Title: Welcome to Daniel Painter
1Welcome to Daniel Painters Architectural
Engineering Senior Thesis Presentation of Two
Freedom Square
April 16, 2003Pennsylvania State University
2Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
3Background Information
- Located in Reston, Virginia
- Part of Reston Town Center
- Seven Miles from Dulles Airport
- 16-story Office Building
- 450,000 Square Feet
- 2nd building of a two building complex
- Total Cost 42 million
- Start and Finish Dates
- October 24, 2000
- June 15, 2002
- Building Code BOCA 1996
4Important People
- Owner Boston Properties
- Architect SmithGroup, Inc.
- Structural Engineer Tadjer Cohen Edelson
- General Contractor Centex Construction
5Picture of Two Freedom Square
6Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
7Existing Structure Floor System
- Two-way Flat Slab with Drop Panels
- 8 Slab
- 10 to 12 Drop Panels
- Floor to Floor Height
- 11-11
- Bay Sizes
- N-S direction
- 31-6
- 28-0
- 25-0
- E-W direction
- 30-6
- 29-0
8Bay Sizes
29
29
30.5
30.5
31.5
28
25
25
28
31.5
9Existing Structure Lateral System
- Eccentrically Braced Frames
- Columns vary in sizes
- Largest - 32 x 32
- Smallest - 12 x 24
- Column Strength
- 4,000 psi (13th to roof)
- 6,000 psi (9th to 12th)
- 8,000 psi (4th to 8th)
- 10,000 psi (cellar 2 to 3rd)
- Wind vs. Seismic
- Wind Controlled System
- Overall Drift was 21
- Allowable Drift
- h/400 6.6 inches
- Actual drift
- Wind 3.38 inches
- Seismic 1.68 inches
10Pros and Cons
- Efficient Core Design
- Low Floor to Floor Heights
- Cost Effective
- No Addition Fireproofing Required
11Proposed Problems
- Rearrange the Column Layout by placing the
Columns on the Column Lines - Investigate a Concrete and Steel Design of the
building - Redesign the Core of the Building
- Resize Crane
- Investigate Fireproofing
- Use the IBC 2000 code
12Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
13Structural Design Option ConcreteFloor System
- Two-way Flat Slab with Drop Panels
- 10 Slab
- 12 Drop Panels
- Floor to Floor Height
- 11-11
- Bay Sizes
- N-S direction
- 30-0
- 28-0
- 25-0
- E-W direction
- 30-6
- 29-0
14Bay Sizes
29
29
30.5
30.5
30
28
25
25
28
30
15Structural Design Option ConcreteLateral System
- Eccentrically Braced Frames
- Columns vary in sizes
- Largest - 30 x 30
- Smallest - 18 x 18
- Column Strength
- 5,000 psi was used for all floors
- Wind vs. Seismic
- Wind Controlled System
- Overall Drift was 21
- Allowable Drift
- h/400 6.6 inches
- h 220 ft
- Actual drift
- Wind 5.99 inches
16Pros and Cons
- Simpler Column Layout
- Smaller Columns
- Faster Schedule than Steel
- Same Floor to Floor Height of Existing Structure
- Increased Slab Depth
- Increased Drop Panel Depth
- Redesign of the Core
17Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
18Structural Design Option SteelFloor System
- Slab on Deck
- 2 LOK Deck
- 4½ Concrete Cover
- Maximum Span 10 ft
- Floor to Floor Height
- 14-0
- Non-Composite
- Composite
19Bay Sizes
29
29
30.5
30.5
30
28
25
25
28
30
20Structural Design Option SteelLateral System
- Moment Frames
- In both directions
- Not symmetric
- Comprised of W-Shapes
- Shear Walls
- 4 in the N-S direction
- 10 feet long each
- 2 in the E-W direction
- 20 feet long each
- Overall Height
- Increased to 250 feet
- Wind vs. Seismic
- Wind Controlled System
- Torsion
- Allowable Drift
- h/400 7.5 inches
- Actual Drift
- Wind 7.34 inches
21Pros and Cons
- Increased Floor to Floor Height
- Need for a Crane for Erection
- Longer Schedule than Concrete
- Need of Additional Fireproofing
- Higher Cost than Concrete
22Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
23Construction Management Design OptionEstimates
(RS Means)
Adjusted Cost per Sq. Ft. 69.41
Contractor Fee (25) 17.35
Architect Fee (6) 4.16
Final Cost per Sq. Ft. 90.92
Final Cost 40,934,911.60
Adjusted Cost per Sq. Ft. 74.19
Contractor Fee (25) 18.55
Architect Fee (6) 4.45
Final Cost per Sq. Ft. 97.19
Final Cost 43,757,853.70
24Construction Management Design OptionTime
Estimates (RS Means)
- Concrete Construction
- Existing Structure
- 2 weeks per floor
- 200 days
Steel Construction
Daily Output Amount Days Crews
Steel Erection 13.9 ton/day 3,466.479 tons 249.39 E-6
Non-Composite Deck 4,000 sq. ft./day 450,230 sq. ft. 112.56 E-4
Composite Deck 3,600 sq. ft./day 450,230 sq. ft. 125.06 E-4
Slab pumped 140 cy/day 18,759.58 cy 134 C-20
Slab crane bucket 100 cy/day 18,759.58 cy 187.6 C-7
25Construction Management Design OptionCrane Sizing
- Liebherr
- 290 HC Crane
- Tower Crane
- Cost 11,500 per month
- Capacity 9,070 pounds at 197 foot radius
Capacity at 197 ft
Example of Crane
26Crane Location
27Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
28Architecture Design Option
- New Column Layout
- Adjusted Core Layout
- Adjusted some Floor Layout
- Switched the bathrooms
- Separated the Elevators
Womens
Mens
29Pictures of Ground Floor Plan
30Pictures of 9th Floor Plan
31Pictures of 12th Floor Plan
32Pictures of 15th Floor Plan
33Pros and Cons
- Changed Core
- Column by the Elevators
34Order of Presentation
- Introduction/Background
- Existing Structure
- Structural Design Options
- Concrete Design
- Steel Design
- Breadth Design Option
- Construction Management
- Architecture
- Conclusion
- Questions
35Conclusion
- Steel vs. Concrete
- Concrete has a lower Floor to Floor Height
- Steel Requires Additional Fireproofing
- Concrete is Cheaper
- New Column Layout
- Requires a redesign of the Core of the Building
- Reduces the number of Columns in the building
- Schedule
- Concrete Building is faster to Construct
- Crane Necessary for Steel Construction
- So which Design should be Chosen??
36So which Design should be Chosen??
- The Existing Structure is the Logical Choice due
to the Cost, Schedule, and better Core Design - The Steel Redesign Adds Height, a Crane and Cost
- The Concrete Redesign could work with some
Refining
37Special Thanks
- William Hendrix and Joel Kelty from SmithGroup
- The AE Faculty
- Friends in the Lab
38Questions