Title: Loy Yang Power Station Control System Upgrade.
1Loy Yang Power Station Control System Upgrade.
BARRY DUNGEY General Manager Engineering
Maintenance June 2008
2Key Project Objectives
- Original control system is of mid 1970s design
with circuit board, relay and wire wrap
technology. - The main driver for the project is the difficulty
in supporting obsolete control equipment.( Our
policy is to run for approx 5 years following
withdrawal of support by our equipment supplier) - The opportunity is also being taken to gain
improvements in system performance and reduce
business risk exposure. - ( i.e. Alternative control room)
- Plant trip rates were increasing with a
significant number due to control system faults. - Upgrade will include the installation of a
separate plant safety system. - Complete unit cut over to be achieved in 35-40
day outage duration
3Number of Trips Trip Rate.
4Project Timeline
5Loy Yang Power Expectations
- The current control system is fairly tight as it
is already being run on a digital platform, hence
LYP are not expecting significant direct
improvements in efficiency as a result. (Some
studies indicate that up to 2 improvement is
possible from older systems) - The system will deliver flexibility to do things
smarter, fault find easier, and implement future
plant logic change easier. - The supplier has provided a guarantee that they
will support the new control system for 35 years,
hence no further significant upgrades are
expected in the remaining life of the plant.
6Yokogawa Site Observations
- Site surveys noted that the current control
strategies are sound. - Boiler thermocouple dynamic response suitably
fast to allow for quick movement in loads. - Existing spray valves and actuators not
significantly limiting performance - Existing controls have some issues when limits
are reached wind-up, excess output pull-back,
etc
7Benefits from Yokogawa control design
- Integration between steam temperature and
combustion controls minimises interaction - Over-firing minimised by using transient
contribution of superheater sprays to main steam
pressure control - Contributes to wider operating range from milling
plant - Boiler thermal stress reduced
- Flexibility on turbine ramp rates possible
- On line efficiency tools improved.
8Benefits (Continued)
- In summary, the current process is about
achieving incremental improvements, particularly
with - Start up and shutdown sequences
- Better trim controls associated with excess air
(oxygen). - Maximising future flexibility with an open system
which can accept third party products. - Improved Operator information and diagnostics
9Original Coal Handling Plant
10Coal Handling Plant (Part)
11Coal Handling Plant (Overview Screen)
12Major Plant Drive Graphic
13Future Control Room Layout
14Simulation For Engineering and Training
15Optimised Sootblowing
- Loy Yang Power has four superheater elements, 2
reheater elements and an economiser within each
furnace convection path. - To manage boiler fouling, 74 sootblowers are used
to clean the elements using high pressure steam
from the Reheat Steam System. - The original design used a time based operation
system with two cleaning cycles per day.
16Original Sootblower Control Panel
17Optimised Sootblowing - NGISB
- An optimised sootblowing system (NGISB - Next
Generation Intelligent Sootblowing System) has
been installed on one unit as a trial. It uses a
Synengco supplied NGISB system interfaced to PLC
based sootblower controls supplied by Siemens. - The NGISB gathers data from the plant historian
at near real time and continuously calculates the
ideal sootblower schedule using a thermal boiler
model within business rule constraints.
18Sootblower Optimisation System Aims
- Reduce sootblowing frequency
- Maintain boiler attemporator spray flows within
the ideal valve control range - Minimise Reheat Spray Flow
- Maintain Steam and Metal Temperatures close to
target and minimise alarm conditions to maximise
thermal efficiency. - Set and Forget operation.
19Siemens/Synengco Sootblower Control System
20Optimised Sootblowing Results
- Sootblowing frequency reduced to 32.5 of the
original time based schedule. - Annualised Savings per Unit
- 24.7 TJ of energy
- 8.1 Ml of Cold Reheat Steam
- 4,900 Tonnes of CO2
21(No Transcript)
22Optimised Sootblowing Results (Continued)
- Reducing RH Spray Flow to a minimum has a
positive impact on overall steam cycle efficiency
estimated to be 0.3 - Reduced thermal excursions in the boiler due to
sootblowing leading to a more stable boiler. - Better than 12 month payback on current costs.
23QUESTIONS