Title: FET Environmental Primer Air Regulations: Permitting Basics


1
FET Environmental Primer Air Regulations
Permitting Basics
  • Steven Klafka, P.E.
  • Wingra Engineering, S.C.
  • Madison, Wisconsin
  • www.wingraengineering.com

2
Air Quality Permit Overview
  • WDNR responsible for permit issuance
  • USEPA oversight
  • Construction permits for new sources
  • Operation permits for existing sources

3
Air Pollution Sources
  • Operations Issued Air Quality Permits
  • Stationary - Process or Point
  • Stationary - Factory or Facility
  • Portable - Asphalt Plant
  • Indirect - Parking Lots and Highways
  • Not Issued Air Quality Permits
  • Area - Small Boilers, Wildfires
  • Mobile - Cars, Trucks, Busses
  • Off Road Lawn mowers, Snowmobiles

4
Wisconsin VOC Emissions
5
Air Pollution Sources Issued Permits
  • Burning of fuels or wastes.
  • Conveying or handling of dusty materials like
    sand, wood shavings, etc.
  • Evaporation of solvents from painting, printing,
    cleaning, gluing, storage, etc.
  • Chemical processing and reactions.

6
Types of Emission Estimates
  • MTE or Uncontrolled Need for Permit
  • Full capacity 8,760 hrs/yr 0 collection
  • Potential Determines Compliance
  • Full capacity 8,760 hrs/yr Required
  • Actual Reported for Annual Fees
  • Actual capacity, hrs/yr and collection

7
Sample Permit Calculations 1
  • Shotblasting Operation with 99 Efficient
    Baghouse
  • Capacity 2 tons per hour of metal
  • USEPA Emission Factor 17 lbs TSP/ton of metal
  • Applicable Discharge Limit NR 415.05(2) 3.59
    P 0.62
  • Comparison with General Permit Exemption
    Thresholds
  • MTE 2 tph x 17 lbs of TSP/ton 34 lbs of
    TSP/hr
  • gt 5.7 lbs TSP/hr, NR 406 construction permit
    required
  • Actual 34 lbs/hr x (1 0.99) 0.34 lbs TSP/hr
  • Potential 3.59 (2) 0.62 5.5 lbs TSP/hr

8
Types of Emission Estimates
9
CONSTRUCTION PERMITS
  • Must be issued prior to construction or
    modification of regulated sources.
  • NR 406 - Exemptions and Schedules
  • NR 405 - PSD rules for Large Projects
  • NR 410 Fees
  • NR 411 Parking Lots and Roads
  • NR 150 Environmental Assessment EIS

10
Types of Specific Exemptions
  • Natural gas-fired boilers lt 25 mmbtu/hr
  • Wood-fired boilers lt 5 mmbtu/hr
  • Paint/ink usage lt 1,666 lbs VOC/month
  • VOC storage tanks lt 10,000 gallons
  • Emergency generators lt 3,000 kilowatts
  • Each state has own specific exemptions.

11
Types of General Exemptions
  • Uncontrolled emissions lt all permit thresholds
  • 5.7 lbs/hr of total suspended particles (TSP)
  • 3.4 lbs/hr of particles lt 10 microns (PM10)
  • 9.0 lbs/hr of sulfur dioxide (SO2)
  • 9.0 lbs/hr of nitrogen oxides (NOx)
  • Thresholds for gt500 air toxics under NR 445
  • Use specific exemption first, then general.

12
Sample Permit Calculations 2
  • Paint Spray Booth with 95 Efficient Filters
  • Actual paint usage 600 gallons per month
  • Maximum paint usage 1.5 gallons per hour
  • Maximum VOC content 3.5 lbs VOC per gallon
  • Maximum solids content 6.0 lbs solids per
    gallon
  • Spray gun transfer efficiency 70
  • Comparison with Specific Permit Exemption
    Thresholds
  • Actual 600 gpm x 3.5 lbs/gal 2,100 lbs/month
    VOC
  • gt 1,666 lbs of VOC/month exemption threshold

13
Sample Permit Calculations 2
  • Comparison with General Permit Exemption
    Thresholds
  • VOC Emission Estimate
  • MTE 1.5 gph x 3.5 lbs/gal 5.3 lbs/hr
  • lt 5.7 lbs/hr general exemption threshold for VOC
  • PM10 Emission Estimate
  • MTE 1.5 gph x 6.0 lbs/gal x (1 - 0.7) 2.7
    lbs/hr
  • lt 3.4 lbs/hr general exemption threshold for PM10
  • ConclusionNo NR 406 construction permit is
    required based on the general permit exemption
    thresholds.

14
Schedule and Fees
  • Permit issuance within 2 to 12 months.
  • 30-day public comment period.
  • Public hearing if requested by public or
    applicant.
  • 1,350 initial application fee
  • 2,300 to 85,000 permit issuance fee
  • NR 438 annual emission fee (35/ton)

15
Criteria for Permit Approval
  • Comply with emission limitations.
  • Comply with air quality standards using
    dispersion modeling analysis.
  • Standards include the NR 404 National Ambient Air
    Quality Standards or NR 445 Acceptable Air
    Concentrations for hazardous air pollutants.
  • Comply with current policies.

16
Typical Permit Schedule
  • Week 1 Submit application to DNR
  • Week 5 Receive DNR request for information.
  • Week 7 Respond to request for information.
  • Week 11 DNR issues draft permit and PD.
  • Week 12 Publish notice for public comments.
  • Week 16 Public comment period ends.
  • Week 18 DNR issues final permit and invoice.

17
Expedited Permit Issuance
  • Pre-application meeting with DNR.
  • Submit a complete application.
  • Anticipate DNR application review needs.
  • Provide emission calculations.
  • Comply with applicable requirements.
  • Conduct DNR modeling risk analyses.
  • Prepare environmental assessment.
  • Anticipate public involvement.

18
Recent Air Permit Enforcement
  • 45,000 Failure to obtain permit.
  • 45,600 Exceeded emission limits.
  • 60,000 Failure to maintain records.
  • 65,000 Failure to obtain permit.
  • 71,820 Failure to maintain records.
  • 86,450 Failure to raise stack.
  • http//www.doj.state.wi.us/dls/environpro/news/

19
Keys to Successful Air Permits
  • Stay involved in review process.
  • Review preliminary permit prior to official
    draft permit.
  • Anticipate future production needs and provide
    flexibility in permit.
  • Minimize unnecessary requirements.

20
PSD Rules Add Complexity
  • NR405-Prevention of Significant Deterioration
  • Applies to new large sources
  • Applies to modifications of large sources
  • Additional permit issuance time
  • Best Available Control Techology or BACT
  • Pre-construction ambient monitoring
  • Dispersion modeling for increments NAAQS
  • Visibility, growth and vegetation analyses

21
PSD Thresholds (tons/year)
Air Pollutant New Plant Modification
PM10 100/250 15
SO2 100/250 40
NOx 100/250 40
CO 100/250 100
VOC 100/250 40
Pb 100/250 0.6
22
PSD Avoidance
  • PSD rules uses potential emissions.
  • Permit restrictions on capacity,operating hours,
    or collection are considered.
  • PSD avoided to save permit issuance complexity or
    processing time, or eliminate control
    requirements.
  • Balance restrictions and future growth.

23
Anatomy of an Air Permit
  • Description of source or process.
  • Emission limitations.
  • Wis. Adm. Code citations.
  • Record keeping requirements.
  • Monitoring requirements.
  • Testing and certification requirements.
  • Reporting requirements.

24
Sample Air Permit
25
Construction Permit References
  • Jeff Hanson, Construction Permit Leader
    hansojc_at_dnr.state.us and (608) 267-6876
  • Regional DNR Office Air Staff
  • Air Permit Web Site
  • http//www.dnr.state.wi.us/org/aw/air/reg/regs.
    htm
  • Provides application forms, instructions,
    issued and pending construction permits, and
    modeling guidance.
  • Application Forms Instructions
  • ftp//www.dnr.state.wi.us/DAW/AM/permits/AppForms/
  • Issued Pending Operation Permits
  • ftp//www.dnr.state.wi.us/DAW/AM/permits/OpPermit/
    PmtDocs/

26
OPERATION PERMITS
  • Application must be filed for existing regulated
    sources or prior to expiration of construction
    permits.
  • Title V of 1990 Clean Air Act Amendments
    (Congress)
  • 40 CFR Part 70 (USEPA)
  • NR 407 - Exemptions Schedules (WI)

27
Processes included in Permit
  • Similar exemption thresholds as provided for
    construction permits.
  • Includes processes which require a construction
    permit if built today.
  • Includes minor processes which exceed NR 407
    Table 2 inclusion thresholds (i.e. 2,000 lbs/yr).

28
Types of Operation Permits
  • FOP or Title V or Part 70 Permit
  • 100 TPY PM, SO2, NOx, CO, VOC, Pb, Lower TPY for
    VOC if located in ozone nonattainment area (SE
    Wisconsin)
  • 10 TPY Federal Air Toxic or 25 TPY Combined Air
    Toxics
  • Subject to most thorough review and compliance
    demonstration.
  • Subject to MACT, if available.
  • All applications for existing WI sources were due
    by 1995.

29
Types of Operation Permits Contd
  • Federally Enforceable Synthetic Minor Permit
  • Limits potential emissions by using operating
    hours or production restrictions to remain below
    thresholds.
  • Avoids MACT or other FOP requirements.
  • All WI applications were due by 1995.
  • Balance FESOP restrictions and future growth.

30
Types of Operation Permits Contd
  • SOP State Only Permit
  • Required by state not federal rules.
  • Potential emissions less than FOP thresholds
    (i.e. 100 TPY)
  • Only annual compliance reports.
  • All applications for existing WI sources were due
    by 1998.

31
Types of Operation Permits Contd
  • Applications for all existing sources in
    Wisconsin have been submitted to DNR.
  • Construction permits for new or modified
    processes are replaced with operation permits
    prior to expiration or incorporated into the
    facility-wide operation permit.

32
Operation Permit References
  • Keith Pierce, Operation Permit Leader
    pierck_at_dnr.state.us and (608) 267-0562
  • Regional DNR Office Air Staff
  • DNR Air Permit Web Site
  • http//www.dnr.state.wi.us/org/aw/air/reg/regs
    .htm
  • Provides application forms, instructions,
    issued and pending operation permits, permit
    application software.
  • USEPA MACT Web Site
  • http//www.epa.gov/ttn/atw/eparules.html

33
Air Permits in a Nutshell
  • NR 406 construction permits required prior to the
    start of construction or modification.
  • NR 407 operation permits are for existing
    processes, or replace construction permits.
  • Review permits thoroughly before issuance to
    assure accuracy and flexibility.