer responsible for
  • Application Fee
  • Expedited and Standard 4.50/kW (300 min and
    7,500 max
  • Costs of impact and detailed studies if required
  • Grid modification requirements can include
    ongoing charges
  • Witness Test Fee
  • Costs associated with design, construction and
    installation of the facility and all associated
    interconnection equipment on the customers side
    of the meter
  • Not all projects will require impact or detailed
    studies or EPS upgrades

18
Third Party Ownership
  • Application must include information for both
    generation owner (interconnecting Customer) and
    electric or retail customer (Customer)
  • Utility will correspond with owner, customer and
    installer
  • Listing email addresses for all parties on
    application makes communication easier and faster
  • Utility will enter into agreement with our
    electric customer (Attachment G of tariff)
  • Note Any Ownership change would require
    updated documentation submitted to the Utility
    Company

19
Common Application Mistakes
  • Number of inverters being used not indicated
  • Utility account or meter number not included or
    incorrect
  • Address of facility not correct
  • Name on application differs from name on utility
    account
  • Application not signed
  • Ownership of property not identified
  • Not identifying third party ownership of
    generator

20
Common process delays
  • New construction or service upgrade
  • Host/Owner misidentification
  • Changing inverter or other equipment
  • Not supplying electrical permit
  • Certificate of Completion (CoC) signed and dated
    before date given approval to install

21
Behind the scenes at utility
  • Review and replacement of metering, modifications
    to billing
  • Modifications to protection systems as required
    (e.g. replace or install fusing, install switch,
    modify breaker/recloser set-points, transfer
    trip, etc.)
  • Larger generators require review by NEPOOL
    reliability committee and registration with
    ISO-NE
  • Adding generation asset to geographic information
    systems, maps, system one-lines, dispatch
    systems, etc.
  • Publish internal special operating guidelines for
    utility field personnel on larger generators.
  • Set up future testing for relay protection, meter
    calibration, insurance tracking, etc.

22
Many Stakeholders Involved
Utility
Interconnecting Customer
  • Application analyst processes application and
    contracts
  • Lead Engineer for reviews/studies
  • Relay Engineering
  • Distribution Planning
  • Distribution Dispatch
  • Distribution Design Engineering
  • Meter Operations
  • Meter Engineering
  • Meter Data Services
  • Relay Telecom Operations
  • Inspection team
  • Customer Service / Billing
  • Legal
  • Customer
  • Equipment vendor
  • Lead contractor
  • Electrician
  • Electrical Engineer (PE)
  • Relay Engineer
  • Relay testing firm
  • Legal

ISO-NE (If necessary)
23
Interconnection Summary and Recommendations
  • Submit your interconnection application with
    National Grid early, during conception phase
    before committing to buy no matter how simple or
    small the DG might be.
  • You can always request general utility
    information about a specific location from your
    utility
  • Large interconnection application take longer to
    study
  • Stand alone (no load behind the meter)
    interconnection application take longer to study
  • Interconnection timeframes do not apply to
    Electric Power System construction if required.

24
Summary and Recommendationscontinued
  • The Interconnection Standard is a wealth of
    information get to know it
  • Time frames are standard working days and do not
    include delays due to missing information or
    force majeure events
  • Interconnection expenses such as application
    fees, required studies, potential system
    modifications and witness tests should be
    budgeted into each project
  • Consider hiring an engineer to help with
    interconnection process
  • ISO-NE notification not included in time frame
  • Interconnection applications have increased
    significantly in the past few years APPLY
    EARLY!!!

25
Compensation for excess CHP generation
  • If the customer will never export power no
    concern
  • If under 60 kWs, customer can net usage over
    billing period
  • Paid average clearing price for load zone for
    excess
  • If customer will export power they can sell
    their exported power to the market through a
    registered market participant.
  • Customer will need a Qualifying Facility (QF)
    certificate from FERC for the generator, to
    sell to local utility (Power Purchase Schedule)
  • Receive hourly clearing price for load zone for
    excess
  • Customer can work with any registered market
    participants to sell power
  • Customer must pay for all power they use.
  • Energy is netted for each hour, not over the
    billing period
  • FERC QF page http//www.ferc.gov/industries/elec
    tric/gen-info/qual-fac.asp

26
State vs. ISO-NE Process
  • If project is large enough (gt6 -10 MWs), will
    need to interconnect to transmission system
    through Small Generator Interconnection
    Procedures (SGIP)
  • Need to apply to the New England Independent
    System Operator (ISO-NE)
  • If you will be selling your power to a third
    party, or bidding in capacity to the Forward
    Capacity Market (FCM) you may have to apply
    through ISO-NE
  • If circuit is already FERC Jurisdictional and
    project is selling to a third party, it will need
    to apply to ISO-NE.
  • If another generator is selling to the wholesale
    market, then the circuit is FERC jurisdictional
  • http//www.iso-ne.com/genrtion_resrcs/nwgen_inter/
    index.html

27
Interconnection Contacts Tariff Links
  • National Grid
  • Email Distributed.Generation_at_us.ngrid.com
  • Phone Alex Kuriakose (781) 907-1643, Bob
    Moran (508) 897-5656
  • W. Adam Smith (781) 907-5528,
    Vishal Ahirrao (781) 907-3002
  • Sean Diamond (781) 907-2611, Chandra
    Bilsky (401) 784-7174
  • Kevin G. Kelly (978) 725-1325
  • http//www.nationalgridus.com/non_html/shared_int
    erconnectStds.pdf
  • NSTAR
  • Joseph Feraci  (781) 441-8196
    (joseph.feraci_at_nstar.com)
  • Paul Kelley (781) 441-8531 (paul.kelley_at_nstar.c
    om)
  • http//www.nstar.com/business/rates_tariffs/inter
    connections
  • Unitil
  • Tim Noonis 603-773-6533 (noonis_at_unitil.com)
  • http//www.unitil.com/energy-for-residents/electr
    ic-information/distributed-energy-resources/renewa
    ble-energy-generation
  • WMECo
  •  Phone 413-787-1087

28
Other Information Resources
  • MA DG and Interconnection Website
    http//sites.google.com/site/massdgic/
  • Net Metering Basicshttp//sites.google.com/site/
    massdgic/Home/net-metering-in-ma
  • Interconnection Guide for Distributed Generation
    (Mass-CEC)http//www.masscec.com/masscec/file/I
    nterconnectionGuidetoMA_Final28129.pdf

28
29
Appendix Technical Aspects of Integrating
DGwith the Utility Distribution EPS
30
Interconnection StandardsLocal Rules National
Grid
  • What are the local rules that apply to DG
    interconnections?
  • National Grid ESB 756 Parallel Generation
    Requirements
  • Originates from the ESB 750 Series and applicable
    Company tariffs in each state jurisdiction
  • ESB 756 main document
  • Appendices to ESB 756 for Jurisdictional
    Requirements
  • Some key factors that influence the
    revision/update of Electric Service Requirements
    are
  • Government
  • DPU (Massachusetts), PSC (NY), and PUC (one each
    for NH RI)
  • FERC
  • Federal, State, and Local Laws
  • MA Court Rules Solar PV Installations are
    Electrical. PHYSICAL INSTALLATION of PV Systems
    Must Be Done by LICENSED ELECTRICIANS. July 2012
    ruling by Suffolk Superior Court
  • Company tariffs
  • Company policies practices
  • National codes

Each utility has their requirements pursuant to
the regulations that govern them as varying from
state-to-state based on the NESC.
www.nationalgridus.com/electricalspecifications
31
Interconnection Standards (contd) National Grid
ESB 750 Series
  • Key Points for Electric Service Requirements
  • Require some means of disconnect and main
    overcurrent protection, i.e., service equipment.
  • Billing meters secure.
  • Interface points clear to avoid potential
    operating and safety problems.
  • Key Points for Parallel Generation Requirements
  • Company determines the interconnect voltage and
    method of interconnection.
  • Prior notification to and approval by the Company
    is required for any generation to be installed or
    operated in parallel with the Company EPS.

32
Technical Issues
  • Technical Process End-to-End (Study to
    Energization/Synchronization) with National Grid
  • Technical Submittals for Utility Review
  • Potential Impacts of Parallel Generation on
    Distribution Electrical Power Systems (EPS)
  • Limits on National Grid Distribution EPS
  • Radial Systems
  • Network Systems
  • Service Connections of Small Net Metered DGs lt
    600V
  • Typical Distribution EPS Upgrade Costs for
    Complex DG Installations

33
Technical IssuesTechnical Submittals for
Utility Review
Recommended Guidelines for Residential and
Commercial Single-line Diagram Submittals (for
example, see Exhibit 5 Figures 1 2 in ESB 756
Appendix C)
  • 1. Identify the project, Companys electric
    service order (ESO) number, location and
    submitters name and address.
  • 2. Indicate standard and any non-standard system
    voltages, number of phases, and frequency of the
    incoming circuit. Indicate wye and delta systems
    show whether grounded or ungrounded.
  • 3. Identify cable, conductors and conduit, the
    type and number including Point of Common
    Coupling. (The Company is interested in how the
    power is getting from the service point to the
    protective equipment.)

34
Technical Issues (contd)Limits on Distribution
EPS - Radial
  • Typical Planning Limits for DG Connection to
    Radial Distribution Feeder

DG installations are classified into two types -
those interconnecting to the National Grid system
on a dedicated radial feeder and those
interconnecting on a non-dedicated radial feeder.
35
Technical Issues Anti-Islanding on Distribution
EPS - Radial
  • Anti-Islanding Protection
  • The Companys position is that the
    interconnection of all parallel generators
    requires safeguards for synchronization and
    back-feed situations. A parallel generator is
    prohibited to energize a de-energized Company
    circuit.
  • The Company uses three main tests any
    determine if anti-islanding protection is
    required for exceeding minimum load issue or a
    protection issue or operating concern
  • Feeder Load versus Generation Test
  • Fault Sensitivity Test
  • Feeder Selectivity Test
  • Tips
  • DG Customers protective device coordination
    study demonstrates generation voltage and/or
    frequency protection will trip within 2.00
    seconds for the loss of the utility source.
  • Type-tested inverter-based parallel generation
    operated in regulated current mode, transient
    overvoltage protection is required upon detection
    of an island.
  • When DTT is specified for a parallel generation
    project, the Company will determine the
    requirements and responsibilities for equipment,
    installation, and communications media in the
    interconnection study.

36
Technical IssuesLimits on Distribution EPS -
Network
  • Unlike radial distribution systems that deliver
    power to each customer in a single path from
    source to load, underground secondary area
    network systems deliver power to each customer
    through a complex and integrated system of
    multiple transformers and underground cables that
    are connected and operate in parallel.
  • Area Networks consist of one or more primary
    circuits from one or more substations or
    transmission supply points arranged such that
    they collectively feed secondary circuits serving
    one (a spot network) or more (an area network)
    electric customers.

37
Technical Issues (contd)Limits on Distribution
EPS - Network
Area Networks consist of one or more primary
circuits from one or more substations or
transmission supply points arranged such that
they collectively feed secondary circuits serving
one (a spot network) or more (an area network)
Interconnecting Customers. Portions of the
following cities are served by area networks
(customers in these areas should ask where the
nearest radial system is located for possible
tie-in)
WMECo Unitil National Grid NSTAR
Greenfield Pittsfield Springfield West Springfield Fitchburg Brockton Lynn Worcester Boston New Bedford Cambridge
(For National Grid, see Exhibit 3 in ESB 756
Appendix B, or C, or D.)
37
38
Technical Issues (contd)Limits on Distribution
EPS - Network
  • The connection of customer DG facilities on
    networks is an emerging topic, which
  • (i) poses some issues for the Company to maintain
    adequate voltage and worker safety and
  • (ii) has the potential to cause the power flow on
    network feeders to shift (i.e., reverse) causing
    network protectors within the network grid to
    trip open.
  • To ensure network safety and reliability
    additional information will be required for the
    Companys engineering analysis such as
  • Electric demand profile showing minimum load
    during peak generation time,
  • Expected generation profile shown for a 24-hour
    period and typical 7-day duration, and
  • Customers complete electric service single-line
    diagram up to the service point supplied by the
    Companys secondary network EPS.

39
Technical Issues Upgrades and System
Modifications
Some Upper End Typical Utility Interconnection
Costs Duration Scheduling for Complex DG
Installations
Notes 1) Distribution EPS relates to 15kV class
system. 2) These are representative estimates
only and are not inclusive of all costs i.e.
land rights, removal costs, taxes, etc. which
will vary from job to job and that they are
presented here for budgetary purposes only.
40
Post ISA CoordinationWitness Testing (overview)
  • 1.) Relay Witness Testing
  • National Grid Witnesses relays trip based on
    settings approved by NG Protection Engineer
  • 2.) DTT Witness Testing
  • Communication (RFL) to the Local Substation
  • Typically Fiber or Lease line
  • 3.) RTU Witness Testing (1MW)
  • Provide Real time monitoring of Large DG at
    National Grids Regional Control Center.
  • Ordering Correct (MPLS) communication circuit
    from Verizon
  • Verizon Regional Account Teams consults with
    Verizons Service Delivery Department

41
Appendix Net Metering
42
Net Metering in Massachusetts
  • December 2009 Net Metering Tariff
  • Three Net Metering Classes
  • Class 1 Any generator up to 60 KW is eligible
  • Class 2 Agricultural, solar, or wind net
    metering facility over 60 KW but less than or
    equal to 1 MW (for municipal or government its
    per unit)
  • Class 3 Agricultural, solar, or wind net
    metering facility over 1 MW but less than or
    equal to 2 MW (for municipal or government its
    per unit)
  • Recent changes
  • limits projects to 2 MWs per parcel of land and a
    single meter
  • Must apply to the System of Assurance (SofA) at
    massaca.org for net metering services

43
Net Metering Tariff
  • Eligible customers can apply by submitting a
    Schedule Z.
  • Eligibility determined when approved within the
    SoA
  • Utility can not allow net metering without SofA
    approval
  • Class 2 and Class 3 will need a production meter
    on generation.
  • Net Metering is limited to 3 of each utilitys
    peak MW for private and 3 of peak for public
    projects for NG-MA this total limit is 308 MWs.
  • Contribution towards total 6 limit is posted on
    each utilitys web site and updated monthly
  • As of 4/16, NG-MA is at 94 MWs for the private
    and of 52 MW toward the public cap

44
Net Metering changes
  • Three Factor Approach (order 11-11C)
  • Single parcel / single interconnection point /
    single meter
  • Enacted to limit gaming and limits one meter per
    parcel of land with a limit of 2 MWs on the
    parcel for private entities
  • A governmental entity can have a total of 10 MWs
    of net-metered accounts throughout the state or
    on a parcel
  • No more 6 1 MW projects on a parcel
  • We can not provide more than one interconnection
    point (POI)
  • In addition, if theres an existing meter(s) on a
    parcel, then customer cant request a meter just
    for the net metering facility, it must be behind
    an existing meter
  • Otherwise separate metered project could earn
    higher credits than if it was behind an existing
    meter

45
Net Metering and Interconnection Order
  • Net Metering eligibility
  • The DPU ruled in the interconnection tariff order
    (10-75E) that Early ISAs will NOT meet the
    executed ISA requirement for entrance into the
    System of Assurance, and will refer the matter to
    DPU 11-11 for further investigation.
  • Until such time as the DPU reaches a resolution
    of the issue, Distribution Companies are directed
    to clearly mark Early ISAs on the title page and
    on the signature page with the words Early ISA
    for identification purposes.

46
Net Metering Credits
  • Energy use is netted over the billing month
  • If there is net energy use utility will bill
    customer for net use
  • If net energy export export kWH the following
  • Renewable installations will be credited at near
    retail rate for excess kWH (minus conservation
    and renewable energy charges).
  • Non-Renewable credited at average monthly
    clearing price ISO-NE
  • Tariff allows credits to be allocated (with
    limitations)
  • Customer still responsible for customer charges
    and demand charges, even if net export

        Credit the following charges Credit the following charges Credit the following charges Credit the following charges
Tier min max Type Default Service kWH Dist- ribution kWH Trans- mission kWH Trans- ition kWH
1 0 60 KW Agriculture Wind, PV X X X X
2 gt60 KW 1 MW Agriculture Wind, PV X X X X
3 gt1 MW 2 MW Agriculture Wind, PV X Govt only X X
47

48
(No Transcript)
49
(No Transcript)
50
Net Metering Production Reporting
  • Net Metering Tariff requires reporting of
    generators kWH output.
  • Class 1 Facilities to provide in writing by
    January 31 and September 30
  • Class 2 and Class 3 Facilities may participate in
    production tracking system (PTS).
  • Mass CEC provided PTS data to the utilities,
    still working through implementation issues
  • Utility will request data from Class 2 and 3
    Facilities

51
Net Metering Summary
  • If planning to Net Meter, submit Schedule Z with
    interconnection application
  • Correctly fill out Schedule Z
  • Name must match electric account of Host Customer
  • Must be signed by Host Customer
  • If allocating, verify name/address/account info
    of customer(s) or will need to submit corrected
    form
  • Production reporting is required.
  • Over 60 kWs require registration as a settlement
    only generator (SOG) associated ISO OP 18
    metering requirements
Write a Comment
User Comments (0)
About PowerShow.com