Sorting Out Whitby Landmark - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Sorting Out Whitby Landmark

Description:

Sorting Out Whitby Landmark Duncan W. Glaholt Doe v. Canadian Surety Co. [1937] S.C.R. 1 Bonds as a specialty One law for all sureties An undertaking given by ... – PowerPoint PPT presentation

Number of Views:74
Avg rating:3.0/5.0
Slides: 32
Provided by: mar1319
Category:

less

Transcript and Presenter's Notes

Title: Sorting Out Whitby Landmark


1
Sorting Out Whitby Landmark
  • Duncan W. Glaholt

2
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
3
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
4
Doe v. Canadian Surety Co. 1937 S.C.R. 1
  • Bonds as a specialty
  • One law for all sureties
  • An undertaking given by the contractor without
    the consent of the surety was a variation of the
    contract discharging the surety.

5
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
6
Thomas Fuller Construction Co. (1985) Ltd. v.
Continental Insurance Co., 1973 3 O.R. 202
(H.C.)
  • It is not a breach not to report minor delays.
  • Notice was necessary, but only when default was
    so serious that a declaration of default and a
    call upon the bonding company to perform is
    required.

7
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
8
Citadel General Assurance Co. v. Johns-Manville
Canada Inc.(1983), 147 D.L.R. (3d) 593 (S.C.C.)
  • Compensated v. gratuitous suretyship
  • Only a prejudicial non-compliance is a defense
  • Even then, only to the extent of the prejudice

9
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
10
Falk Bros. Industries Ltd. v. Elance Steel
Fabricating Co. Ltd.(1989), 62 D.L.R. (4th) 236
(S.C.C.)
  • Bonds as a class insurance
  • The world post Citadel
  • Failure to give notice is less serious than
    failure to bring an action
  • Relief from forfeiture can be granted under
    Insurance Act in respect of delayed notices of
    claims.

11
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
12
Paul DAoust Construction Ltd. v. Markel
Insurance Company of Canada(2001), 208 D.L.R.
(4th) 225 (S.C.C.)
  • Bonds as a specialty again
  • To be effective, an original signed bond must be
    delivered.

13
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
14
Whitby Landmark Developments Inc. v. Mollenhauer
Construction Ltd. (2002), 4 C.L.R. (3d) 1 (Ont.
S.C.J.)
  • Bonds as a contract
  • Failure to give notice of default fatal
  • Bond extends to cost savings provisions of
    contract

15
Justice Lamek
  • If Zurich intended to restrict the obligations
    that it undertook or to eliminate certain of
    Mollenhauers contractual obligations from the
    scope of the bond, it could easily have done
    so.  It did not.  Instead, Zurich issued a bond
    that obliged it, in the event of Mollenhauers
    default, to "complete the Contract in accordance
    with its terms and conditions".  It would be
    difficult to formulate a provision that would
    more easily embrace all of the obligations of
    Mollenhauers under its contract with Landmark.

16
Justice Lamek
  • If Zurich intended to restrict the obligations
    that it undertook or to eliminate certain of
    Mollenhauers contractual obligations from the
    scope of the bond, it could easily have done
    so.  It did not.  Instead, Zurich issued a bond
    that obliged it, in the event of Mollenhauers
    default, to "complete the Contract in accordance
    with its terms and conditions".  It would be
    difficult to formulate a provision that would
    more easily embrace all of the obligations of
    Mollenhauers under its contract with Landmark.

17
Justice Lamek
  • If Zurich intended to restrict the obligations
    that it undertook or to eliminate certain of
    Mollenhauers contractual obligations from the
    scope of the bond, it could easily have done
    so.  It did not.  Instead, Zurich issued a bond
    that obliged it, in the event of Mollenhauers
    default, to "complete the Contract in accordance
    with its terms and conditions".  It would be
    difficult to formulate a provision that would
    more easily embrace all of the obligations of
    Mollenhauers under its contract with Landmark.

18
Justice Lamek
  • If Zurich intended to restrict the obligations
    that it undertook or to eliminate certain of
    Mollenhauers contractual obligations from the
    scope of the bond, it could easily have done
    so.  It did not.  Instead, Zurich issued a bond
    that obliged it, in the event of Mollenhauers
    default, to "complete the Contract in accordance
    with its terms and conditions".  It would be
    difficult to formulate a provision that would
    more easily embrace all of the obligations of
    Mollenhauers under its contract with Landmark.

19
Reaction to Whitby Landmark Trial Decision
  • J. Steven Tatrallyay
  • Decision will have a major impact on the surety
    industry
  • R. Bruce Reynolds
  • Decision is much ado about nothing
  • Courts statement that the CCDC performance bond
    clearly and unambiguous-ly rendered the surety
    liable for collateral mone-tary obligations was
    just plain wrong.

20
Whitby Landmark Developments Inc. v. Mollenhauer
Construction Ltd. (2003), 67 O.R. (3d) 628 (C.A.)
  • There is no basis in the language of the bond
    or in the circumstances surrounding its
    negotiation or completion to suggest that the
    cost-sharing provisions of the construction
    contract are not included as bonded losses.

21
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
22
Meanwhile, in Saskatchewan
  • Lac La Ronge Indian Band v. Dallas Contracting
    Ltd. (2004), 35 C.L.R. (3d) 236 (Sask. C.A.)

23
Facts
  • Compensated surety
  • CCDC performance bond
  • Late completion
  • Termination
  • Liquidated damages

24
Trial Decision (2001), 9 C.L.R. (3d) 25 (Sask.
Q.B.)
  • Surety was liable with respect to liquidated
    damages for delay.

25
Trial Judge
  • the phrase complete the Contract does not
    confine the suretys liability to completing the
    work described in the Contract
  • by the terms of the Contract, the Band may deduct
    liquidated damages from the amount otherwise
    payable to Dallas under the Contract and,
    therefore, may deduct them from the remaining
    funds
  • the definition in the Bond of the term balance
    of the Contract price confirms the ability to
    deduct liquidated damages from the amount
    otherwise payable to Dallas.

26
Court of Appeal (Jackson J.A.)(2004), 35 C.L.R.
(3d) 236 (Sask. C.A.)
  • Surety was not liable with respect to liquidated
    damages for delay.

27
  • Whitby
  • In case of default, surety has 3 options
  • - remedy default
  • - complete contract
  • - obtain new bid
  • Lac La Ronge
  • In case of default, surety has 3 options
  • - remedy default
  • - complete contract
  • - obtain new bids

28
  • Whitby
  • There was no qualification on type of default
    referred to
  • Third option did not limit suretys obligation to
    funding the completion of physical construction,
    but included other costs and damages.
  • Lac La Ronge
  • Surety did neither, but the measure of damages
    cant be greater than if it had fulfilled either
    option.
  • Suretys obligation cant be greater under option
    2 than under option 3, because no surety would
    ever use option 2 if it meant greater liability

29
  • Whitby
  • Third option required surety to pay costs of
    completion less balance of contract price, which
    was defined as total amount payable by obligee to
    principal less amount paid by principal to
    obligee.
  • Therefore, amount surety had to pay to complete
    was higher than it would have been without cost
    sharing agreement.
  • Lac La Ronge
  • Balance of contract price does not mean damages
    award can be deducted from amount payable.
  • Total amount payable is amount of contract.
  • Words complete the contract can more easily be
    interpreted as complete the work than as
    perform all obligations under the contract.

30
?
Lac La Ronge
Whitby Landmark
Elance Steel
Paul DAoust
Citadel v. Johns Manville
Doe v. Canadian Surety
Thomas Fuller
31
The End
Write a Comment
User Comments (0)
About PowerShow.com