Title: Project Management
1Introduction to Management Science 8th
Edition by Bernard W. Taylor III
Chapter 13 Project Management
2Chapter Topics
- The Elements of Project Management
- The Project Network
- Probabilistic Activity Times
- Activity-on-Node Networks and Microsoft Project
- Project Crashing and Time-Cost Trade-Off
- Formulating the CPM/PERT Network as a Linear
Programming Model
3Overview
- Uses networks for project analysis.
- Networks show how projects are organized and are
used to determine time duration for completion. - Network techniques used are
- CPM (Critical Path Method)
- PERT (Project Evaluation and Review Technique)
- Developed during late 1950s.
4Elements of Project Management
- Management is generally perceived as concerned
with planning, organizing, and control of an
ongoing process or activity. - Project Management is concerned with control of
an activity for a relatively short period of time
after which management effort ends. - Primary elements of Project Management to be
discussed - Project Team
- Project Planning
- Project Control
5The Elements of Project Management The Project
Team
- Project team typically consists of a group of
individuals from various areas in an organization
and often includes outside consultants. - Members of engineering staff often assigned to
project work. - Most important member of project team is the
project manager. - Project manager is often under great pressure
because of uncertainty inherent in project
activities and possibility of failure. - Project manager must be able to coordinate
various skills of team members into a single
focused effort.
6The Elements of Project Management The Project
Network
- A branch reflects an activity of a project.
- A node represents the beginning and end of
activities, referred to as events. - Branches in the network indicate precedence
relationships. - When an activity is completed at a node, it has
been realized.
Figure 13.2 Network for Building a House
7The Project Network Planning and Scheduling
- Network aids in planning and scheduling.
- Time duration of activities shown on branches
Figure 13.3 Network for Building a House with
Activity Times
8The Project Network Concurrent Activities
- Activities can occur at the same time
(concurrently). - A dummy activity shows a precedence relationship
but reflects no passage of time. - Two or more activities cannot share the same
start and end nodes.
Figure 13.4 Expanded Network for Building a House
Showing Concurrent Activities
9The Project Network Paths Through a Network
Table 8.1 Paths Through the House-Building Network
10The Project Network The Critical Path (1 of 2)
- The critical path is the longest path through the
network the minimum time the network can be
completed. In Figure 13.5 - Path A 1 ? 2 ? 3 ? 4 ? 6 ? 7, 3 2 0 3 1
9 months - Path B 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? 7, 3 2 0 1
1 1 8 months - Path C 1 ? 2 ? 4 ? 6 ? 7, 3 1 3 1 8
months - Path D 1 ? 2 ? 4 ? 5 ? 6 ? 7, 3 1 1 1 1
7 months
11The Project Network The Critical Path (2 of 2)
Figure 13.6 Alternative Paths in the Network
12The Project Network Activity Scheduling
Earliest Times
- ES is the earliest time an activity can start.
ESij Maximum (EFi) - EF is the earliest start time plus the activity
time. EFij ESij tij
Figure 13.7 Earliest Activity Start and Finish
Times
13The Project Network Activity Scheduling
Earliest Times
- LS is the latest time an activity can start
without delaying critical path time. LSij LFij
- tij - LF is the latest finish time. LFij Minimum
(LSj)
Figure 13.8 Latest Activity Start and Finish Times
14The Project Network Activity Slack
- Slack is the amount of time an activity can be
delayed without delaying the project. - Slack Time exists for those activities not on the
critical path for which the earliest and latest
start times are not equal. - Shared Slack is slack available for a sequence of
activities.
Figure 13.9 Earliest and Latest Activity Start
and Finish Times
15The Project Network Calculating Activity Slack
Time (1 of 2)
- Slack, Sij, computed as follows Sij LSij -
ESij or Sij LFij - EFij
Figure 13.10 Activity Slack
16The Project Network Calculating Activity Slack
Time (2 of 2)
Table 8.2 Activity Slack
17Probabilistic Activity Times
- Activity time estimates usually can not be made
with certainty. - PERT used for probabilistic activity times.
- In PERT, three time estimates are used most
likely time (m), the optimistic time (a) , and
the pessimistic time (b). - These provide an estimate of the mean and
variance of a beta distribution - mean (expected time)
- variance
18Probabilistic Activity Times Example (1 of 3)
Figure 13.11 Network for Installation Order
Processing System
19Probabilistic Activity Times Example (2 of 3)
Table 8.3 Activity Time Estimates for Figure 13.11
20Probabilistic Activity Times Example (3 of 3)
Figure 13.12 Network with Mean Activity Times and
Variances
21Probabilistic Activity Times Earliest and Latest
Activity Times and Slack
Figure 13.13 Earliest and Latest Activity Times
22Probabilistic Activity Times Earliest and Latest
Activity Times and Slack
Table 8.4 Activity Earliest and Latest Times and
Slack
23Probabilistic Activity Times Expected Project
Time and Variance
- The expected project time is the sum of the
expected times of the critical path activities. - The project variance is the sum of the variances
of the critical path activities. - The expected project time is assumed to be
normally distributed (based on central limit
theorem). - In example, expected project time (tp) and
variance (vp) interpreted as the mean (?) and
variance (?2) of a normal distribution
24Probability Analysis of a Project Network (1 of 2)
- Using normal distribution, probabilities are
determined by computing number of standard
deviations (Z) a value is from the mean. - Value is used to find corresponding probability
in Table A.1, Appendix A.
25Probability Analysis of a Project Network (2 of 2)
Figure 13.14 Normal Distribution of Network
Duration
26Probability Analysis of a Project Network Example
1 (1 of 2)
- Z value of 1.90 corresponds to probability of
.4713 in Table A.1, Appendix A. Probability of
completing project in 30 weeks or less (.5000
.4713) .9713. - ?2 6.9 ? 2.63
- Z (x-?)/ ? (30 -25)/2.63 1.90
27Probability Analysis of a Project Network Example
1 (2 of 2)
Figure 13.15 Probability the Network Will Be
Completed in 30 Weeks or Less
28Probability Analysis of a Project Network Example
2 (1 of 2)
- Z (22 - 25)/2.63 -1.14
- Z value of 1.14 (ignore negative) corresponds to
probability of .3729 in Table A.1, appendix A. - Probability that customer will be retained is
.1271
29Probability Analysis of a Project Network Example
2 (2 of 2)
Figure 13.16 Probability the Network Will Be
Completed in 22 Weeks or Less
30Probability Analysis of a Project
Network CPM/PERT Analysis with QM for Windows
Exhibit 13.1
31Activity-on-Node Networks and Microsoft Project
- The project networks developed so far have used
the activity-on-arrow (AOA) convention. - Activity-on-node (AON) is another method of
creating a network diagram. - The two different conventions accomplish the same
thing, but there are a few differences. - An AON diagram will often require more nodes than
an AOA diagram. - An AON diagram does not require dummy activities
because two activities will never have the same
start and end nodes. - Microsoft Project handles only AON networks.
32Activity-on-Node Networks and Microsoft
Project Node Structure
This node includes the activity number in the
upper left-hand corner, the activity duration in
the lower left-hand corner, and the earliest
start and finish times, and latest start and
finish times in the four boxes on the right side
of the node.
Figure 13.17 Activity-on-Node Configuration
33Activity-on-Node Networks and Microsoft
Project AON Network Diagram
Figure 13.18 House-Building Network with AON
34Activity-on-Node Networks and Microsoft
Project Microsoft Project (1 of 4)
Exhibit 13.2
35Activity-on-Node Networks and Microsoft
Project Microsoft Project (2 of 4)
Exhibit 13.3
36Activity-on-Node Networks and Microsoft
Project Microsoft Project (3 of 4)
Exhibit 13.4
37Activity-on-Node Networks and Microsoft
Project Microsoft Project (4 of 4)
Exhibit 13.5
38Project Crashing and Time-Cost Trade-Off
Definition
- Project duration can be reduced by assigning more
resources to project activities. - Doing this however increases project cost.
- Decision is based on analysis of trade-off
between time and cost. - Project crashing is a method for shortening
project duration by reducing one or more critical
activities to a time less than normal activity
time. - Crashing achieved by devoting more resources to
crashed activities.
39Project Crashing and Time-Cost Trade-Off Example
Problem (1 of 5)
Figure 13.19 Network for Constructing a House
40Project Crashing and Time-Cost Trade-Off Example
Problem (2 of 5)
Crash cost and crash time have linear
relationship total crash cost/total crash time
2000/5 400/wk
Figure 13.20 Time-Cost Relationship for Crashing
Activity 1?2
41Project Crashing and Time-Cost Trade-Off Example
Problem (3 of 5)
Table 8.5 Normal Activity and Crash Data for the
Network in Figure 13.19
42Project Crashing and Time-Cost Trade-Off Example
Problem (4 of 5)
Figure 13.21 Network with Normal Activity Times
and Weekly Activity Crashing Costs
43Project Crashing and Time-Cost Trade-Off Example
Problem (5 of 5)
- As activities are crashed, the critical path may
change and several paths may become critical.
Figure 13.22 Revised Network with Activity 1?2
Crashed
44Project Crashing and Time-Cost Trade-Off Project
Crashing with QM for Windows
Exhibit 13.6
45Project Crashing and Time-Cost Trade-Off General
Relationship of Time and Cost (1 of 2)
- Project crashing costs and indirect costs have an
inverse relationship. - Crashing costs are highest when the project is
shortened. - Indirect costs increase as the project duration
increases. - Optimal project time is at minimum point on the
total cost curve.
46Project Crashing and Time-Cost Trade-Off General
Relationship of Time and Cost (2 of 2)
Figure 13.23 A Time-Cost Trade-Off
47The CPM/PERT Network Formulating as a Linear
Programming Model
- The objective is to determine the earliest time
the project can be completed (i.e., the critical
path time).
General linear programming model Minimize Z
?xi subject to xj - xi ? tij for all
activities i ? j xi, xj ? 0 Where xi
earliest event time of node i xj earliest
event time of node j tij time of activity i ? j
48The CPM/PERT Network Example Problem Formulation
and Data (1 of 2)
Minimize Z x1 x2 x3 x4 x5 x6
x7 subject to x2 - x1 ? 12 x3 - x2 ? 8 x4 -
x2 ? 4 x4 - x3 ? 0 x5 - x4 ? 4 x6 - x4 ?
12 x6 - x5 ? 4 x7 - x6 ? 4 xi, xj ? 0
49The CPM/PERT Network Example Problem Formulation
and Data (2 of 2)
Figure 13.24 CPM/PERT Network for the
House-Building Project with Earliest Event Times
50The CPM/PERT Network Example Problem Solution
with Excel (1 of 4)
Exhibit 13.7
51The CPM/PERT Network Example Problem Solution
with Excel (2 of 4)
Exhibit 13.8
52The CPM/PERT Network Example Problem Solution
with Excel (3 of 4)
Exhibit 13.9
53The CPM/PERT Network Example Problem Solution
with Excel (4 of 4)
Exhibit 13.10
54Probability Analysis of a Project Network Example
Problem Model Formulation
xi earliest event time of node I xj earliest
event time of node j yij amount of time by
which activity i ? j is crashed Minimize Z
400y12 500y23 3000y24 200y45 7000y46
200y56 7000y67 subject to y12 ? 5 y12 x2 -
x1 ? 12 x7 ? 30 y23 ? 3 y23 x3 - x2 ? 8
y67 ? 1 y24 ? 1 y24 x4 - x2 ? 4 x67 x7 -
x6 ? 4 y34 ? 0 y34 x4 - x3 ? 0 xj, yij ? 0
y45 ? 3 y45 x5 - x4 ? 4 y46 ? 3 y46 x6 -
x4 ? 12 y56 ? 3 y56 x6 - x5 ? 4
55Probability Analysis of a Project Network Example
Problem Excel Solution (1 of 3)
Exhibit 13.11
56Probability Analysis of a Project Network Example
Problem Excel Solution (2 of 3)
Exhibit 13.12
57Probability Analysis of a Project Network Example
Problem Excel Solution (3 of 3)
Exhibit 13.13
58PERT Project Management Example Problem Problem
Statement and Data (1 of 2)
- Given the following data determine the expected
project completion time and variance, and the
probability that the project will be completed in
28 days or less.
59PERT Project Management Example Problem Problem
Statement and Data (2 of 2)
60PERT Project Management Example Problem Solution
(1 of 4)
Step 1 Compute the expected activity times and
variances.
61PERT Project Management Example Problem Solution
(2 of 4)
Step 2 Determine the earliest and latest times
at each node.
62PERT Project Management Example Problem Solution
(3 of 4)
Step 3 Identify the critical path and compute
expected completion time and
variance. Critical path (activities with no
slack) 1 ? 2 ? 3 ? 4 ? 5 Expected project
completion time (tp) 24 days Variance v 4
4/9 4/9 1/9 5 days
63PERT Project Management Example Problem Solution
(4 of 4)
Step 4 Determine the Probability That the
Project Will be Completed in 28 days or
less. Z (x - ?)/? (28 -24)/?5
1.79 Corresponding probability from Table A.1,
Appendix A, is .4633 and P(x ? 28) .9633.
64(No Transcript)