Loy Yang Power Station Control System Upgrade. - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Loy Yang Power Station Control System Upgrade.

Description:

... and Training Optimised Sootblowing Loy Yang Power has four superheater elements, 2 reheater elements and an economiser within each furnace convection path. – PowerPoint PPT presentation

Number of Views:178
Avg rating:3.0/5.0
Slides: 24
Provided by: rtom8
Category:

less

Transcript and Presenter's Notes

Title: Loy Yang Power Station Control System Upgrade.


1
Loy Yang Power Station Control System Upgrade.
BARRY DUNGEY General Manager Engineering
Maintenance June 2008
2
Key Project Objectives
  • Original control system is of mid 1970s design
    with circuit board, relay and wire wrap
    technology.
  • The main driver for the project is the difficulty
    in supporting obsolete control equipment.( Our
    policy is to run for approx 5 years following
    withdrawal of support by our equipment supplier)
  • The opportunity is also being taken to gain
    improvements in system performance and reduce
    business risk exposure.
  • ( i.e. Alternative control room)
  • Plant trip rates were increasing with a
    significant number due to control system faults.
  • Upgrade will include the installation of a
    separate plant safety system.
  • Complete unit cut over to be achieved in 35-40
    day outage duration

3
Number of Trips Trip Rate.
4
Project Timeline
5
Loy Yang Power Expectations
  • The current control system is fairly tight as it
    is already being run on a digital platform, hence
    LYP are not expecting significant direct
    improvements in efficiency as a result. (Some
    studies indicate that up to 2 improvement is
    possible from older systems)
  • The system will deliver flexibility to do things
    smarter, fault find easier, and implement future
    plant logic change easier.
  • The supplier has provided a guarantee that they
    will support the new control system for 35 years,
    hence no further significant upgrades are
    expected in the remaining life of the plant.

6
Yokogawa Site Observations
  • Site surveys noted that the current control
    strategies are sound.
  • Boiler thermocouple dynamic response suitably
    fast to allow for quick movement in loads.
  • Existing spray valves and actuators not
    significantly limiting performance
  • Existing controls have some issues when limits
    are reached wind-up, excess output pull-back,
    etc

7
Benefits from Yokogawa control design
  • Integration between steam temperature and
    combustion controls minimises interaction
  • Over-firing minimised by using transient
    contribution of superheater sprays to main steam
    pressure control
  • Contributes to wider operating range from milling
    plant
  • Boiler thermal stress reduced
  • Flexibility on turbine ramp rates possible
  • On line efficiency tools improved.

8
Benefits (Continued)
  • In summary, the current process is about
    achieving incremental improvements, particularly
    with
  • Start up and shutdown sequences
  • Better trim controls associated with excess air
    (oxygen).
  • Maximising future flexibility with an open system
    which can accept third party products.
  • Improved Operator information and diagnostics

9
Original Coal Handling Plant
10
Coal Handling Plant (Part)
11
Coal Handling Plant (Overview Screen)
12
Major Plant Drive Graphic
13
Future Control Room Layout
14
Simulation For Engineering and Training
15
Optimised Sootblowing
  • Loy Yang Power has four superheater elements, 2
    reheater elements and an economiser within each
    furnace convection path.
  • To manage boiler fouling, 74 sootblowers are used
    to clean the elements using high pressure steam
    from the Reheat Steam System.
  • The original design used a time based operation
    system with two cleaning cycles per day.

16
Original Sootblower Control Panel
17
Optimised Sootblowing - NGISB
  • An optimised sootblowing system (NGISB - Next
    Generation Intelligent Sootblowing System) has
    been installed on one unit as a trial. It uses a
    Synengco supplied NGISB system interfaced to PLC
    based sootblower controls supplied by Siemens.
  • The NGISB gathers data from the plant historian
    at near real time and continuously calculates the
    ideal sootblower schedule using a thermal boiler
    model within business rule constraints.

18
Sootblower Optimisation System Aims
  • Reduce sootblowing frequency
  • Maintain boiler attemporator spray flows within
    the ideal valve control range
  • Minimise Reheat Spray Flow
  • Maintain Steam and Metal Temperatures close to
    target and minimise alarm conditions to maximise
    thermal efficiency.
  • Set and Forget operation.

19
Siemens/Synengco Sootblower Control System
20
Optimised Sootblowing Results
  • Sootblowing frequency reduced to 32.5 of the
    original time based schedule.
  • Annualised Savings per Unit
  • 24.7 TJ of energy
  • 8.1 Ml of Cold Reheat Steam
  • 4,900 Tonnes of CO2

21
(No Transcript)
22
Optimised Sootblowing Results (Continued)
  • Reducing RH Spray Flow to a minimum has a
    positive impact on overall steam cycle efficiency
    estimated to be 0.3
  • Reduced thermal excursions in the boiler due to
    sootblowing leading to a more stable boiler.
  • Better than 12 month payback on current costs.

23
QUESTIONS
Write a Comment
User Comments (0)
About PowerShow.com