Title: Construction Project Bankruptcy Strategic Considerations for Owners, General Contractors and Construction Managers
1Construction Project Bankruptcy Strategic
Considerations for Owners, General Contractors
and Construction Managers
2Presenters
- Charles A. Dale, Boston office, focuses his
practice on matters of bankruptcy and insolvency
with extensive experience in the construction
industry. -
- Joseph B.C. Kluttz, Charlotte office, focuses on
the structuring and restructuring of large
financial transactions within construction and
other industries to avoid and manage insolvency
risk.
Brian R. Davidson, Pittsburgh office, focuses in
the area of complex commercial litigation with an
emphasis on construction industry litigation.
Andrew L. Swope, Harrisburg office, focuses in
the area of complex commercial litigation with an
emphasis in commercial, construction and
bankruptcy law.
3State of the Industry
- McGraw-Hill Construction (of which ENR is part)
is forecasting a 7.4 decline in construction
starts in 2009, following declines of 12.4 this
year and 8.0 in 2007. All Sectors Go Negative
Next Year As A Real Recession Rattles Markets, by
Tim Grogan and Steve Setzer, ENR.com, 11/12/08 - Litigation is cropping up across the country
over building developments that unraveled as
U.S. financing tightened , leaving financiers,
developers and contractors to fight over who
should pay for the failed deals. As Building
Projects Collapse, Suits Pile Up, by Lynne Marek,
The National Law Journal, 11/3/08 - The U.K.'s 82 billion-pound building industry,
accounting for about 5 of the economy, has
ground to a halt, with little work being booked
because of faltering demand and a credit freeze.
Builders Hold 1.7 Billion Payments in
Recession Sign, by Tim Barwell, Bloomberg.com,
10/17/08
4(No Transcript)
5Basic Facts
- 200 Million Dollar Ethanol Plant
- Project Specific Owner
- EPC Contractor
- Major Subcontractors / Suppliers
- Project Partially Financed Remaining Financing
to be Obtained During Construction - Fast Track to Meet Peak Season Demand
- Performance / Payment Bonds
- Owner Letters of Credit
- Parental Guarantee from Owner
- Various Forms of Insurance
6Scenario 1
- Owner Learns About Problems on the Project
- Two Major Subcontractors Have Not Been Paid for
Two Months and are Threatening to File Liens - One Major Equipment Supplier Behind Schedule and
Unwilling to Complete Fabrication Absent
Substantial Advance Payment Due to Cash Flow
Problems Unrelated to the Project
7Scenario 1 The Issues
- What Can the Owner Do to Protect Its Interest
- Direct Payment
- Joint Payment Arrangements
- Set Off
- Lien on Equipment
- Passage of Title
- What Can the EPC Contractor Do to Protect Its
Interest - Mechanics Lien Waivers
- Performance Bonds
- Liens
8Scenario 2
- Major Equipment Supplier Goes Bankrupt
- Absent Delivery of the Equipment, the Project
Will be Substantially Delayed - EPC Contractor Claims that the Automatic Stay
Constitutes a Force Majeure Event
9Scenario 2 The Issues
- What Can the Owner/EPC Contractor Do to Protect
Their Interests - Passage of Title
- Executory Contracts
- Termination of Subcontract Due to Bankruptcy
Filing - Right of EPC Contractor/Owner to Equipment
- Force Majeure Issue
10Scenario 3
- Corn and Gas Prices Skyrocket Increases Costs
of Production and Decreases Demand for Ethanol - Financial System Meltdown Makes Financing Very
Difficult to Obtain - Owner Unable to Obtain Financing to Complete the
Project and Falls Behind on Invoices - Owner Asks EPC Contractor to Continue Performing
- EPC Contractor Has Procured 50 Million of
Services, Equipment and Materials From
Subcontractors and Suppliers That Has Not Been
Paid For - EPC Contractor Falls Behind on Invoices from
Subcontractors and Begins Receiving Demands for
Payment
11Scenario 3 The Issues
- What Can the EPC Contractor Do to Protect Its
Interests - Limited NTP with Guaranteed Funding
- Bonds
- Letter of Credit
- Securing Payments
- Escrow Accounts
- Parental Guarantees
- Can Market Forces Excuse Performance of a
Contract - Force Majeure
- Commercial Impracticability
12Scenario 4
- Owner Files For Bankruptcy Protection
- Owner Threatens To Reject The EPC Contract In
Bankruptcy - Subcontractors and Suppliers Assert Claims
Against EPC Contractor in Court and Arbitration
13Scenario 4 The Issues
- How Will the Bankruptcy Filing Impact the EPC
Contract - Treatment of Executory Contracts
- Impact of Assumption
- Can the EPC Contractor Continue to Push for
Payment - Automatic Stay
- What About Pre-Petition Payments from the Owner
- Preference Issues
14Scenario 5
- Owner Rejects EPC Contract
- EPC Contractor Asserts Claims Against Owner in
Bankruptcy Court - Multiple Subcontractors and Suppliers Commence
Separate Arbitrations and Lawsuits Against EPC
Contractor in Various Forums
15Scenario 5 The Issues
- What Happens as a Result of Rejecting the EPC
Contract - Rejection v. Termination
- How Can the EPC Contractor Obtain Payment
- Letter of Credit
- Payment Bonds
- Parental Guarantee
- Bankruptcy Claim Process
- Mechanics Liens
- Preference Issues
- EPC Contractor Options - Forum for Resolving
Claims - Arbitration Provisions in EPC Contract
- Extension of Automatic Stay to Other Actions
- Removal of Actions to Bankruptcy Court
16Scenario 6
- Project is Partially Destroyed by Fire
- Cause of Fire Is Traced to Equipment Provided by
Bankrupt Supplier - Owner Receives Substantial Settlement From
Casualty Insurer - Owner Seeks to Assert Claim Against Supplier and
Its Insurer in the Suppliers Bankruptcy Case
17Scenario 6 The Issues
- Right to Casualty Insurance Proceeds
- Lien Issues
- Right to Assert a Claim Against Supplier
- Claims Covered by Insurance Proceeds and the
Automatic Stay
18Construction Project Bankruptcy Strategic
Considerations for Owners, General Contractors
and Construction Managers
19Contact Information
- To contact Charles A. Dale
- chad.dale_at_klgates.com
- 617.261.3112
-
- To contact Joseph B.C. Kluttz
- joe.kluttz_at_klgates.com
- 704.331.7485
To contact Brian R. Davidson brian.davidson_at_klga
tes.com 412.355.6267
To contact Andrew L. Swope andrew.swope_at_klgates.c
om 717.231.4512