1
  • San Francisco Masjid Project

2
Historical Information
  • Raza obtained by children of Shehzada Abdul
    Taiyab Bhaisaheb Zakiuddin Saheb
  • They would
  • Oversee large part of architectural planning
  • Be directly involved in obtaining required
    permits
  • Give sizeable contribution to the masjid fund
  • Be involved in monitoring progress

3
Historical Information (continued)
  • Asaas laid in 1996
  • Site surveys have been done
  • Plans drawn and signed off
  • (Shehzada Malik-ul-Ashtar Bhaisaheb)
  • Architect is Zoher Bhaisaheb Vajhiuddin
  • Masjid Committee had been formed
  • Contribution commitments had been made
  • Collection of funds

4
City Visit
  • Plans had been submitted to city to obtain
    permission
  • Grandfather Clause - present day 2 acre minimum
  • Maximum built up allowance
  • Distinction made between Dawoodi Bohras and other
    Muslims - our local community
  • Existing complaints
  • Helpfulness of city

5
Current State
  • Changes in variance were suggested by city
  • Changes are being incorporated by Zoher Bhaisaheb
  • Blue prints
  • Elevation
  • Landscaping / Infrastructure

6
Next Step - City
  • Revisit city on Jan. 26th
  • Need letterhead with dates / times/ duration of
    all annual events
  • Permission for City Commission Hearing

7
Next Step - Jamaat
  • Formation of new Masjid Committee
  • Masjid Presentation to neighbors
  • 500 ft. radius - roughly 28 houses
  • Stressing
  • Renovation / Beautification / Landscaping
  • Increased Property Value for all
  • Maximum of 100 people usage
  • Preparation for City Commission Hearing

8
City Commission Hearing
  • 6 weeks after application in city
  • Panel includes
  • Local Business owners
  • Fremont Chair holders
  • Fire Department
  • Neighbors summoned and asked questions
  • Set time and date by city
  • No show - its a go!

9
Preparation for Construction
  • Obtain all appropriate building permits (6
    months)
  • Tests
  • Soils
  • Water Table
  • Secure Contractors / Subcontractors
  • Secure building materials
  • Construction!

10
How Can I Help?
  • Preparation for neighbor presentation
  • Door to door approach
  • Flyer / invitation creation
  • Coordination / set-up
  • Markaz set-up
  • Tables / chairs / equipment
  • Participation

11
How Can I Help? (continued)
  • Be enthusiastic / pro-active
  • Offer khidmat to Janab Aamil Saheb
  • Preparation for neighbor presentation
  • Contributions
  • Monetary
  • Dua
  • Tasbee
  • Physical

12
How Can I Help? (continued)
  • DO NOT answer questions you do not know answers
    to!
  • DRIVE SLOWER!
  • BE QUIET!

13
Pre-Construction Events
14
Timeline
15
General Masjid Facts
  • Approximately 8,000 square feet complex
  • Waqaf area roughly the size of existing markaz
  • Multi-purpose basement
  • Second story for Womens area
  • Syedna Abdeali Saifuddin Sahebs masjid pillars
  • One minara - accessible by stairs
  • 25 parking spaces
  • Handicapped access and parking

16
Closing
  • Updates will be given regularly as well as
    posted on website
  • Main focus for Masjid project is neighborhood
    presentation
  • Please respect our neighbors
  • Possible question/answer session with Janab Turab
    Bhaisaheb
  • Shabaab invitation to Aamir Bhaisaheb
  • Questions?